Construction Schedule Sample Clauses

Construction Schedule. The progress schedule of construction of the Project as provided by Developer and approved by District.
AutoNDA by SimpleDocs
Construction Schedule. Construction Contractor shall prepare and submit to Owner and Design Professional, for their review and approval, a construction schedule. This construction schedule shall conform to the format outlined in Subsection 3.4 below (“Construction Schedule”). The approved Construction Schedule shall be attached to the GMP Amendment. The Construction Schedule shall be integrated into the Master Project Schedule.
Construction Schedule. Construction Schedule means the schedule for the Project prepared by the Contractor and appended hereto as Appendix ‘A’, as revised and/or updated from time to time pursuant to the Owner’s written approval.
Construction Schedule. 3.5.1 The Contractor shall:
Construction Schedule. The Construction Schedule shall include all pertinent dates and periods for timely completion of the Work.
Construction Schedule. 7.22.1 The Contractor shall submit its detailed construction schedule to the Project Manager prior to the start of the work. The purpose of the schedule is to allow the Project Manager to monitor the Contractor’s progress on the work. The schedule shall account for normal inclement weather, unusual soil or other conditions that may influence the progress of the work, schedules and coordination required by any utility, off or on site fabrications, and all other pertinent factors that relate to progress.
Construction Schedule a. Within fifteen (15) calendar days after the award of the Contract, the Contractor shall prepare and submit to the Project Manager and District an as-planned construction schedule showing in detail how the Contractor plans to prosecute the work within the time set for Final Completion. The schedule shall include the work of all trades necessary for construction of the Project, and shall be sufficiently complete and comprehensive to enable progress to be monitored on a day-by-day basis. The information for each activity shall include at a minimum the activity description, duration, start date and completion date.
AutoNDA by SimpleDocs
Construction Schedule. The Approved graphical representation of Contractor’s as- planned schedule for performance of the Work, and all Approved updates thereto, prepared in accordance with the requirements of the Contract Documents and that provides for Substantial Completion of the Work within the Contract Time.
Construction Schedule. 3.5.1 The Contractor shall: .1 prepare and submit to the Owner and the Contract Administrator within seven (7) Calendar Days from the Commencement Date, unless otherwise stipulated elsewhere in the Agreement or agreed to by the Contract Administrator, a construction schedule for their review and acceptance that indicates the timing of the major activities of the Work and provides sufficient detail of the critical events and their inter-relationship to demonstrate the Work shall be performed in conformity with the Contract Time. The construction schedule shall:
Construction Schedule. 5.1 Coordination: