Achievement of Final Completion Sample Clauses

Achievement of Final Completion. Within 10 Business Days of receipt of the Notice of Final Completion by Owner and the Owner Engineer, Owner shall inspect the Project and/or cause the Project to be inspected by the Owner Engineer, Owner Agents, and/or the Financing Engineer, and Owner shall either: (a) deliver to Contractor a written acceptance of Contractor’s Notice of Final Completion in the form set forth in Appendix I-3 (the “Certificate of Final Completion”), or (b) notify Contractor in writing that it disputes Contractor’s certification that the conditions for Final Completion have been met, or stating that it cannot confirm such satisfaction, stating with specificity the reasons therefor. If Owner issues the Certificate of Final Completion, the date of Owner’s receipt of the Notice of Final Completion will be deemed the “Final Completion Date.” If Owner notifies Contractor that it disputes satisfaction of the conditions for Final Completion or cannot confirm such satisfaction, then Contractor shall either promptly undertake such action or Work as necessary to meet such conditions or verify satisfaction thereof and issue another Notice of Final Completion to Owner or refer the matter to dispute resolution in accordance with Article 17. In the event Contractor prevails in the Dispute, the date of Owner’s receipt of the then applicable Notice of Final Completion shall be deemed the Final Completion Date.
AutoNDA by SimpleDocs
Achievement of Final Completion. The last portion of the Work has been finally certified and accepted by Owner and the Independent Consultant; and
Achievement of Final Completion. Owner will within five (5) Business Days following Owner’s receipt of the Notice of Final Completion for a Facility, either (i) deliver a written certification stating that the requirements for Final Completion of such Facility have been achieved, or (ii) notify Contractor in writing that such requirements have not been achieved, stating the reasons therefore. If Owner certifies that such requirements have been met, then the date of such Notice of Final Completion will be deemed the date Final Completion of such Facility or System. If Owner notifies Contractor that such requirements have not been met, then Contractor will promptly take such actions as will cause such requirements to be met, and upon meeting such requirements, Contractor will issue to Owner another Notice of Final Completion. Such procedure will be repeated as necessary until Owner certifies that such requirements have been met. Should Owner fail to make any notification to Contractor within the aforesaid five (5) Business Day period after its receipt of Notice of Final Completion, then the Facility shall be deemed to have achieved Final Completion as of the date of the Notice of Final Completion. So long as Owner has satisfied the aforesaid five-Business Day notice requirement, the issuance by Owner of a certificate stating that the requirements of Sections 18.1.1 through 18.1.5 have been met shall be a condition to achievement of Final Completion.
Achievement of Final Completion. The City shall, in consultation with the Owner Representative, within 20 days following receipt of the Notice of Final Completion, inspect the Project, review the report submitted by the Design-Builder and either (1) deliver a written certificate to the Design-Builder stating that all conditions set forth in subsection (A) of this Section have been satisfied, or (2) notify the Design-Builder in writing that Final Completion has not been achieved, stating in detail the reasons therefor. In the event that the City determines that Final Completion has not been achieved, the Design-Builder shall promptly take such action or perform such Design-Build Work as will achieve Final Completion and shall issue to the City another Notice of Final Completion pursuant to (B) of this Section. Such procedure shall be repeated as necessary until Final Completion is achieved. If the City, in its written certificate delivered in accordance with this subsection, states that it concurs that all conditions set forth in subsection (A) of this Section have been satisfied, the Project shall be deemed to have achieved Final Completion and Final Completion shall be deemed to have been established on the date of the Design-Builder’s most recent Notice of Final Completion.
Achievement of Final Completion. No later than five (5) Business Days after the date on which the Contractor determines, in its reasonable discretion, that it has achieved Final Completion, the Contractor shall deliver to the Owner Lessor an executed Final Completion Certificate, substantially in the form attached hereto as Exhibit C (the “Final Completion Certificate”). For purposes of this Agreement, the date of achievement of Final Completion shall be the date on which the Contractor delivers to the Owner Lessor the Final Completion Certificate.
Achievement of Final Completion. Upon receipt of the initial or any subsequent Notice of Final Completion, Owner shall use commercially reasonable efforts to inspect the Facility within [ * * * ]* Business Days and either: (a) deliver to Contractor a written certification stating that it has achieved Final Completion; or (b) notify Contractor in writing that Final Completion has not been achieved and stating the reasons therefore. Contractor shall achieve Final Completion of the Work within [ * * * ]* after the achievement of Substantial Completion.

Related to Achievement of Final Completion

  • Final Completion The full and final completion of all Work in accordance with the Contract Documents.

  • Final Completion Date Final Completion for the Work as defined in Article 6.1.3 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by September 30, 2022.

  • Project/Milestones Taxpayer provides refrigerated warehousing and logistic distribution services to clients throughout the United States. In consideration for the Credit, Taxpayer agrees to invest in a new refrigeration and distribution facility in the XxXxxxxxx Park area of Sacramento, California, and hire full-time employees (collectively, the “Project”). Further, Taxpayer agrees to satisfy the milestones as described in Exhibit A (“Milestones”) and must maintain Milestones for a minimum of three (3) taxable years thereafter. In the event Taxpayer employs more than the number of full-time employees, determined on an annual full-time equivalent basis, than required in Exhibit A, for purposes of satisfying the “Minimum Annual Salary of California Full-time Employees Hired” and the “Cumulative Average Annual Salary of California Full-time Employees Hired,” Taxpayer may use the salaries of any of the full-time employees hired within the required time period. For purposes of calculating the “Minimum Annual Salary of California Full-time Employees Hired” and the “Cumulative Average Annual Salary of California Full-time Employees Hired,” the salary of any full-time employee that is not employed by Taxpayer for the entire taxable year shall be annualized. In addition, the salary of any full-time employee hired to fill a vacated position in which a full-time employee was employed during Taxpayer’s Base Year shall be disregarded.

  • Targets and Milestones Comparing the relative performance of different groups to the over or under- representation within the institution and taking into account our current performance in our Access Agreement milestones, areas for particular focus include: Low Participating Neighbourhoods; Low income groups; Target groups to include gender, disability and care leavers; Black and minority ethnic (BME) group attainment; Completion rates. As a result of the analysis of our performances, our access, success and progression interventions will concentrate on the following: Continuation of involvement in collaborative outreach activity via the KMPF and the Kent and Medway Collaborative Network (KMCNet) as part of the National Network for Collaborative Outreach (NNCO); Recognition of the importance of carefully targeted activity; The use of serial rather than one-off interventions; The importance of long-term outreach to include the whole student lifecycle; The helpfulness of Higher Education Access Tracker (HEAT) for evaluating the impact of interventions; The importance of a whole institution approach; The importance of student attendance monitoring; Ease of access to information and student welfare support; An increasing emphasis on evaluation of activities across the student lifecycle; Accessibility of employability advice and support. Given our relatively strong record to date for widening access and student success, most of the targets seek to maintain, and where possible improve, this performance within a more challenging financial environment. Such targets may be especially challenging and stretching in relation to the access of those from Low Participating Neighbourhoods (LPNs), given the demographic decline in the number of young people (aged 18-21) in the population and the University’s already high recruitment levels from these groups. We have removed the University’s NS-SEC target in response to the UK Performance Indicator Steering Group announcement that HESA will no longer be publishing the NS-SEC indicator after 2016. As we already have LPN and Household Income targets in place we shall not be replacing this target with an alternative. We have reviewed our success targets and added new progression targets for 2017. There was a concern in the institution that our internal reporting did not allow for national and regionally adjusted benchmark comparison. We have therefore made the following adjustments to our success targets: Non-continuation two years following year of entry: part-time first degree entrants – all entrants: Replacing the OFFA agreement target with the similar data from HESA allows for national benchmarking to be undertaken in order to ensure that the University is maintaining its commitment to these students. We aim to keep our non-continuation rate in this area below our HESA benchmark rate. Non-continuation following year of entry: UK domiciled full-time first degree entrants – mature entrants: Changing the target to clearly focus on mature full-time first degree students (to match the national HESA data) ensures that we focus our efforts on this section of the student population and for the outcomes to be compared with HESA benchmarks rather than internally produced data. We aim to ensure that this student population’s non-continuation rate is at or below the HESA benchmark rate by 2020/21. Non-continuation following year of entry: UK domiciled full-time first degree entrants – all entrants: In order to ensure that young students are not disadvantaged by the focus on mature entrants, the University will also commit to maintaining the overall non-continuation rate for all students at or below the HESA benchmark. BME: the University will replace the current phrasing of the target around BME success with a more explicit aim of reducing the success gap experienced by BME students. Progression: the University has added a progression target that aims to keep us around or above the sector benchmark for the Employment Indicator from the DLHE survey. Combined targets from the collaborative KMPF project (agreed by all partners) are to raise applications and subsequent conversions to higher education from within the target schools and colleges in LPNs. These targets will need to be reviewed in the coming years to reflect changes to GCSE grading in schools. Our institutional and collaborative targets are included in tables 7a and 7b respectively.

  • Milestones Subject to the provisions of the SGIP, the Parties shall agree on milestones for which each Party is responsible and list them in Attachment 4 of this Agreement. A Party’s obligations under this provision may be extended by agreement. If a Party anticipates that it will be unable to meet a milestone for any reason other than a Force Majeure event, it shall immediately notify the other Parties of the reason(s) for not meeting the milestone and (1) propose the earliest reasonable alternate date by which it can attain this and future milestones, and (2) requesting appropriate amendments to Attachment 4. The Party affected by the failure to meet a milestone shall not unreasonably withhold agreement to such an amendment unless it will suffer significant uncompensated economic or operational harm from the delay, (1) attainment of the same milestone has previously been delayed, or (2) it has reason to believe that the delay in meeting the milestone is intentional or unwarranted notwithstanding the circumstances explained by the Party proposing the amendment.

  • Commercial Milestones In partial consideration of the rights granted by AstraZeneca to Licensee hereunder, Licensee shall pay to AstraZeneca the following payments, which shall be non-refundable, non-creditable and fully earned upon the first achievement of the applicable milestone event:

  • Development Milestones In addition to its obligations under Paragraph 7.1, LICENSEE specifically commits to achieving the following development milestones in its diligence activities under this AGREEMENT: (a) (b).

  • PROGRESS AND COMPLETION 8.2.1 All time limits stated in the Contract Documents are material terms and time is the essence of the Contract. A failure by Contractor to do what is required by the time specified in the Contract Documents is a breach of the contract.

  • Sales Milestones On a Co-Co Product-by-Co-Co Product basis, Celgene shall make the following sales milestone payments to Jounce that are set forth below upon the first achievement by or on behalf of Celgene, its Affiliates or Sublicensees of the sales milestone events (“Sales Milestone Events”) set forth below with respect to sales of such Co-Co Product in the ROW Territory. Sales Milestone Event (Per Co-Co Product, ROW (i.e., ex-U.S.)) Milestone Payments (in $ millions) [***] [***] [***] [***]

  • Substantial Completion “Substantial Completion” means the stage in the progress of the Work when the Work, or designated portions thereof, may still require minor modifications or adjustments but, in the Owner’s opinion, the Work has progressed to the point such that all parts of the Work under consideration are fully operational and usable for intended purposes, as evidenced by a Certificate of Substantial Completion approved by the Owner. If a Certificate of Occupancy is required by public authorities having jurisdiction over the Work, said certificate shall be issued before the Work or any portion thereof is considered substantially complete. When the Contractor considers that the Work, or a portion thereof which the Owner agrees to accept separately, is substantially complete, the Contractor shall notify Owner’s Designated Representative (sometimes referred to as the “ODR”) and request a determination as to whether the Work or designated portion thereof is substantially complete. If the ODR does not consider the Work substantially complete, the ODR will notify the Contractor giving reasons therefore. Failure on the Owner’s part to list a reason does not alter the responsibility of the Contractor to complete all Work in accordance with the terms of this Agreement. After satisfactorily completing items identified by Owner’s Designated Representative, the Contractor shall then submit another request for the ODR to determine Substantial Completion. If The ODR considers the Work substantially complete, The ODR will prepare and deliver a certificate of Substantial Completion which shall establish the date of Substantial Completion, shall include a punch list of items to be completed or corrected before final completion and final payment, shall establish the time within which the Contractor shall finish the punch list, and shall establish responsibilities of the Owner and the Contractor for security, maintenance, heat, utilities, damage to the Work, warranty and insurance. Failure to include an item on the punch list does not alter the responsibility of the Contractor to complete all Work in accordance with the terms and conditions of this Agreement. The certificate of Substantial Completion shall be signed by the Owner and the Contractor to evidence acceptance of the responsibilities assigned to them in such certificate. Substantial Completion (as defined in this agreement) for all stages of the Work shall be achieved on or before the following Substantial Completion date: DATE FOR SUBSTANTIAL COMPLETION: TBD Under no circumstances will the time for Substantial Completion exceed this date without a written amendment to this Agreement. THE TIMES SET FORTH IN THE CONSTRUCTION DOCUMENTS ARE AN ESSENTIAL ELEMENT OF THE AGREEMENT. TIME LIMITS STATED IN THE CONTRACT DOCUMENTS ARE OF THE ESSENCE OF THIS AGREEMENT.