PROGRESS AND COMPLETION Sample Clauses

PROGRESS AND COMPLETION. 8.2.1 All time limits stated in the Contract Documents are material terms and time is the essence of the Contract. A failure by Contractor to do what is required by the time specified in the Contract Documents is a breach of the contract.
AutoNDA by SimpleDocs
PROGRESS AND COMPLETION. 8.2.1 Time limits stated in the Contract Documents are of the essence of the Contract. By executing the Agreement the Contractor confirms that the Contract Time is a reasonable period of performing the Work.
PROGRESS AND COMPLETION. 8.1.1 Time limits stated in the Design-Build Documents are of the essence of the Contract. By executing the Design-Build Amendment the Design-Builder confirms that the Contract Time is a reasonable period for performing the Work.
PROGRESS AND COMPLETION. 4.2.2, 8.2, 9.8, 9.9.1, 14.1.4, 15.1.4 Progress Payments 9.3, 9.6, 9.8.5, 9.10.3, 14.2.3, 15.1.4 Project, Definition of
PROGRESS AND COMPLETION. It is expressly understood by the Contractor and Owner that time is important in the performance of this Agreement. The Contractor shall begin the Work on the date of commencement set forth in the written notice to proceed. The Contractor shall carry the Work forward expeditiously with adequate forces and shall complete it in accordance with the Schedule.
PROGRESS AND COMPLETION. CONTRACTOR shall commence work on the services to be performed upon full execution of this Agreement and shall consider full execution of this Agreement as Notice to Proceed. All services shall be completed as mutually agreed upon by both parties; deviations from the schedule shall be approved by VCTC. Progress reports, which include a summary of work completed during the billing period, will be provided by the CONTRACTOR with each invoice.
PROGRESS AND COMPLETION. All time limits stated in the Contract Documents are of the‌ essence of the agreement between Owner and Contractor. Contractor shall begin each phase of the Project, where applicable, in accordance with the Project Schedule and shall commence the Work on the dates set forth in the applicable Construction Schedule. Contractor shall carry out the Work expeditiously, with adequate forces, and shall achieve Substantial Completion in accordance with the Project’s milestones, the Construction Schedule, and within the Contract Time.
AutoNDA by SimpleDocs
PROGRESS AND COMPLETION. (a) Time limits stated in the Contract Documents are of the essence of the Contract. By executing the Building Construction Services Agreement, the Prime Contractor confirms that the Contract Time is a reasonable period for performing the Work.
PROGRESS AND COMPLETION. 15.4.1 Time of the Essence Time limits stated in the Contract Documents are of the essence to the Contract Documents. By executing the Facilities Lease, Developer confirms that the Contract Time is a reasonable period for performing the Work.
PROGRESS AND COMPLETION. Time limits stated in the Contract Documents are of the essence of this Agreement. By executing the Agreement, the Design/Builder confirms that the Contract Time is a reasonable period of time for achieving Substantial Completion of the Work. Design/Builder agrees to have all work substantially completed NOT LATER THAN, July 31, 2003.