Owner Requested Change Order Sample Clauses

Owner Requested Change Order. (a) Owner agrees that it will not request or direct changes in the Work or the Facility which (i) reduces Contractor's Scope of Work or (ii) materially alters the Technical Specifications, in each case, without Contractor's prior written consent, such consent not to be unreasonably withheld or delayed.
AutoNDA by SimpleDocs
Owner Requested Change Order. Without invalidating this Agreement, Owner may request changes in the Work or the Project. Owner shall request such changes in the Work or the Project by delivering a written Change Order request to Contractor. As soon as practicable after receipt of a Change Order request, but in no event later than five (5) Days after receipt of a Change Order request, Contractor shall prepare and forward to Owner in writing: (i) a quotation for the price for the extra or changed Work and change to the Schedule of Values (if applicable); (ii) an estimate of any required adjustment to the Construction Schedule; (iii) any adjustment to Performance Criteria; and (iv) an estimate of any impact of the proposed change on any Applicable Permit, warranty and any other term or condition of this Agreement. The Parties shall negotiate in good faith to determine the adjustment to the Contract Price for Change Orders contemplated by this Section 9.1. If the Parties do not agree on the adjustment to the Contract Price in respect of this Section 9.1, then the adjustment to the Contract Price may be determined in accordance with Exhibit 16 but only if the Parties so agree. If the Parties do not agree either (A) to a fixed price Change Order, or (B) that an adjustment to the Contract Price shall be determined in accordance with Exhibit 16, then Owner may nonetheless direct Contractor to proceed with the Work that is the subject of the Change Order, in which case (1) for a deductive Change Order, the Contract Price shall be reduced by the amount of any reduction in Contractor’s Direct Costs and (2) in the case of an additive Change Order (or Change Order involving additive and deductive elements), Contractor shall be paid an amount equal to any net increase in its Direct Costs in performing the Change Order plus a markup of six percent (6%). Contractor shall submit Applications for Payment no more frequently than monthly with respect to Contractor’s Direct Costs in accordance with the preceding sentence and Owner shall be obligated to pay such undisputed amounts within thirty (30) Days after Owner’s receipt of Contractor’s Application for Payment.
Owner Requested Change Order. Without invalidating this Agreement, Owner may request changes in the Work or the Project. Owner shall request such changes in the Work or the Project by delivering a written Change Order request to Contractor. As soon as practicable after receipt of a Change Order request, but in no event later than five (5) Days after receipt of a Change Order request, Contractor shall prepare and forward to Owner in writing: (i) a quotation for the price for the extra or changed Work and change to the Schedule of Values (if applicable);
Owner Requested Change Order. Owner, at any time or from time to time, may request a change to the Scope of Work (a “Change”) by issuing a notice to Construction Manager. Within five (5) Business Days of receipt of such notice, Construction Manager shall prepare and deliver to Owner a detailed written estimate (the “Construction Manager Estimate”) relating to the contemplated change, which shall include:

Related to Owner Requested Change Order

  • Change Order (5) The Change Order is then submitted to the Project Manager who immediately processes the CO with OPC as required by Bulletin 3.5 and BGS’ Contracting Plan.

  • Change Orders Any alteration or deviation from the Services mentioned or any other contractual specifications that result in a revision of this Agreement shall be executed and attached to this Agreement as a change order (“Change Order”).

  • Work Schedule Changes 215. It is agreed that pursuant to the exercise of management rights, normal work schedules may be changed without mutual agreement, subject to compliance with other provisions of this Agreement. However, it is agreed that the effects of consequences of such changes are subject to the meet and confer obligation to the extent required by state law.

  • Project Schedule Construction must begin within 30 days of the date set forth in Appendix A, Page 2, for the start of construction, or this Agreement may become null and void, at the sole discretion of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame.

  • CONTRACT ITEM CHANGES A. If a manufacturer discontinues a contracted item, that item will automatically be considered deleted from the contract with no penalty to Contractor. However, H-GAC may at its sole discretion elect to make a contract award to the next lowest Respondent for the item, or take any other action deemed by H-GAC, at its sole discretion, to be in the best interests of its Customers.

  • Change Request Either Landlord or Tenant may request Changes after Landlord approves the Approved Plans by notifying the other party thereof in writing in substantially the same form as the AIA standard change order form (a “Change Request”), which Change Request shall detail the nature and extent of any requested Changes, including (a) the Change, (b) the party required to perform the Change and (c) any modification of the Approved Plans and the Schedule, as applicable, necessitated by the Change. If the nature of a Change requires revisions to the Approved Plans, then the requesting party shall be solely responsible for the cost and expense of such revisions and any increases in the cost of the Tenant Improvements as a result of such Change. Change Requests shall be signed by the requesting party’s Authorized Representative.

  • Change Request Procedures 4.1. Either party can request changes to the Service in accordance with the change request form attached to the Order Form or provided by SAP from time to time (“Change Request”).

  • Project Changes 1.8.1. All changes shall be administered per the UGC.

  • Approval of Plans and Specifications The Plans and Specifications will conform to the requirements and conditions set out by applicable law or any effective restrictive covenant, and to all governmental authorities which exercise jurisdiction over the Leased Premises or the construction thereon.

  • Construction Schedule The progress schedule of construction of the Project as provided by Developer and approved by District.