Pre-commissioning Sample Clauses

Pre-commissioning. The state when the plant/ unit/ system have been erected in accordance with the drawings, specifications, instructions and applicable codes and regulations; all other specific contractual construction activities are completed with respect to the plant/ unit/ system including compliance of check list and all the relevant technical documents are handed over to NRDA. Pretests/ Dry tests for the installed units are completed and certified by the OEM/channel partner. The Plant/ Unit/ system is considered ready for pre-commissioning when all the construction activities (including but not limited to the activities mentioned under “mechanical completion”) are completed, all the check list points are attended and all the relevant technical documents like alignment record/ test reports/ fabrication drawings etc. are handed over to the NRDA. However, with prior agreement with NRDA, construction may continue completion of check list points including residual area grading, paving, clean up, removal of temporary construction facilities, painting, insulation and correction of miscellaneous errors or omissions etc. that do not interfere with pre-commissioning activities. Pre-commissioning activities are operational activities performed in order to make the plant/ unit/ system ready for commissioning.
AutoNDA by SimpleDocs
Pre-commissioning. On completion the installation of all pumps, piping, valves, pipe connections, electrical wiring, motor control panels and water level controlling devices the Concessionaire shall proceed as follows: Testing of M.C.C.:
Pre-commissioning. PathNet shall install an Initial System in such a way that it can be operated and tested without interfering with Texaco's existing system performance. PathNet shall have all equipment in place to allow for a cutover by Texaco of its existing channels. Texaco and PathNet shall mutually agree upon a pre-commission plan and approve it in writing. This System is deemed Pre-Commissioned when fully operational.
Pre-commissioning. Functional verification of Facility utility and auxiliary systems, including electrical power, control systems, firewater, fuel gas system and utilities necessary to support the Units during and after commissioning and reinstatement of Equipment components; preparation of Equipment for commissioning, start-up and testing;
Pre-commissioning. TANK CONTRACTOR shall provide all labor, supervision, materials, including required spare parts, equipment and consumables and each and every item required to safely and effectively pre-commission the Phase 2 Tanks. TANK CONTRACTOR is to use this paragraph as a guide to be incorporated into his procedure to be approved by PURCHASER. No later than twelve (12) months before TANK CONTRACTOR is ready for pre-commissioning activities, it shall submit for PURCHASER’s approval, a Pre-commissioning Schedule and Execution Plan, outlining as a minimum the following: • Detailed logic network diagram and bar charts to show the sequence of Work and manpower requirements, including without limitation the following activities, materials and equipment required, and the requirements for interaction with others. • Material, including spare parts, and consumable checklists indicating purchase dates and deliveries. • Equipment checklists including requisitions and expected deliveries. • Recommended De-Commissioning Procedure. Pre-commissioning activities shall include but not be limited to:
Pre-commissioning. 1411 In addition to the tasks defined for pre-commissioning in Section 3, it is also recommended that extensive 1412 quality control checks be completed on all installed components. Pre-commissioning should also include 1413 weight-withhold and vibration tests to ensure mechanical robustness similar to those carried out according to 1414 IEC 61959, Secondary cells and batteries containing alkaline or other non-acid electrolytes - Mechanical tests 1415 for sealed portable secondary cells and batteries. 1416 During pre-commissioning the electrical interconnection to the grid from the Flow Battery should be checked 1417 that the interconnection conforms to the applicable IEEE standard(s) before proceeding to commissioning.
Pre-commissioning. A. Contractor will perform pre-commissioning services. This shall include as a minimum:
AutoNDA by SimpleDocs
Pre-commissioning. A. Pre-Commissioning – In Contractor fabrication facility, Contractor’s technician shall perform all firmware updates and validate signal switching and routing, IP addressing, and serial communications of all equipment with all transmitters and receivers connected to the system PRIOR to the 1st load of control code.

Related to Pre-commissioning

  • Commissioning Commissioning tests of the Interconnection Member’s installed equipment shall be performed pursuant to applicable codes and standards. The Cooperative must be given at least five Business Days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.

  • Decommissioning The expenditure for Decommissioning will be estimated on the basis of technical studies undertaken by the Contractor, to be agreed by the National Petroleum Agency, as part of each Field Development Program and revised as necessary.

  • Synchronization, Commissioning and Commercial Operation 4.1.1 The Power Producer shall give at least thirty (30) days written notice to the SLDC and GUVNL, of the date on which it intends to synchronize the Power Project to the Grid System.

  • Pre-Commencement Phase Services The services required to be provided by the Contractor for the Pre- Commencement Phase of the Project in accordance with the Contract Documents.

  • PRE-COMMENCEMENT PHASE Part 1 - Pre-commencement Phase Services Part 2 - Construction Documents and Site Plan SECTION 3 – CONSTRUCTION PHASE Part 1 - Construction Phase Services Part 2 - Changes to the Work Part 3 - Time. Part 4 - Correcting the Work, Inspections, Covering and Uncovering Work Part 5 - Subcontractors, Trade Contractors, and Suppliers

  • Project Completion The Project and the Work are complete.

  • De-commissioning due to Emergency 17.6.1 If, in the reasonable opinion of the Concessionaire, there exists an Emergency which warrants de-commissioning and closure of the whole or any part of the Bus Terminal, the Concessionaire shall be entitled to de- commission and close the whole or any part of the Bus Terminal to Users and passengers for so long as such Emergency and the consequences thereof warrant; provided that such de-commissioning and particulars thereof shall be notified by the Concessionaire to the Authority without any delay, and the Concessionaire shall diligently carry out and abide by any reasonable directions that the Authority may give for dealing with such Emergency.

  • Joint Occupational Health and Safety Committee The Employer and the Union recognize the role of the joint Occupational Health and Safety Committee in promoting a safe and healthful workplace. The parties agree that a Joint Occupational Health and Safety Committee shall be established for each Employer covered by this Collective Agreement. The Committee shall govern itself in accordance with the provisions of the Industrial Health and Safety Regulations made pursuant to the Workers’ Compensation Act. The Committee shall be as between the Employer and the Union, with equal representation, and with each party appointing its own representatives. Representatives of the Union shall be chosen by the Union membership or appointed by the Union. All minutes of the meetings of the Joint Occupational Health & Safety Committee will be recorded in a mutually agreeable format and will be sent to the Union. The Union further agrees to actively pursue with the other Health Care Unions a Joint Union Committee for the purposes of this Article. The Employer agrees to provide or cause to be provided to Employer members of the Joint Occupational Health and Safety Committee adequate training and orientation to the duties and responsibilities of committee members to allow the incumbents to fulfil those duties competently. The Union agrees to provide or cause to be provided to Union members of the Joint Occupational Health and Safety Committee adequate training and orientation to the duties and responsibilities of committee members to allow the incumbents to fulfil those duties competently. Such training and orientation shall take place within six (6) months of taking office.

  • Grievance Commissioner System This is to confirm the discussion of the parties during collective bargaining that they are committed to encouraging early discussion and resolution of labour relations issues at the local level and seek to resolve grievances in a timely and cost efficient manner. To that end, this is to confirm that pursuant to Article 8, the parties agree that the Employer and Union at individual nursing homes may agree to utilize the following process in order to resolve a particular grievance through the utilization of a joint mediation-arbitration procedure:

  • Extra Work At any time during the Term of this Agreement, City may request that Consultant perform Extra Work. As used herein, “Extra Work” means any work which is determined by City to be necessary for the proper completion of the Project, but which the Parties did not reasonably anticipate would be necessary at the execution of this Agreement. Consultant shall not perform, nor be compensated for, Extra Work without written authorization from City’s Representative.

Time is Money Join Law Insider Premium to draft better contracts faster.