Commencement, Prosecution, and Completion of Work Sample Clauses

Commencement, Prosecution, and Completion of Work. The Contractor will be required (a) to commence the Work under this Contract on the applicable Proceed Order Date, (b) to prosecute the Work with faithfulness and energy (c) to install the various parts of the work with equal steps shown on the Overall Project Schedule and at the same rate (or better) shown on the Overall Project Schedule and (d) to complete the Work within the Contract Time, as adjusted. Commencement of the Work shall mean actual physical work on the Site. Unless otherwise agreed, and subject to Change Orders, Material Completion of the Project must be achieved on or before the date established as the Material Completion and Occupancy Date under the Schedule.
AutoNDA by SimpleDocs
Commencement, Prosecution, and Completion of Work. The CM/GC will be required (a) to commence the Work under this Contract on the applicable Proceed Order Date, (b) to prosecute the Work with faithfulness and energy (c) to install the various parts of the work with equal steps shown on the Overall Project Schedule and at the same rate (or better) shown on the Overall Project Schedule and (d) to complete the Work within the Contract Time, as adjusted. Commencement of the Work shall mean actual physical work on the Site. Unless otherwise agreed, and subject to Change Orders, Material Completion of the Project must be achieved on or before the date established as the Material Completion and Occupancy Date under the Schedule. CM/GC’s Acceleration for failure to meet Schedule Requirements. In the event the CM/GC shall be delinquent in respect to achieving the Milestone dates established in the Overall Project Schedule, CM/GC shall, within seven days after receipt of written demand of the Owner, cause its employees and Subcontractors to perform work at an accelerated pace with hours and days in addition to the normal working hours and working days, as necessary to promptly bring the Work into compliance with the Overall Project Schedule. Fulfillment of this requirement as to overtime work shall not relieve the CM/GC from liability for breach of the covenant as to time. For account of recovery of lost time required of the CM/GC for its breach of covenant as to time, the CM/GC shall be entitled to no claim against the Owner for any payment, repayment, reimbursement, remittance, remuneration, compensation, profit, cost, overhead, expense, loss expenditure, allowance, charge, demand, hire, wages, salary, tax, cash, assessment, price, money, xxxx, statement, dues, recovery, restitution, benefit, recoupment, exaction, injury or damages. Construction Progress Schedule and Overall Project Schedule. Submittal, Approval, and Updates. Not later than sixty days after the Effective Date of the Contract, but prior to the Proceed Order, the CM/GC must submit a Construction Progress Schedule in accordance with Section 2.1.5. Approval of Overall Project Schedule. . Upon recommendation by the Design Professional and approval by the Owner, the Construction Progress Schedule shall become the Overall Project Schedule, and becomes a part of this Contract. The Overall Project Schedule shall govern the schedule of activities of the CM/GC under this Contract Monthly Updates. The CM/GC must provide the Design Professional and the Owner w...
Commencement, Prosecution, and Completion of Work. (1) The Contractor agrees that it will begin the work herein embraced upon receipt of the Notice to Proceed, unless the Fund consents, in writing, to begin at a different date, and that it will prosecute the same with such diligence that all work covered by the Contract shall be substantially completed and performed on or before the time specified on page X- 0 of the Agreement.
Commencement, Prosecution, and Completion of Work. The CMR will be required (a) to commence work under this Contract as of the Effective Date of the Contract, (b) to prosecute the work with faithfulness and energy (c) to install the various parts of the work with equal steps shown on the Overall Project Schedule and at the same rate (or better) shown on the Overall Project Schedule and (d) to complete the work within the Contract Time, as adjusted. Commencement of work shall mean beginning the Basic Services. Unless otherwise agreed, and subject to Change Orders, Material Completion of the Project must be achieved on or before the date established as the Material Completion Date.
Commencement, Prosecution, and Completion of Work. The Contractor shall not commence the Work until the Contracting Officer has issued NTP. The Contractor shall diligently prosecute the Work so as to achieve Substantial Completion of the Work, as defined in Section III (Terms and Conditions), “Substantial Completion and Contract Completion” clause, within the time specified in Section I (Project Information), “Period of Performance” clause. If the Contract specifies different completion dates for different phases or portions of the Work, the Contractor shall diligently prosecute the Work so as to achieve Substantial Completion of such phases or portions of the Work within the times specified.
Commencement, Prosecution, and Completion of Work. (APR 1984) - Alternate I (APR 1984) The Contractor shall be required to:
Commencement, Prosecution, and Completion of Work. The CM/GC will be required (a) to commence the Work under this Contract on the applicable Proceed Order Date, (b) to prosecute the Work with faithfulness and energy (c) to install the various parts of the Work with equal steps shown on the Overall Project Schedule and at the same rate (or better) shown on the Overall Project Schedule and (d) to complete the Work within the Contract Time, as adjusted. Commencement of the Work shall mean actual physical work on the Sites. Unless otherwise agreed, and subject to Change Orders, Material Completion of the Project must be achieved on or before the date established as the Material Completion Date.
AutoNDA by SimpleDocs
Commencement, Prosecution, and Completion of Work. The Contractor shall be required to (a) commence work under this contract after a prework meeting agreed upon by the Contractor and Forest Service, and (b) prosecute the work diligently. The time stated for completion shall include final cleanup. • The Contractor shall notify the Forest Service in writing upon completion of work. UKT-GT.9# - STEWARDSHIP PROJECTS Project Number 4: NFR 7700239 Road Closure & Stabilization End Results Close/ stabilize National Forest Road (NFR) 7700239 to prevent soil erosion and control pollution in stream channels by completing work at designated locations shown in the following plans, which is staked on the ground. All work shall conform to the contract plans and specifications.
Commencement, Prosecution, and Completion of Work. (APR 1984) The Contractor shall be required to (a) commence work under this contract within Thirty (30) calendar day after the date the Contractor receives the award, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than ninety (90) days after contract award. The time stated for completion shall include final cleanup of the premises. (End of clause) FAR 52.213-4, TERMS AND CONDITIONS -- SIMPLIFIED ACQUISITIONS (OTHER THAN COMMERCIAL ITEMS) (JAN 2022)
Commencement, Prosecution, and Completion of Work. The Contractor shall be required to (a) commence work under this contract after a prework meeting agreed upon by the Contractor and Forest Service, and (b) prosecute the work diligently. The time stated for completion shall include final cleanup. • The Contractor shall notify the Forest Service in writing upon completion of work for each Subdivision. UKT-GT.9# - STEWARDSHIP PROJECTS Project Number 2: Slash Trees End Results Slashing of small trees in project units leaving only the most minor of species as described in the following technical specifications.
Time is Money Join Law Insider Premium to draft better contracts faster.