Days to Achieve Substantial Completion and Final Payment Sample Clauses

Days to Achieve Substantial Completion and Final Payment. A. The Work will be substantially completed within 90 calendar days after the date when the Contract Times commence to run as provided in Paragraph 2.03 of the General Conditions, and completed and ready for final payment in accordance with Paragraph 14.07 of the General Conditions within 120 calendar days after the date when the Contract Times commence to run.
AutoNDA by SimpleDocs
Days to Achieve Substantial Completion and Final Payment. A. The Work shall commence on or after May 17, 2021 and shall be completed and ready for final payment in accordance with Paragraph 14.07 of the General Conditions by July 30, 2021. Work shall not occur on the observed Holidays of May 31, 2021 and City of Walled Lake, Michigan July 4 2021. Work may commence on a separate date prior to May 17, 2021 following written request by Contractor and written approval by Owner.
Days to Achieve Substantial Completion and Final Payment. Phase I, the drilling pad, shall be completed within 20 days after the date when the Contract Times commence to run as provided in the General Conditions. Phase II shall be completed within 30 days of an order to commence Phase II given by the Engineer.
Days to Achieve Substantial Completion and Final Payment. The Work is targeted for Substantial Completion as defined in Article 13.05 of the General Conditions on July 21st, 2006 and is to be completed and ready for final payment in accordance with paragraph 13.08 of the General Conditions within 30 calendar days after the date of Substantial Completion. This date of Substantial Completion is predicated on CCBE providing Notice to Proceed to BIOSOURCE FUELS no later than October 17th, 2005 and that CCBE has acquired all required permits and has reached Substantial Completion on all CCBE-furnished improvements including the site development, tank farm and load out facilities and the process building prior to March 1st, 2006. The Design/Builder and Owner agree and acknowledge that the Plant will be ready for Partial Utilization as defined in Articles 1.01.30 and 13.06 of the General Conditions and that the Owner will be capable of producing product for sale prior to the Substantial Completion date. This is because both the Design/Builder and Owner acknowledge and agree that this is the first commercial scale facility that has been constructed using the Design/Builder’s technology and additional time may be required to optimize the final operations with respect to product throughput and yield, however biodiesel and glycerin product will be produced for sale in advance of the optimization efforts thereby permitting the Owner to begin commercial operations. The Partial Utilization has been defined as the plant being capable of producing at a flow rate of 600 gallons per hour of ASTM D 6751-03 Grade S15 biodiesel. The Partial Utilization date has been established at June 5th, 2006. The incentive for both the Owner and Design/Builder to achieve the target dates for Partial Utilization and Substantial Completion is provided through the payment schedule in which 30% of the Contract Value will be withheld by the Owner until such time as the Design/Builder achieves Substantial Completion.
Days to Achieve Substantial Completion and Final Payment. A. The Work will be substantially completed within calendar days after the Notice to Proceed is issued, and completed and ready for final payment within calendar days after the date the Notice to Proceed is issued. Calendar days do not include documented inclement weather delays, which will be calculated prior to the end of the project and may result in an extension.
Days to Achieve Substantial Completion and Final Payment. The Work will be Substantially Completed within four hundred eighty (480) days after the date when the Contract Times commence to run as provided in paragraph 2.01.A of the General Conditions (as defined in Section 7.01.C.), and completed and ready for final payment in accordance with paragraph 13.08 of the General Conditions within one hundred eighty (180) days after Substantial Completion, unless otherwise provided in the Contract Documents. In no event will DESIGN/BUILDER be required to commission and start-up the Project, including the commencement of water trials and the grinding of corn, within the time period from December 5 to January 5 in any calendar year, and if the Project is ready for commissioning and start-up during such a time period, the number of days within such time period shall not count against the Contract Times for which DESIGN/BUILDER must have the Work completed and ready for final payment in accordance with paragraph 13.08 of the General Conditions.
Days to Achieve Substantial Completion and Final Payment. A. The Work shall be substantially complete within three hundred and thirty-eight (338) calendar days from the Notice to Proceed date and ready for final payment in accordance with Section 14.07 of the General Conditions within 30 calendar days after the substantially complete date. Substantial completion shall include all Xxxxx Pump Station pumps running in automatic mode and the well pump and pump station are operating at the expanded capacity.
AutoNDA by SimpleDocs
Days to Achieve Substantial Completion and Final Payment. The Work will be completed and ready for final payment of the Contract Price in accordance with paragraph 13.08 of the General Conditions within thirty (30) days after the date the OWNER shuts down the plant in late March or early April of 2005, unless otherwise provided in the Contract Documents. During such 30-day period, DESIGN/BUILDER anticipates that the plant will need to be shut down for no more than four (4) days in order for DESIGN/BUILDER to complete the Work.
Days to Achieve Substantial Completion and Final Payment. A. The Project will be substantially completed as stated in the Bid Quotation Form. Final Completion shall be within 45 days of Substantial Completion.
Days to Achieve Substantial Completion and Final Payment. This project will be completed by the substantial and final completion dates of June 30th, 2021 and commissioned by August 31st, 2021. Work can be sequenced and planned as needed and desired by the selected contractor in order to meet their needs and schedules as long as the completion dates set forth are maintained.