Project Schedule. Construction must begin within 30 days of the date set forth in Appendix A, Page 2, for the start of construction, or this Agreement may become null and void, at the sole discretion of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame.
Project Schedule. The Project, for which the provision of financial assistance is the subject of this Agreement, shall be pursued and completed in accordance with the following schedule: ACTIVITY START DATE COMPLETION DATE Final Design 01/01/2012 01/30/2012 Bidding Process 05/01/2012 08/01/2012 Construction 08/15/2012 08/15/2013 NOTE: Construction must begin within 30 days of the date set forth herein for the start of construction, or this Agreement may become null and void, at the sole option of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame. The information detailed in this Appendix A shall serve as the basis for Project monitoring purposes and for determining Project acceptance upon its completion. In the event that circumstances require a change in physical scope, such changes must be approved through the execution of a formal Amendment to this Project Agreement. APPENDIX B
Project Schedule. The Project, for which the provision of financial assistance is the subject of this Agreement, shall be pursued and completed in accordance with the following schedule: ACTIVITY START DATE COMPLETION DATE a) Plan Dates 07/01/2015 11/01/2015 b) Acquisition Dates c) Site Improvement Dates 11/01/2015 06/30/2016 NOTE: Land acquisition and site improvements must begin within 30 days of the date(s) set forth herein for the start of land acquisition and site improvements, or this Agreement may become null and void, at the sole option of the Director. However, the Recipient may apply to the Director in writing for any extensions of these dates. The Recipient shall specify the reasons for the delay in the start of these activities and provide the Director with a new set of dates. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame. The information detailed in this Appendix A shall serve as the basis for Project monitoring purposes and for determining Project acceptance upon its completion. In the event that circumstances require a change in physical scope, such changes must be approved through the execution of an amendment to this Project Agreement. APPENDIX B
Project Schedule. The Project, for which the provision of financial assistance is the subject of this Agreement, shall be pursued and completed in accordance with the following schedule: ACTIVITY START DATE COMPLETION DATE Final Design 10/01/2015 03/31/2016 Bidding Process 05/15/2016 07/15/2016 Construction 08/01/2016 10/31/2016 Construction must begin within 30 days of the date set forth herein for the start of construction, or this Agreement may become null and void, at the sole option of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame. The information detailed in this Appendix A shall serve as the basis for Project monitoring purposes and for determining Project acceptance upon its completion. In the event that circumstances require a change in physical scope, such changes must be approved through the execution of a formal Amendment to this Project Agreement. APPENDIX B PROJECT ADMINISTRATION DESIGNATION The Project Administration Designation required by Section VI.A. of this Agreement, and in accordance with the definitions set forth in Section I of this Agreement, for the sole purpose of administering the Project, as defined and described in Appendix A of this Agreement, under Chapter 164 of the Revised Code and Chapter 164-1 of the Administrative Code is hereby established as follows:
Project Schedule. The Project, for which the provision of financial assistance is the subject of this Agreement, shall be pursued and completed in accordance with the following schedule: ACTIVITY START DATE COMPLETION DATE Final Design 01/01/2016 03/01/2016 Bidding Process 05/01/2016 07/31/2016 Construction 09/01/2016 09/01/2017 Construction must begin within 30 days of the date set forth herein for the start of construction, or this Agreement may become null and void, at the sole option of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame. The information detailed in this Appendix A shall serve as the basis for Project monitoring purposes and for determining Project acceptance upon its completion. In the event that circumstances require a change in physical scope, such changes must be approved through the execution of a formal Amendment to this Project Agreement. APPENDIX B PROJECT ADMINISTRATION DESIGNATION The Project Administration Designation required by Section VI. A. of this Agreement, and in accordance with the definitions set forth in Section I of this Agreement, for the sole purpose of administering the Project, as defined and described in Appendix A of this Agreement, under Chapter 164 of the Revised Code and Chapter 164-1 of the Administrative Code is hereby established as follows: The Recipient designates:
Project Schedule. Construction of the Project must begin within one year of the Effective Date of this Agreement, or this Agreement may become null and void at the sole discretion of the Director. A preliminary construction schedule is provided in Appendix A. Delays, with reason for the delay(s), must be communicated to the Director as soon as possible. The Director will review written requests for extensions and may extend the construction start date, providing that the Project can be completed within a reasonable time frame.
Project Schedule. The Project, for which the provision of financial assistance is the subject of this Agreement, shall be pursued and completed in accordance with the following schedule: ACTIVITY START DATE COMPLETION DATE Final Design 09/01/2016 12/31/2016 Bidding Process 05/01/2017 07/10/2017 Construction 08/01/2017 03/01/2018 Construction must begin within 30 days of the date set forth herein for the start of construction, or this Agreement may become null and void, at the sole option of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame. The information detailed in this Appendix A shall serve as the basis for Project monitoring purposes and for determining Project acceptance upon its completion. In the event that circumstances require a change in physical scope, such changes must be approved through the execution of a formal Amendment to this Project Agreement. APPENDIX B
Project Schedule. Attached to this Amendment will be a schedule identifying the above noted completion times and intermediate milestone dates estimated for the Project. The proposed schedule shall be integrated into the Construction Manager's CPM Schedule upon approval of its Guaranteed Maximum Price Amendment.
Project Schedule. The Project, for which the provision of financial assistance is the subject of this Agreement, shall be pursued and completed in accordance with the following schedule: ACTIVITY START DATE COMPLETION DATE Final Design 06/01/2014 10/01/2014 Bidding Process 11/01/2014 11/20/2014 Construction 04/01/2015 08/30/2015 NOTE: Construction must begin within 30 days of the date set forth herein for the start of construction, or this Agreement may become null and void, at the sole option of the Administrator. However, the Recipient may apply to the Administrator in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Administrator with a new start of construction date. The Administrator will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame. The information detailed in this Appendix A shall serve as the basis for Project monitoring purposes and for determining Project acceptance upon its completion. In the event that circumstances require a change in physical scope, such changes must be approved through the execution of a formal Amendment to this Project Agreement. APPENDIX B
Project Schedule. The Project, for which the provision of financial assistance is the subject of this Agreement, shall be pursued and completed in accordance with the following schedule: ACTIVITY START DATE COMPLETION DATE Final Design 09/01/2013 12/15/2013 Bidding Process 06/06/2014 07/01/2014 Construction 07/15/2014 07/15/2015 NOTE: Construction must begin within 30 days of the date set forth herein for the start of construction, or this Agreement may become null and void, at the sole option of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame. The information detailed in this Appendix A shall serve as the basis for Project monitoring purposes and for determining Project acceptance upon its completion. In the event that circumstances require a change in physical scope, such changes must be approved through the execution of a formal Amendment to this Project Agreement. APPENDIX B