of Attachment Z Sample Clauses

of Attachment Z. The Interconnection Customer shall be responsible for all System Upgrade Facility costs as required by Section 32.3.5.3.2 of Attachment Z or its share of any System Upgrade Facilities and System Deliverability Upgrades costs resulting from the final Attachment S process, as applicable, and Attachment 6 to this Agreement shall be revised accordingly.
AutoNDA by SimpleDocs
of Attachment Z. The cost estimate for Distribution Upgrades shall include the costs of Distribution Upgrades that are reasonably allocable to the Interconnection Customer at the time the estimate is made, and the costs of any Distribution Upgrades not yet constructed that were assumed in the Interconnection Studies for the Interconnection Customer but are, at the time of the estimate, an obligation of an entity other than the Interconnection Customer. The cost estimates for Distribution Upgrades, System Upgrade Facilities, and System Deliverability Upgrades are estimates. The Interconnection Customer is ultimately responsible for the actual cost of the Distribution Upgrades, System Upgrade Facilities, and System Deliverability Upgrades needed for its Small Generating Facility, as that is determined under Attachments S, X, and Z of the ISO OATT.
of Attachment Z. The cost estimate for Distribution Upgrades shall include the costs of Distribution Upgrades that are reasonably allocable to the Interconnection Customer at the time the estimate is made, and the costs of any Distribution Upgrades not yet constructed that were assumed in the Interconnection Studies for the Interconnection Customer but are, at the time of the estimate, an obligation of an entity other than the Interconnection Customer. The cost estimates for Distribution Upgrades and System Upgrade Facilities and System Deliverability Upgrades are estimates. The Interconnection Customer is ultimately responsible for the actual cost of the Distribution Upgrades and System Upgrade Facilities and System Deliverability Upgrades needed for its Small Generating Facility, as that is determined under Attachments S and X and Z of the NYISO OATT. There are no Connecting Transmission Owner Upgrades for the New Facility. DISTRIBUTION UPGRADES Distribution Upgrades for the Existing Facility Segments of the existing distribution circuit will have to be relocated to the new pole line for the Chautauqua Line. The full extent of the distribution relocation and underbuild required as a result of the Chautauqua Line construction will not be known until such time as the Interconnection Customer has obtained all easements and the full line design for the Chautauqua Line is completed (Milestone No. 10 in Attachment 4). Distribution Upgrades for the New Facility None. There are no Distribution Upgrades for the New Facility. SYSTEM UPGRADE FACILITIES System Upgrade Facilities for the Existing Facility Xxxxxxxxx-South Dow Line #859 Sectionalizing Switches To provide for sectionalizing in the event of maintenance or emergency operations of the line, the Connecting Transmission Owner will design and install two (2) 34.5 kV, 1200 X, 00 xX, 000 xX XXX load break switches; one on each side of the tap to the Xxxxxxxxx-South Dow Line #859. Xxxxxxxxx Substation The Connecting Transmission Owner will add three (3) line PTs and one (1) GE IJS relay to add synch check supervision of the Xxxxxxxxx-South Dow Line #859 reclosing.
of Attachment Z. The Interconnection Customer must also comply with the Connecting Transmission Owner’s operating instructions and requirements as referenced herein, including Connecting Transmission Owner’s Bulletin 86-01, dated October 3, 2011, including appendices, as amended from time to time, to the extent not inconsistent with the terms of this Agreement or the NYISO OATT. Attachment 6 - Connecting Transmission Owner’s Description of its Upgrades and Best Estimate of Upgrade Costs The NYISO, in consultation with the Connecting Transmission Owner, shall describe Upgrades and provide an itemized best estimate of the cost, including overheads, of the Upgrades and annual operation and maintenance expenses associated with such Upgrades. The Connecting Transmission Owner shall functionalize Upgrade costs and annual expenses as either transmission or distribution related.
of Attachment Z. The cost estimate for Distribution Upgrades shall include the costs of Distribution Upgrades that are reasonably allocable to the Interconnection Customer at the time the estimate is made, and the costs of any Distribution Upgrades not yet constructed that were assumed in the Interconnection Studies for the Interconnection Customer but are, at the time of the estimate, an obligation of an entity other than the Interconnection Customer. The cost estimates for Distribution Upgrades and System Upgrade Facilities and System Deliverability Upgrades are estimates. The Interconnection Customer is ultimately responsible for the actual cost of the Distribution Upgrades and System Upgrade Facilities and System Deliverability Upgrades needed for its Small Generating Facility, as that is determined under Attachments S and X and Z of the NYISO OATT. Distribution Upgrade Facilities The Connecting Transmission Owner will furnish and commission the Distribution Upgrade Facilities as follows: The Connecting Transmission Owner will install a total of five new distribution line voltage regulators at three locations. The distribution line voltage regulators are needed to maintain the voltage on the Chenango Bridge 428 circuit to within ANSI standards. The non-directional overcurrent recloser controls on the Xxxxxx Corners circuit 428 and the Chenango Bridge circuit 428 Xxxxxx Form 3A reclosers will be replaced with external directional overcurrent relay control, to maintain coordination. 34.5 kv VT’s are to be added for the directional sensing voltages. The Distribution Upgrades include the following equipment: Distribution line voltage regulator installations Location #1 - on L-1135 around P-50 (West Chenango Rd) Three units of single phase 5/8% step voltage regulators 100amps, 200KVA, 19920V, +/- 10% in 32 - 5/8% steps, 00 xxx X xxxx, 000XXX Xxxxxxxx #0 - xx X-0000 around X-0 (Xxxx Xxxx Xx) One unit of single phase 5/8% step voltage regulator 100amp, 76.2KVA, 7620V, +/- 10% in 32 - 5/8% steps, 00 xxx X xxxx, 00XXX Xxxxxxxx #0 - xx X-0000 around P-206 (Hyde St) One unit of single phase 5/8% step voltage regulator 100amp, 76.2KVA, 7620V, +/- 10% in 32 - 5/8% steps, 00 xxx X xxxx, 00XXX Xxxxxx Corners substation 428 circuit recloser control replacement and 3 line VT’s additions. VT type 00XXX XX 34.5Y/19.9-120/240 1P CSP Chenango Bridge 428 circuit recloser control replacement and 3 line VT’s additions. VT Type Areva VEF36-10, 175/300:1, 36 KV, 1300VA, Accuracy 0.3WXY Distribu...
of Attachment Z. The cost estimate for Distribution Upgrades shall include the costs of Distribution Upgrades that are reasonably allocable to the Interconnection Customer at the time the estimate is made, and the costs of any Distribution Upgrades not yet constructed that were assumed in the Interconnection Studies for the Interconnection Customer but are, at the time of the estimate, an obligation of an entity other than the Interconnection Customer. The cost estimates for Distribution Upgrades, System Upgrade Facilities, and System Deliverability Upgrades are estimates. The Interconnection Customer is ultimately responsible for the actual cost of the Distribution Upgrades, System Upgrade Facilities, and System Deliverability Upgrades needed for its Small Generating Facility, as that is determined under Attachments S, X, and Z of the ISO OATT. Attachment 7 - Insurance Coverage Attachment 8 – Initial Synchronization Date [Date] [NYISO Address] [Connecting Transmission Owner Address] Re: _____________ Small Generating Facility Dear __________________: On [Date] [Interconnection Customer] initially synchronized the Small Generating Facility [specify units, if applicable]. This letter confirms that [Interconnection Customer]’s Initial Synchronization Date was [specify]. Thank you. [Signature] [Interconnection Customer Representative] Attachment 9 – Commercial Operation Date [Date] [NYISO Address] [Connecting Transmission Owner Address] Re: _____________ Small Generating Facility Dear __________________: On [Date] [Interconnection Customer] has completed Trial Operation of Unit No. ___. This letter confirms that [Interconnection Customer] commenced Commercial Operation of the Small Generating Facility [specify units, as applicable], effective as of [Date plus one day]. Thank you. [Signature] [Interconnection Customer Representative]
of Attachment Z. The cost estimate for Distribution Upgrades shall include the costs of Distribution Upgrades that are reasonably allocable to NYPA at the time the estimate is made, and the costs of any Distribution Upgrades not yet constructed that were assumed in the Interconnection Studies for NYPA but are, at the time of the estimate, an obligation of an entity other than NYPA. The cost estimates for Distribution Upgrades, System Upgrade Facilities, and System Deliverability Upgrades are estimates. NYPA is ultimately responsible for the actual cost of the Distribution Upgrades, System Upgrade Facilities, and System Deliverability Upgrades needed for its Small Generating Facility, as that is determined under Attachments S, X, and Z of the ISO OATT.
AutoNDA by SimpleDocs
of Attachment Z. Connecting Transmission Owner’s Description of its Upgrades and Best Estimate of Upgrade Costs The NYISO, in consultation with the Connecting Transmission Owner, shall describe Upgrades and provide an itemized best estimate of the cost, including overheads, of the Upgrades and annual operation and maintenance expenses associated with such Upgrades. The Connecting Transmission Owner shall functionalize Upgrade costs and annual expenses as either transmission or distribution related.
of Attachment Z. RG&E shall be responsible for all System Upgrade Facility costs as required by Section 32.3.5.3.2 of Attachment Z or its share of any System Upgrade Facilities and System Deliverability Upgrades costs resulting from the final Attachment S process, as applicable, and Attachment 6 to this Agreement shall be revised accordingly.
of Attachment Z. The cost estimate for Distribution Upgrades shall include the costs of Distribution Upgrades that are reasonably allocable to the Interconnection Customer at the time the estimate is made, and the costs of any Distribution Upgrades not yet constructed that were assumed in the Interconnection Studies for the Interconnection Customer but are, at the time of the estimate, an obligation of an entity other than the Interconnection Customer. The cost estimates for Distribution Upgrades and System Upgrade Facilities and System Deliverability Upgrades are estimates. The Interconnection Customer is ultimately responsible for the actual cost of the Distribution Upgrades and System Upgrade Facilities and System Deliverability Upgrades needed for its Small Generating Facility, as that is determined under Attachments S and X and Z of the NYISO OATT. No System Upgrade Facilties, System Deliverability Upgrades, Connecting Transmission Owner Upgrades or Distribution Upgrades are required for the Small Generating Facility. Attachment 7 Insurance Coverage Each Party shall, at its own expense, maintain in force throughout the period of this Agreement, the following minimum insurance coverage, with insurers authorized to do business in the State of New York: Commercial General Liability Insurance including, but not limited to, bodily injury, property damage, products/completed operations, contractual and personal injury liability with a combined single limit of $1 million per occurrence, $2 million annual aggregate. In lieu of an actual general or public liability insurance policy either party may choose to self-insure the first $1,000,000 of any loss provided it can be shown that it has been a longstanding practice to maintain a high limit/deductible and the self-insurer can show proof of excess limits of at least $2,000,000.