Case Narrative Sample Clauses

Case Narrative. Foundation Wall System The site of the dining hall sloped quite significantly from front to back, so it was necessary to level the area. The design called for the bottom floor to be level with the elevation at the back of the site and the top two floors to be built up when looking at the front of the site. This required that the whole site had to be excavated down to the depth at the back of the site. When working in the excavated area, there was a risk for those workers to be struck by falling objects or pieces of equipment. Benching the walls of the excavation site added an extra measure of safety and sharply decreased the likelihood of a cave-in or an instance of falling equipment. Caissons were chosen as the foundation for the dining hall due to the type of soil in the area as well as the precedent set by existing buildings constructed in the area. To help minimize the safety risks, workers were trained in the proper procedures for installing the deep foundation. A retaining wall was needed at the front of the building, as the back of the building was at grade while the front of the building was at the 2nd story. Cast-in-place concrete was chosen for the front wall of the building during the design development phase. This was chosen over masonry because of the reduced cost and speed of construction of this type of structure versus masonry. This was also safer for workers because it did not involve as many workers in an enclosed space or at heights during construction of the wall. One mechanism to allow for material laydown at the front of the site was to backfill the front retaining wall early so that the backfill was at grade at the front of the site. The original drawings from the structural engineer stated that the steel superstructure and floor of the first level needed to be braced before the wall could be backfilled. The CM asked for the structural engineer to determine what would be required to allow for the retaining wall to be backfilled before the steel was installed. The structural engineer stated that the retaining wall would have needed increased temporary bracing to allow the backfill to be completed before the 1st floor structure and floor were completed. This cost would have had to have been absorbed by the CM, as it would have been a change the owner would not have paid for. The CM said that once they got far enough along in the design they were able to determine that the front storage would not be required, and the extra cost of the t...
AutoNDA by SimpleDocs
Case Narrative. Haul Road A haul road was used to transport materials and equipment along the project corridor. The haul road to the site was limited in size to a single lane design due to the smaller construction footprint. Maintenance of the haul road over time was necessary in order to keep it open and accessible at all times during construction. During this phase, there was risk for workers to be struck, caught in, or compressed by equipment or objects. This was solved by the constructor implementing communication between workers and drivers as an administrative control. Using stone and grading allowed for the road surface to remain safe and prevent instances of slips, trips, or falls. Temporary Bridges Since the project corridor traversed wetlands and creeks, temporary bridges needed to be built to allow movement of equipment and materials. To ensure the safety of workers on the bridge, the CM needed to take measures to prevent falls or being struck by equipment or vehicles. Instead of delegating fall protection to the subs, the CM had temporary walls put up along the bridges to meet OSHA requirements for fall protection. The design width of the bridges eliminated the risk of workers being struck by equipment or vehicles, although signage, temporary barricades, and communication between workers and drivers were still utilized to ensure worker safety.
Case Narrative. Site Excavation When excavating the deep and wide area for the foundation and basement of the house, there was a cave-in hazard for workers. This was eliminated by the constructor’s decision to have the sides of the excavation benched.
Case Narrative. Site Excavation A basement was decided to be included in the site excavation. As both the designer and operation manager (OM) noted, the local market used to have one in typical residential houses. It is because of the area topography which lent itself to a basement since most lots have a slope. Also, the client also dictated this decision based on their needs. The DB team chose benching and sloping methods for site excavation. This type of method is simpler and costs less than other control methods that would require temporary shoring and bracing. The builder had worked with the same excavator for years (they tried to do this with all of their trade subcontractors because they felt it allows the subs to better understand their requirements), and typically gave them the depth and area of the excavation that was needed. The designer said that he had a pre-construction meeting on site with the excavator to discuss a grading plan, but the OM said that they like to rely on the subcontractor’s expertise. The OM said that they are basically paying for the time the "machine is on", but they gave the excavator latitude on the height of the bench, layback, and sloping because they trusted and preferred them to do what was required to safely perform the work. The builder’s policy is to over-excavate four feet past the wall lines to allow a sufficient setback for subs to work safely and efficiently in the area. This cost a little more on excavation, but allowed sufficient room for the forms to be safely maneuvered and eliminated cave-in hazard at the work face.
Case Narrative. Pre-cast Concrete Panel Design To match other buildings and for cost-saving purposes, pre-cast concrete panels were chosen for the outside façade of the building. The only other option explored was using pre-cast concrete panels to window sill height (±3’-6”) and then use cement plank siding on metal stud framing above the present height. For aesthetic reasons, the architect advocated against the siding option. The building design was configured with three enclosed outside courtyards. The courtyard walls were pre-cast concrete panels to match the exterior façade of the rest of the building. One difference between the interior courtyard design and the building exterior were larger windows on the exterior allowing more natural light in for patients without access to the courtyards. The diversity of window sizes affected the design solution by reducing panel standardization and resulting in additional panels of varying sizes and increased complexity in panel connections. The decision was made to have the pre-cast concrete panels manufactured to the full building height where possible in order to minimize the total number of deliveries and lifts required for installation. This was a scheduling decision, but it did also have an effect on safety since fewer deliveries and lifts mean fewer opportunities for incidents. Shear Wall Design The original building design included a shear wall design requiring shear panels to have a direct connection to the footing. Non-load bearing panels were designed to connect to a one foot high concrete stemwall. The CM and pre-cast panel subcontractor made a recommendation during the construction drawing phase to eliminate the stemwall and connect all panels to the foundation. This increased panel lengths by one foot and allowed elimination of the concrete stemwall. The PM said this eliminated remedial xxxx-hammering and sawing of the stemwall to vertically align all panels. The net effect is faster and safer construction. This decision was made primarily due to constructability and scheduling, and the CM said the original design could have been made to have direct footing connections. Pre-cast Panel Installation One of the key decisions that affected the panel installation was the logistics of the structural steel erection. It was decided by the CM to start installation at one building wing and work clockwise wing by wing. This plan allowed the panels to be installed simultaneously with the wing framing once the structural steel f...
Case Narrative. Federal and state governments gave a utility consent decree that wastewater system must be upgraded to meet certain capacity requirements due to reported overflows in the wastewater system. The utility responded to the consent decree and the response was accepted by the government. The accepted consent decree requires the utility to improve the wastewater system so that the overflows within the system are reduced to levels that meet regulatory requirements. Once the consent decree was accepted the utility was required to develop an engineering improvement plan with a list of projects to increase capacity and eliminate chronic overflow locations within the system. The utility used a flow model of the system to test different options and determine which list of projects increased capacity in the most effective way versus their respective cost. The projects were broken up into sewer basins, and each project is dependent on others (thus the projects must be evaluated as a whole). Public meetings were held for input, and a public committee was formed to give input into the process. Another part of the consent decree was a requirement to upgrade sewer treatment plants to meet anticipated peak flow volume based on system improvements and anticipated new connections to the system. The system evaluated the capacity needed at the WW plant based on worst case conditions, and developed a list of options to increase capacity to the required levels from the model. Nine alternatives were identified for the WWTP. Each of these potential improvement alternatives was first developed to a conceptual level. At the conceptual level the alternatives were screened to rule out those that were considered by the utility not to be feasible due to operational, site, or treatment constraints. Also as part of the screening analysis, each alternative was evaluated in terms of costs and non-monetary factors to determine if the alternative should be considered further for analysis. This was done by ranking the options 1-5. Next, the screened alternatives were developed further to generate preliminary design and flow diagrams, hydraulic profiles, plant layouts, and preliminary cost estimates. Table 4-9 shows the list of improvement projects required for each of the options that were further evaluated after screening. Cost estimates and preliminary design drawings were then developed for each of the options for further evaluation. Option 3 was chosen based on both cost and the ability to ef...

Related to Case Narrative

  • Narrative Commentary covering site improvements, circulation, organization of building space in relation to program requirements, building materials, special features, building systems (HVAC, plumbing, fire protection, structural, security, and video voice and data).

  • Management Report Promptly upon receipt thereof, copies of all detailed financial and management reports submitted to Borrower or any other Loan Party by independent auditors in connection with each annual or interim audit made by such auditors of the books of Borrower or any other Loan Party.

  • Annual Compliance Statements (a) The Master Servicers, the Special Servicers, the Certificate Administrator, the Trustee (but only to the extent set forth in the last sentence of this paragraph), any Additional Servicer and each Servicing Function Participant (if such Servicing Function Participant is a servicer contemplated by Item 1108(a)(2)(i), (ii) or (iii) of Regulation AB) (each, a “Certifying Servicer”) shall and the Master Servicers and the Special Servicers shall (i) with respect to any Additional Servicer or Servicing Function Participant (if such Servicing Function Participant is a servicer contemplated by Item 1108(a)(2)(i), (ii) or (iii) of Regulation AB) that is a Designated Sub-Servicer of such party, use commercially reasonable efforts to cause, and (ii) with respect to any other Additional Servicer or Servicing Function Participant (if such Servicing Function Participant is a servicer contemplated by Item 1108(a)(2)(i), (ii) or (iii) of Regulation AB), cause, each Additional Servicer and Servicing Function Participant (other than any party to this Agreement) with which it has entered into a servicing relationship with respect to the Mortgage Loans to, deliver to the Depositor, the Certificate Administrator, the Trust Advisor (in the case of a Special Servicer only), the Rule 17g-5 Information Provider (who shall promptly post such report to the Rule 17g-5 Information Provider’s Website pursuant to Section 8.12(c) of this Agreement) on or before March 1st (subject to a grace period through March 15th) of each year, commencing in 2015 (or, in the case of an Additional Servicer or Servicing Function Participant with respect to a Special Servicer, such party shall provide such Officer’s Certificate to such Special Servicer on or before March 1st (subject to a grace period through March 5th)), an Officer’s Certificate stating, as to the signer thereof, that (A) a review of such Certifying Servicer’s activities during the preceding calendar year or portion thereof and of such Certifying Servicer’s performance under this Agreement, or the applicable sub-servicing agreement or primary servicing agreement in the case of an Additional Servicer, has been made under such officer’s supervision and (B) to the best of such officer’s knowledge, based on such review, such Certifying Servicer has fulfilled all its obligations under this Agreement, or the applicable sub-servicing agreement or primary servicing agreement in the case of an Additional Servicer, in all material respects throughout such year or portion thereof, or, if there has been a failure to fulfill any such obligation in any material respect, specifying each such failure known to such officer and the nature and status thereof. The Certificate Administrator, shall prior to March 1st of each year, commencing in 2015, contact the Trustee and inquire as to whether any Advance was required to be made by the Trustee during the preceding calendar year, and if no such Advance was required to be made by the Trustee, then the Trustee shall not be required to deliver any compliance statement required by this Section 11.12(a) for such period.

  • Compliance Statement Within 30 days after the last day of each month and together with the statements set forth in Section 5.3(c), a duly completed Compliance Statement, confirming that as of the end of such month, Borrower was in full compliance with all of the terms and conditions of this Agreement, and setting forth calculations showing compliance with the financial covenants set forth in this Agreement and such other information as Bank may reasonably request;

  • Problem Statement School bus fleets are aging, and our communities have poor air quality. Replacing school buses with zero emission school buses will address both of these issues.

  • Production Report and Lease Operating Statements Within 60 days after the end of each fiscal quarter, a report setting forth, for each calendar month during the then current fiscal year to date, the volume of production and sales attributable to production (and the prices at which such sales were made and the revenues derived from such sales) for each such calendar month from the Oil and Gas Properties, and setting forth the related ad valorem, severance and production taxes and lease operating expenses attributable thereto and incurred for each such calendar month.

  • Servicer Compliance Statement On or before March 1 of each calendar year, commencing in 2007, the Servicer shall deliver to the Owner and any Depositor a statement of compliance addressed to the Owner and such Depositor and signed by an authorized officer of the Servicer, to the effect that (i) a review of the Servicer’s activities during the immediately preceding calendar year (or applicable portion thereof) and of its performance under this Agreement and any applicable Reconstitution Agreement during such period has been made under such officer’s supervision, and (ii) to the best of such officers’ knowledge, based on such review, the Servicer has fulfilled all of its obligations under this Agreement and any applicable Reconstitution Agreement in all material respects throughout such calendar year (or applicable portion thereof) or, if there has been a failure to fulfill any such obligation in any material respect, specifically identifying each such failure known to such officer and the nature and the status thereof.

  • Stability Testing Patheon may be requested to conduct stability testing on the Products in accordance with the protocols set out in the Specifications for the separate fees and during the time periods set out in Schedule C to a Product Agreement. Patheon will not make any changes to these testing protocols without prior written approval from Client. If a confirmed stability test failure occurs, Patheon will notify Client within one Business Day, after which Patheon and Client will jointly determine the proceedings and methods to be undertaken to investigate the cause of the failure, including which party will bear the cost of the investigation. Patheon will not be liable for these costs unless it has failed to perform the Manufacturing Services in accordance with the Specifications, cGMPs, and Applicable Laws. Patheon will give Client ail stability test data and results at Client’s request.

  • Background and Narrative of Budget Reductions 2. Assumptions Used in the Deficit Reduction Plan: - EBF and Estimated New Tier Funding: - Equal Assessed Valuation and Tax Rates: - Employee Salaries and Benefits: - Short and Long Term Borrowing: - Educational Impact: - Other Assumptions: - Has the district considered shared services or outsourcing (Ex: Transportation, Insurance) If yes please explain: ESTIMATED LIMITATION OF ADMINISTRATIVE COSTS (School Districts Only) (For Local Use Only)

  • Management Reporting (a) Provide periodic reports, in accordance with agreed upon frequency and content parameters, to the Funds. As reasonably requested by the Funds, the Transfer Agent shall furnish ad hoc reports to the Funds.

Time is Money Join Law Insider Premium to draft better contracts faster.