Project Close-out Sample Clauses

Project Close-out. Termination of a research project that used controlled-access data from an NIHdesignated data repository (e.g., dbGaP) and confirmation of data destruction when the research is completed and/or discontinued. The project close-out process is completed in the dbGaP Authorized Access System.
AutoNDA by SimpleDocs
Project Close-out a. Within thirty (30) days after the completion of the PROJECT’s construction and the ARCHITECT’s receipt of as-built documents from the Contractor, ARCHITECT will review the as-built documents prepared by the Contractor and revise the record drawings and specifications so that they include all material changes made necessary by CCD’s, ICD’s, change orders, RFI’s, change order requests (“COR’s”), Bulletins, clarifications as noted by the Contractor in its as-built documents and/or any other DISTRICT approved document which details the changes that were made to the DSA approved Construction Documents. The ARCHITECT shall incorporate such changes into a complete AutoCAD as-built file, in the original, executable, software format, and PDF files, and provide all such documents, including five (5) hard copies, to the DISTRICT at no additional cost. In the event the Contractor fails to provide its as-built documents within 30 days of the PROJECT’s completion, the ARCHITECT shall notify the DISTRICT, in writing, of the Contractor’s failure and recommend the appropriate withholding from the Contractor’s final payment under the Contract with the DISTRICT.
Project Close-out a. Acceptance of the completed construction shall be with the concurrence of the Department. Within 30 days of completion of construction or other activities authorized by this agreement, the Recipient shall provide written notification to the Department. The Recipient shall follow and request a final review, in accordance with the procedures in I.M. 6.110, Final Review, Audit, and Close-out Procedures for Federal-aid, Federal- aid Swap, and Farm-to-Market Projects. Failure to comply with the procedures may result in loss of funds and the ability to let future projects through the Department; reimbursed funds shall be returned and a possible suspension may be placed on the Recipient from receiving funds from the Department on future projects until the Recipient has demonstrated responsible management of funds on roadway projects.
Project Close-out a. The ENGINEER shall assure delivery of the following documents described below to the DSA for review prior to issuance of a “Certificate of Completion”.
Project Close-out. During the Project Close-Out phase the CMF shall (1) develop specific criteria for determining the final acceptability of contractor’s work (whether determination is by CMF or by others); (2) establish dates for equipment testing, acceptance periods, warranty dates and instructional requirements; (3) conduct frequent inspections throughout the finishing stages; (4) obtain close-out documentation including guarantees, warranties, samples, test reports and certifications, Owner Close-Out forms, operating and maintenance manuals, keys and completed as-built drawings from the contractor and vendors; and (5) jointly with the Design Consultant, certify final completion of the facility for acceptance by the Owner. The CMF shall monitor and track the progress of the contractor’s timely submission of project close-out documentation. The CMF shall send all project closeout documents to the Design Consultant for review and approval. The CMF shall periodically produce a project closeout documentation report sorted by contractor for the Owner and contractors until all documentation has been received.
Project Close-out. The Agreement Expiration Date refers to the last date for LOCAL AGENCY to incur valid Project costs or credits and is the date the Agreement expires. LOCAL AGENCY has sixty (60) days after that Expiration Date to make final allowable payments to Project contractors or vendors, prepare the Project Closeout Report, and submit the final invoice to CALTRANS for reimbursement for allowable Project costs. Any unexpended Project funds not invoiced by that sixtieth (60th) day will be reverted and will no longer be accessible to reimburse late Project invoices.
Project Close-out a. Within 30 days of completion of construction or other activities authorized by this agreement, the Subrecipient shall provide written notification to the Department and request a final audit, in accordance with the procedures in I.M. 6.110, Final Review, Audit, and Close-out Procedures for Federal-aid Projects. Failure to comply with the procedures will result in loss of federal funds remaining to be reimbursed and the repayment of funds already reimbursed. The Subrecipient may be suspended from receiving federal funds on future projects.
AutoNDA by SimpleDocs
Project Close-out. 2.9.1 The Designer will prepare the Record Documents based upon the As-Built Drawings and Documents received from the OAR. The OAR will have reviewed and accepted the Contractor’s As-Built Drawings and Documents when in their opinion they meet the intent of the Contract Documents and field observations. The Designer will prepare a complete set of Record Drawings representing, to the best of their knowledge, the as-built conditions of the Work, as further detailed in EDC-06.
Project Close-out a. Within thirty (30) days after the completion of the PROJECT’s construction and the ARCHITECT’s receipt of as-built documents from the Contractor, ARCHITECT will review the as-built documents prepared by the Contractor and revise the record drawings and specifications so that they include all material changes made necessary by CCD’s, ICD’s, (if applicable) change orders, RFI’s, change order requests (“COR’s”), Bulletins, clarifications as noted by the Contractor in its as-built documents and/or any other DISTRICT approved document which details the changes that were made to the DSA approved Construction Documents. The ARCHITECT shall incorporate such changes into a complete AutoCAD as-built file, in the original, executable, software format, and PDF files, and provide all such documents, including five (5) hard copies, to the DISTRICT at no additional cost. In the event the Contractor fails to provide its as-built documents within thirty (30) days of the PROJECT’s completion, the ARCHITECT shall notify the DISTRICT, in writing, of the Contractor’s failure and recommend the appropriate withholding from the Contractor’s final payment under the Contract with the DISTRICT.
Project Close-out. The termination date of this AGREEMENT refers to the last date for RECIPIENT to incur valid Project costs or credits. RECIPIENT has 60 days after the termination date of this AGREEMENT to make final allowable payments to third-party contractors, prepare the Project Closeout Report, and submit the final invoice to SANDAG for reimbursement for allowable Project costs. Any unexpended Project funds invoiced after 90 days post the termination date of this AGREEMENT will be forfeited and will no longer be accessible by RECIPIENT to reimburse for Project expenses.