Final Completion Date Sample Clauses

Final Completion Date. Final Completion for the Work as defined in Article 6.1.3 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by September 30, 2022.
AutoNDA by SimpleDocs
Final Completion Date. The date established in the Agreement by which the Design-Builder shall achieve Final Completion. The Final Completion Date may be modified only by Change Order or Change Directive in accordance with the Agreement.
Final Completion Date. The date the Task Order Work is completed, including completion of the final punch list, and delivered along with those items specified in the Contract Documents and is accepted by the City.
Final Completion Date. The date established in the GMP Amendment by which the Design-Builder shall achieve Final Completion. The Final Completion Date may be modified only by Change Order or Change Directive in accordance with the Agreement.
Final Completion Date. Final Completion for the Work as defined in Article 6.1.3 of the General Conditions to the Continuing Contract for Design Build Services shall be achieved by March 12, 2021.
Final Completion Date. Final completion of the Work shall be achieved in accordance with the CPM schedule attached hereto.
Final Completion Date. The Design-Builder shall finally complete the Work in accordance with the Contract Documents per Exhibit 1 (the “Final Completion Date”).
AutoNDA by SimpleDocs
Final Completion Date. Contractor shall achieve Final Completion no later than [***] ([***]) Days after achieving Substantial Completion of Train 2 (“Final Completion Date”). The Final Completion Date shall only be adjusted by Change Order as provided under this Agreement.
Final Completion Date. Final completion of the Work shall be achieved by .
Final Completion Date. The date upon which the Project is fully constructed and all Work required on the Project and Project Site is fully performed as verified in writing by the Owner.