Recovery Plans Sample Clauses

Recovery Plans. In the event of any schedule delays in respect of construction milestones or the substantial completion date, Purchaser shall be advised of (as applicable) any recovery plans and shall be invited to attend meetings between Seller and its suppliers and contractors in respect thereof; provided, however, neither Seller, its suppliers nor its contractors shall be obligated to implement any recommendations of Purchaser in respect of any such recovery plans.
AutoNDA by SimpleDocs
Recovery Plans. For as long as Services are provided hereunder, PICO shall, and shall cause its relevant Affiliates to, maintain backup, business continuation and disaster recovery plans, procedures and policies (collectively, “Recovery Plans”) consistent with past practices as they existed during the twelve (12) months immediately preceding the Offering. PICO shall provide UCP:
Recovery Plans. If the Monthly Progress Report shows that the Substantial Completion is projected to occur ninety (90) days later than the then-current Guaranteed Substantial Completion Date, Contractor will submit a written schedule recovery plan for Concessionaire’s Review concurrent with the next monthly Project Schedule update. Such recovery schedule shall (i) include a list of all activities changed, added or deleted along with all logic changes and an accompanying narrative explaining the nature of the changes as required by Section 1.4.6(A) of the Technical Requirements and (ii) set forth a revised Project Schedule that shall be subject to Concessionaire’s Approval for which projected Substantial Completion shall not, subject to Section 6.6.5, be later than 365 days after the Guaranteed Substantial Completion Date. Contractor shall respond to Concessionaire’s comments in accordance with the process outlined in Section 2.1.1.2 until Concessionaire and the Department have approved the revised Project Schedule. Concessionaire’s Review of a recovery plan and Concessionaire’s Approval of a revised Project Schedule shall not affect any of Concessionaire’s rights or Contractor’s obligations under this Agreement, including Contractor’s obligations to pay Late Completion Payments. Once a revised Project Schedule is reviewed and approved by Concessionaire hereunder and the Department under the Comprehensive Agreement, it shall become the Project Schedule and be used as the basis for subsequent Monthly Progress Reports.
Recovery Plans. The Guaranteed Maximum Price is based on Contractor working as many hours as necessary to properly perform the Work and achieve the Project Schedule requirements. In the event it is necessary for Contractor or any Subcontractor to work additional overtime in order to maintain the Project Schedule, Contractor shall be responsible for all costs relating to such overtime, though Contractor shall have the right to use the Construction Contingency in accordance with Section 3.1.5 hereof. “Recovery Plan” means a detailed narrative explanation clearly stating the scope and extent of any and all resource loading, activity re-sequencing and other acceleration activities required for all affected elements of the Work to enable Contractor to either: (a) complete the respective Interim Milestones by the respective Interim Milestone Dates; or (b) obtain Substantial Completion of the Work in its entirety within the Contract Time.
Recovery Plans. The Guaranteed Maximum Price is based on Contractor working as many hours as necessary to properly perform the Work and achieve the Project Schedule requirements. “Recovery Plan” means a detailed narrative explanation clearly stating the scope and extent of any and all resource loading, activity re-sequencing and other acceleration activities required for all affected elements of the Work to enable Contractor to either: (a) complete the respective Interim Milestones by the respective Interim Milestone Dates; or (b) obtain Substantial Completion within the Contract Time.
Recovery Plans. If progress of the Redevelopment Work falls materially behind schedule and the Chief Real Estate Officer reasonably determines that Lessee is in jeopardy of not achieving the CO Date on or before the Required Construction Completion Date, then County may issue a written notice (each a “Recovery Plan Notice”) to Lessee identifying areas of concern and requiring that Lessee provide a Recovery Plan detailing the measures to be implemented by Lessee in order to recover any lost time in the Construction Schedule. Lessee shall, within fifteen (15) days after receipt of a Recovery Plan Notice, provide a Recovery Plan to County. Within thirty (30) days after County’s receipt of a Recovery Plan from Lessee, County shall instruct Lessee in writing whether or not to proceed with the Recovery Plan as submitted, or in accordance with reasonable revisions thereto required by County (a “Construction Change Directive”). Upon Lessee’s receipt of the Construction Change Directive, Lessee shall instruct its contractors to implement the Recovery Plan as soon as reasonably possible and any additional costs associated with implementation of the Recovery Plan shall be borne by Lessee. Lessee’s failure (a) to provide a Recovery Plan within the time requirements provided for in this Subsection 5.7.3, or (b) to implement immediately a Recovery Plan upon receipt of a Construction Change Directive to do so, shall each be a material breach of this Agreement.‌
Recovery Plans. (11) 23BIn the event of a Disaster, establish and maintain connectivity for County Locations, from Supplier sites to County Locations, and between County Locations to deliver the Services in accordance with the County’s Disaster Recovery Plans.
AutoNDA by SimpleDocs
Recovery Plans. The Original Project Guaranteed Maximum Price or Expansion Project Guaranteed Maximum Price (as applicable) is based on Contractor working as many hours as necessary to properly perform the Work and achieve the Original Project Schedule and Expansion Project Schedule requirements. “Recovery Plan” means a detailed narrative explanation clearly stating the scope and extent of any and all resource loading, activity re-sequencing and other acceleration activities required for all affected elements of the Work to enable Contractor to either: (a) complete the respective Original Project Interim Milestones or Expansion Project Interim Milestones by the respective Original Project Interim Milestone Dates or Expansion Project Interim Milestone Dates; or (b) obtain Original Project Substantial Completion or Expansion Project Substantial Completion (as applicable) within the applicable Contract Time.

Related to Recovery Plans

  • Disaster Recovery Plan Contractor agrees that upon request of System Agency, Contractor shall provide copies of its most recent business continuity and disaster recovery plans.

  • Development Plans 4.3.1 For each Licensed Indication and corresponding Licensed Product in the Field, Licensee will prepare and deliver to Licensor a development plan and budget (each a “Development Plan”). The initial Development Plans for each Licensed Indication will be delivered within […***…] after the Grant Date for such Licensed Indication.

  • Project Plans The Contractor: must carry out the Contractor's Activities in accordance with, and otherwise implement, the Project Plans; and for the purposes of subparagraph (i), must: prepare Project Plans based, where applicable, on the draft Project Plans lodged by the Contractor in its tender for the Contractor's Activities, and otherwise in accordance with the requirements of the Contract and submit them to the Contract Administrator so as to ensure that there is no delay or disruption to the Contractor's Activities and in any event no later than the number of days specified in the Contract Particulars after the Award Date for each Project Plan; not commence any of the Contractor's Activities to which any Project Plan applies, unless the Contract Administrator has had the number of days specified in the Contract Particulars for each Project Plan to review the Project Plan and has not rejected the Project Plan; if any Project Plan is rejected, submit an amended Project Plan to the Contract Administrator; in any event, finalise each Project Plan so as to ensure that there is no delay or disruption to the Contractor's Activities and in any event in accordance with the requirements of the Contract to the satisfaction of the Contract Administrator; after each Project Plan has been finalised: regularly review, update and amend each Project Plan in accordance with the process set out in each Project Plan (and otherwise at least on each anniversary of the Award Date); update or amend a Project Plan on request of the Contract Administrator; and continue to correct any defects in or omissions from a Project Plan (whether identified by the Contract Administrator or the Contractor), and submit an updated or amended Project Plan to the Contract Administrator, after which: the Contractor must continue to comply with the requirements of the then current Project Plan until the process in subparagraph (ii) has been completed in respect of the updated or amended Project Plan; and subsubparagraphs B - E will apply (to the extent applicable); and document and maintain detailed records of all: reviews, updates, amendments and submissions of each Project Plan; audits or other monitoring of each Project Plan; and training and awareness programs and communications provided to Contractor and subcontractor personnel in respect of each Project Plan (including each updated or amended Project Plan). The Contractor will not be relieved from compliance with any of its obligations under the Contract or otherwise at law or in equity as a result of: the implementation of, and compliance with, the requirements of any Project Plan; any direction by the Contract Administrator concerning a Project Plan or the Contractor's compliance or non-compliance with a Project Plan; any audit or other monitoring by the Contract Administrator or anyone else acting on behalf of the Commonwealth of the Contractor's compliance with a Project Plan; or any failure by the Contract Administrator, or anyone else acting on behalf of the Commonwealth, to detect any defect in or omission from a Project Plan including where any such failure arises from any negligence on the part of the Contract Administrator or other person.

  • Work Plans Tenant shall prepare and submit to Landlord for approval schematics covering the Tenant Improvements prepared in conformity with the applicable provisions of this Work Letter (the “Draft Schematic Plans”). The Draft Schematic Plans shall contain sufficient information and detail to accurately describe the proposed design to Landlord and such other information as Landlord may reasonably request. Landlord shall notify Tenant in writing within ten (10) business days after receipt of the Draft Schematic Plans whether Landlord approves or objects to the Draft Schematic Plans and of the manner, if any, in which the Draft Schematic Plans are unacceptable. Landlord’s failure to respond within such ten (10) business day period shall be deemed approval by Landlord. If Landlord reasonably objects to the Draft Schematic Plans, then Tenant shall revise the Draft Schematic Plans and cause Landlord’s objections to be remedied in the revised Draft Schematic Plans. Tenant shall then resubmit the revised Draft Schematic Plans to Landlord for approval, such approval not to be unreasonably withheld, conditioned or delayed. Landlord’s approval of or objection to revised Draft Schematic Plans and Tenant’s correction of the same shall be in accordance with this Section until Landlord has approved the Draft Schematic Plans in writing or been deemed to have approved them. The iteration of the Draft Schematic Plans that is approved or deemed approved by Landlord without objection shall be referred to herein as the “Approved Schematic Plans.”

  • Marketing Plans Contractor and the Exchange recognize that Enrollees and other health care consumers benefit from efforts relating to outreach activities designed to increase heath awareness and encourage enrollment. The parties shall share marketing plans on an annual basis and with respect to periodic updates of material changes. The marketing plans of the Exchange and Contractor shall include proposed and actual marketing approaches, messaging and channels and provide samples of any planned marketing materials and related collateral as well as planned, and when completed, expenses for the marketing budget. The Contractor shall include this information for both the Exchange and the outside individual market. The Exchange shall treat all marketing information provided under this Section as confidential information consistent with Section 1.4.1. The obligation of the Exchange to maintain confidentiality of this information shall survive termination or expiration of this Agreement.

  • Improvement Plans A. A professional improvement plan is a clearly articulated assistance program for a teacher whose student growth measure dimension of the evaluation is below the expected level of student growth. For the purposes of this agreement, improvement plans shall be based on the individual student growth measure level, and not for overall subjects or classes taught.

  • Recovery Schedule If the initial schedule or any current updates fail to reflect the Work’s actual plan or method of operation, or a contractual milestone date is more than fifteen (15) days behind, Owner may require that a recovery schedule for completion of the remaining Work be submitted. The Recovery Schedule must be submitted within seven (7) calendar days of Owner’s request. The Recovery Schedule shall describe in detail Construction Contractor’s plan to complete the remaining Work by the required Contract milestone date. The Recovery Schedule submitted shall meet the same requirements as the original Construction Schedule. The narrative submitted with the Recovery Schedule should describe in detail all changes that have been made to meet the Contract milestone dates.

  • Disaster Recovery and Business Continuity The Parties shall comply with the provisions of Schedule 5 (Disaster Recovery and Business Continuity).

  • Payment Plans Employees covered by the Samaritan Choice medical insurance plan who have outstanding balances that are payable to Samaritan Health Services for in network, covered, and authorized (if medically necessary) services will be provided payment plan offerings upon request from the employee. The request will be made to Patient Financial Services, and may be directed through the Hospital Patient Financial Counselor. Patient Financial Services will work with employees to identify the appropriate payment arrangement based on the employee financial needs/eligibility. Within 120 days from first patient statement, employees must contact Patient Financial Services and identify themselves as a SHS SEIU member and ask for a payment plan arrangement that does not exceed six percent (6%) of their household income. Such requests will be granted using the existing SHS payment options and funding programs. To be eligible for a payment plan, employees must comply with all requirements for establishing appropriate payment options/eligibility, including the completion of a financial assistance application with supporting documentation. Employees who comply with all terms of the payment plan(s) will not be subject to collections or wage garnishment.

  • Safety Plan Developer’s safety plan specifically adapted for the Project. Developer's Safety Plan shall comply with all provisions regarding Project safety, including all applicable provisions in these Construction Provisions.