Common use of of Attachment Z Clause in Contracts

of Attachment Z. The cost estimate for Distribution Upgrades shall include the costs of Distribution Upgrades that are reasonably allocable to the Interconnection Customer at the time the estimate is made, and the costs of any Distribution Upgrades not yet constructed that were assumed in the Interconnection Studies for the Interconnection Customer but are, at the time of the estimate, an obligation of an entity other than the Interconnection Customer. The cost estimates for Distribution Upgrades and System Upgrade Facilities and System Deliverability Upgrades are estimates. The Interconnection Customer is ultimately responsible for the actual cost of the Distribution Upgrades and System Upgrade Facilities and System Deliverability Upgrades needed for its Small Generating Facility, as that is determined under Attachments S and X and Z of the NYISO OATT. There are no Connecting Transmission Owner Upgrades for the New Facility. DISTRIBUTION UPGRADES Distribution Upgrades for the Existing Facility Segments of the existing distribution circuit will have to be relocated to the new pole line for the Chautauqua Line. The full extent of the distribution relocation and underbuild required as a result of the Chautauqua Line construction will not be known until such time as the Interconnection Customer has obtained all easements and the full line design for the Chautauqua Line is completed (Milestone No. 10 in Attachment 4). Distribution Upgrades for the New Facility None. There are no Distribution Upgrades for the New Facility. SYSTEM UPGRADE FACILITIES System Upgrade Facilities for the Existing Facility Xxxxxxxxx-South Dow Line #859 Sectionalizing Switches To provide for sectionalizing in the event of maintenance or emergency operations of the line, the Connecting Transmission Owner will design and install two (2) 34.5 kV, 1200 X, 00 xX, 000 xX XXX load break switches; one on each side of the tap to the Xxxxxxxxx-South Dow Line #859. Xxxxxxxxx Substation The Connecting Transmission Owner will add three (3) line PTs and one (1) GE IJS relay to add synch check supervision of the Xxxxxxxxx-South Dow Line #859 reclosing.

Appears in 8 contracts

Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement

AutoNDA by SimpleDocs

of Attachment Z. The cost estimate for Distribution Upgrades shall include the costs of Distribution Upgrades that are reasonably allocable to the Interconnection Customer at the time the estimate is made, and the costs of any Distribution Upgrades not yet constructed that were assumed in the Interconnection Studies for the Interconnection Customer but are, at the time of the estimate, an obligation of an entity other than the Interconnection Customer. The cost estimates for Distribution Upgrades and System Upgrade Facilities and System Deliverability Upgrades are estimates. The Interconnection Customer is ultimately responsible for the actual cost of the Distribution Upgrades and System Upgrade Facilities and System Deliverability Upgrades needed for its Small Generating Facility, as that is determined under Attachments S and X and Z of the NYISO OATT. There DISTRIBUTION UPGRADES No Distribution Upgrades are no Connecting Transmission Owner Upgrades required for the New Facility. DISTRIBUTION UPGRADES Distribution Upgrades for the Existing Small Generating Facility Segments of the existing distribution circuit will have to be relocated to the new pole line for the Chautauqua Line. The full extent of the distribution relocation and underbuild required as a result of the Chautauqua Line construction will not be known until such time as the Interconnection Customer has obtained all easements and the full line design for the Chautauqua Line is completed (Milestone No. 10 in Attachment 4). Distribution Upgrades for the New Facility None. There are no Distribution Upgrades for the New Facilityexpansion. SYSTEM UPGRADE FACILITIES System Upgrade Facilities The increase of generation added to the National Grid sub-transmission line will require relay settings modifications at the remote ends of the 34.5 xX Xxxxxx-Patroon Line #5 to which the interconnection is made. The changes, for both the Xxxxxx and Patroon Substations shall include, but not be limited to, development, implementation, and testing of new settings for the Existing Facility Xxxxxxxxx-South Dow Line #859 Sectionalizing Switches To provide for sectionalizing existing relays. ESTIMATE OF SYSTEM UPGRADE FACILTIES Insurance Coverage Interconnection Customer shall, at its own expense, maintain in force throughout the period of this Agreement, the following minimum insurance coverage, with insurers authorized to do business in the event State of maintenance or emergency operations New York: Commercial General Liability Insurance including, but not limited to, bodily injury, property damage, products/completed operations, contractual and personal injury liability with a combined single limit of the line$1 million per occurrence, the Connecting Transmission Owner will design and install two (2) 34.5 kV, 1200 X, 00 xX, 000 xX XXX load break switches; one on each side of the tap to the Xxxxxxxxx-South Dow Line #859. Xxxxxxxxx Substation The Connecting Transmission Owner will add three (3) line PTs and one (1) GE IJS relay to add synch check supervision of the Xxxxxxxxx-South Dow Line #859 reclosing$2 million annual aggregate.

Appears in 5 contracts

Samples: Small Generator Interconnection Agreement, Small Generator Interconnection Agreement, Small Generator Interconnection Agreement

AutoNDA by SimpleDocs
Time is Money Join Law Insider Premium to draft better contracts faster.