Guaranteed Substantial Completion Date Sample Clauses

Guaranteed Substantial Completion Date. Contractor shall achieve Substantial Completion no later than the date specified in Attachment E (“Guaranteed Substantial Completion Date”). The Guaranteed Substantial Completion Date shall only be adjusted by Change Order as provided under this Agreement.
AutoNDA by SimpleDocs
Guaranteed Substantial Completion Date. Contractor shall achieve Substantial Completion of the Work no later than Two Hundred Forty Eight (248) Days after issuance of NTP (“Guaranteed Substantial Completion Date”). The Guaranteed Substantial Completion Date shall only be adjusted by Change Order as provided under this Agreement.
Guaranteed Substantial Completion Date. Contractor shall achieve Substantial Completion of Project 3 no later than the date specified in Attachment 5 (“Guaranteed Substantial Completion Date”). The Guaranteed Substantial Completion Date shall only be adjusted by Change Order as provided under this Agreement.
Guaranteed Substantial Completion Date. Except as provided herein, the EPC Contractor shall achieve Substantial Completion of the Work not later than the Substantial Completion Date, as set forth in the Project Schedule. The Substantial Completion Date shall not be extended unless agreed to by written Project Change Order signed by Client and EPC Contractor. Time is of the essence with respect to the EPC Contractor’s obligations hereunder, including without limitation the EPC Contractor’s obligation to achieve Substantial Completion prior to the Substantial Completion Date as set forth in the Project Schedule.
Guaranteed Substantial Completion Date. Contractor shall achieve Substantial Completion no later than *** (“Guaranteed Substantial Completion Date”). The Guaranteed Substantial Completion Date shall only be adjusted by Change Order as provided under this Agreement.
Guaranteed Substantial Completion Date. Contractor shall achieve Substantial Completion of Subproject 5 no later than the date specified in Attachment E (“Guaranteed Substantial Completion Date”). The Guaranteed Substantial Completion Date shall only be adjusted by Change Order as provided under this Agreement.
Guaranteed Substantial Completion Date. Contractor guarantees that it shall achieve Substantial Completion no later than ninety (90) days following the Customer Signing Date, as adjusted pursuant to this Article 4 or as a result of Force Majeure Events, Host Customer delays, Sunrun delays or Utility or Governmental Authority delays (“Guaranteed Substantial Completion Date”). The Guaranteed Substantial Completion Date may only be adjusted as provided in this Contract or by mutual agreement of the Parties.
AutoNDA by SimpleDocs
Guaranteed Substantial Completion Date. Contractor shall achieve Substantial Completion of the Work no later than twenty-nine (29) Days after achieving Mechanical Completion (“Guaranteed Substantial Completion Date”). The Guaranteed Substantial Completion Date shall only be adjusted by Change Order as provided under this Agreement.
Guaranteed Substantial Completion Date. Contractor guarantees that Substantial Completion of each of the Systems will occur on or before the “Guaranteed Substantial Completion Date” for each System. The Guaranteed Substantial Completion Date for each FGD System at each Facility shall be the date that is ninety (90) days after date on which such System achieves Provisional Acceptance.
Guaranteed Substantial Completion Date. The date which is 555 days after the Starting Date, subject to extension in accordance with the terms of this Agreement, by which date Contractor has committed to achieve Substantial Completion.