Punch List definition

Punch List means the list of items, prepared in connection with the inspection of the Project by the Owner’s Representative or Architect in connection with Substantial Completion of the Work or a portion of the Work, which the Owner’s Representative or Architect has designated as remaining to be performed, completed or corrected before the Work will be accepted by the Owner.
Punch List signed by the County;
Punch List means a list developed by the Project Manager after Substantial Completion that identifies defects or deficient workmanship or work not completed in conformance with the Contract Documents.

Examples of Punch List in a sentence

  • Upon completion of all Punch List items, the Independent Engineer shall issue the Completion Certificate.

  • Failure of the Concessionaire to complete all the Punch List items within the time set forth in Clause 14.4.(a) for any reason, other than conditions constituting Force Majeure or for reasons solely attributable to the Authority, shall entitle the Authority to terminate this Agreement.

  • All items in the Punch List shall be completed by the Concessionaire within 90 (ninety) days of the date of issue of the Provisional Certificate and for any delay thereafter, other than for reasons solely attributable to the Authority or due to Force Majeure, the Authority shall be entitled to recover Damages from the Concessionaire to be calculated and paid for each day of delay until all items are completed 0.1% (zero point one per cent) of the Performance Security.

  • Subject to payment of such Damages, the Concessionaire shall be entitled to a further period not exceeding 120 (one hundred and twenty) days for completion of the Punch List items.

  • CMAR, in conjunction with the Inspector, Consultant and Project Manager, shall prepare and submit to the CITY a comprehensive Punch List of items to be completed or corrected prior to Final Acceptance and Final Payment.


More Definitions of Punch List

Punch List means a list of items of Work to be completed or corrected by Contractor before Final Completion, and indicates items to be finished, remaining Work to be performed, or Work that does not meet quality or quantity requirements as required in the Contract Documents.
Punch List are those minor items of Work identified and listed by DP and agreed to by Owner to be completed by Contractor after Substantial Completion and prior to Final Completion, which do not prevent the Project from being fully used for the purpose for which it is intended and which will not prevent the issuance of a certificate of occupancy.
Punch List shall have the meaning assigned to it under Article 6.7 (d).
Punch List. A list of minor construction Project items to be completed or corrected by the Construction Contractor, any one of which do not materially impair the use of the Project work, or the portion of the Project work inspected, for its intended purpose. A Punch List shall be prepared by the Professional upon having made a determination that the Project work, or a portion of the Project construction work inspected, in concert with the Professional, the Construction Contractor, the Department, Project Director, the Field Representative, the State/Client Agency and any construction manager, is substantially complete and shall be attached to the respective DMB-455, Certificate of Substantial Completion form. This standard document form is a part of the “DMB- 460, Project Procedures” documents package.
Punch List shall have the meaning as set forth in Clause 12.2.1;
Punch List or “Punch List work” means minor adjustments, repairs or deficiencies in the Work, as determined by the Commissioner in his sole discretion.
Punch List means the list generated by Contractor and approved by Owner Parties of incomplete or Defective Work that must be corrected before the Project achieves Final Completion.