DELAYS AND IMPACTS Sample Clauses

DELAYS AND IMPACTS. A. Should Subcontractor be delayed in the prosecution or completion of the Work by the act, neglect or default of the Owner, Contractor or other third party for whom they are legally responsible, or should Subcontractor be delayed waiting for materials or information required to be furnished by Owner or Contractor, or by damage caused by fire or other casualty for which the Subcontractor is in no way responsible, or by the combined action of the workforce, in no way caused by, or resulting from default or collusion on the part of the Subcontractor, then the time herein fixed for the completion of the Work shall be extended by the number of days that Subcontractor has been delayed, but no allowance or extension shall be made unless a claim therefore is presented in writing to the Contractor within forty-eight (48) hours of the commencement of such delay, and in no circumstances shall the time of completion be extended to a date which will prevent the Contractor from completing the entire Project within the time that Owner allows Contractor for such completion.
AutoNDA by SimpleDocs
DELAYS AND IMPACTS. If JCI is delayed in the commencement, performance, or completion of the Work and/or M&V Services by causes beyond its control and without its fault, including but not limited to inability to access property; concealed or unknown conditions encountered at the project, differing from the conditions represented by Customer in the bid documents or otherwise disclosed by Customer to JCI prior to the commencement of the Work; a Force Majeure (as defined below) condition; failure by Customer to perform its obligations under this Agreement; or failure by Customer to cooperate with JCI in the timely completion of the Work, JCI shall provide written notice to Customer of the existence, extent of, and reason for such delays and impacts. Under such circumstances, an equitable adjustment in the time for performance, price and payment terms, and the Assured Performance Guarantee shall be made.
DELAYS AND IMPACTS. If Contractor is delayed in the commencement, performance, or completion of the Work and/or M&V Services by causes beyond its control and without its fault, including but not limited to inability to access property; concealed or unknown conditions encountered at the project, differing from the conditions represented by City in the bid documents or otherwise disclosed by City to Contractor prior to the commencement of the Work; a Force Majeure (as defined below) condition; failure by City to perform its obligations under this Attachment; or failure by City to cooperate with Contractor in the timely completion of the Work, Contractor shall provide written notice to City of the existence, extent of, and reason for such delays and impacts. Under such circumstances, an equitable adjustment in the time for performance, price and payment terms, and the Assured Performance Guarantee shall be made. If an adjustment to price and/or payment is required, the parties shall negotiate additional compensation as provided in Schedule S-4 and an amendment or change order to this Contract shall be mutually executed by the parties, as appropriate. Should Contractor encounter concealed or unknown conditions in an existing structure, Contractor shall immediately give notice to the Customer’s designated representative of such conditions before they are disturbed.
DELAYS AND IMPACTS. If JCI is delayed in the commencement, performance, or completion of the Work and/or M&V Services by causes beyond its control and without its fault, including, but not limited to, inability to access property; concealed or unknown conditions encountered at the project, differing from the conditions represented by Customer in the bid documents or otherwise disclosed by Customer to JCI prior to the commencement of the Work (unless JCI should have discovered those conditions through reasonable visual inspection of the property and/or facilities and/or through a reasonable review of specifications, drawings, and/or plans regarding the Project); a Force Majeure (as defined below) condition; failure by Customer to perform its obligations under this Agreement; or failure by Customer to cooperate with JCI in the timely completion of the Work, JCI shall provide written notice to Customer of the existence, extent of, and reason for such delays and impacts. Under such circumstances, an equitable adjustment in the time for performance, price and payment terms, and the Assured Performance Guarantee shall be made, subject to the mutual written agreement of the parties.
DELAYS AND IMPACTS. If JCI is delayed in the commencement, performance, or completion of the Work and/or M&V Services by causes beyond its control and without its fault, including but not limited to inability to access property; concealed or unknown conditions encountered at the project that could not reasonably have been discovered by JCI during the comprehensive energy audit of Customer’s facilities by JCI; a Force Majeure (as defined below) condition; failure by Customer to perform its obligations under this Agreement; or failure by Customer to cooperate with JCI in the timely completion of the Work, JCI shall provide written notice to Customer of the existence, extent of, and reason for such delays and impacts. Under such circumstances, the parties will agree on an equitable adjustment in the time for performance, and, to the extent warranted by the circumstances, the parties will agree on an equitable adjustment in price and payment terms, and Assured Performance Guarantee.
DELAYS AND IMPACTS. If BREP is delayed in the commencement, performance, or completion of the Work and/or Services by causes beyond its control and without its fault, including but not limited to inability to access property, Hazardous Materials or Environmental Conditions present at a Project Site, Concealed Conditions or unknown conditions encountered at a Project Site differing from the conditions represented by the State or otherwise disclosed by the State to BREP prior to the commencement of the Work, a Force Majeure condition pursuant to Section 11.5 of the CEA, failure by the State to perform its obligations under this Agreement, or failure by the State to cooperate with BREP in the timely completion of the Work, BREP shall provide written notice to the State of the existence, extent of, and reason for such delays and impacts. Under such circumstances, an equitable adjustment in the time for performance, price and payment terms shall be made. If the Parties cannot reach agreement regarding an equitable adjustment under this Section 6, BREP will proceed with the Work and/or Services to the extent reasonably practicable, and the dispute shall be resolved by the Parties pursuant to ARTICLE 14 of the CEA.
DELAYS AND IMPACTS. If JCI is delayed or impacted in the commencement, performance, or completion of the Work and/or M&V Services by causes beyond its control and without its fault, including but not limited to inability to access property; concealed or unknown conditions encountered at the project, differing from the conditions represented by Customer in the bid documents or otherwise disclosed by Customer to JCI prior to the commencement of the Work; a Force Majeure Event (as defined below) condition; failure by Customer to perform its obligations under this Agreement; or failure by Customer to cooperate with JCI in the timely completion of the Work, JCI shall provide written notice to Customer of the existence, extent of, and reason for such delays and impacts. Under such circumstances, an equitable adjustment in the time for performance, price, scope and payment terms, and the Assured Performance Guarantee shall be made, provided any adjustments to price and the Assured Performance Guarantee shall be consistent with applicable Laws. Any adjustment to the contract time for performance, price, scope and payment terms shall be submitted in accordance with the Change Order process set forth in paragraph 11 of this Agreement.
AutoNDA by SimpleDocs
DELAYS AND IMPACTS. If the TOTBIA &/or DERKZ are delayed in the commencement, performance, or completion of the beautification project by causes beyond their control and without the party’s fault, including but not limited to inability to access property; concealed or unknown conditions encountered at the project; failure by Property Owners, Xxxx & Xxxxxx Xxxxxx, to perform its obligations under this agreement; or failure by Property Owners, Xxxx & Xxxxxx Xxxxxx, to cooperate with the TOTBIA in the timely completion of the beautification project, the TOTBIA shall provide written notice to Property Owners, Xxxx & Xxxxxx Xxxxxx, of the existence, extent of, and reason for such delays and impacts.

Related to DELAYS AND IMPACTS

  • Delays and Complaints Delivery delays and service complaints will be monitored on a continual basis. Documented inability to perform under the conditions of the contract, via the Complaint to Vendor process (PUR 7017 form) contemplated for this Contract, may result in default proceedings and cancellation.

  • Delays If no event of Force Majeure shall have occurred and be continuing and in the event that a delay shall have been caused by the negligence or willful misconduct of the Custodian in carrying out an Instruction to credit or transfer cash, the Custodian shall be liable to the Fund: (a) with respect to Principal Accounts, for interest to be calculated at the rate customarily paid on such deposit and currency by the Custodian on overnight deposits at the time the delay occurs for the period from the day when the transfer should have been effected until the day it is in fact effected; and, (b) with respect to Agency Accounts, for interest to be calculated at the rate customarily paid on such deposit and currency by the Subcustodian on overnight deposits at the time the delay occurs for the period from the day when the transfer should have been effected until the day it is in fact effected. The Custodian shall not be liable for delays in carrying out Instructions to transfer cash which are not due to the Custodian's own negligence or willful misconduct.

  • Faults Unless you notify us in writing of a material fault with any Equipment within seven days following delivery, you will be deemed to have accepted it. You acknowledge and agree that seven days is a reasonable period for the purpose of inspecting the Equipment and testing it for material faults.

  • ALTERATIONS AND IMPROVEMENTS Tenant shall make no alterations to the buildings or improvements on the Premises or construct any building or make any other improvements on the Premises without the prior written consent of Landlord. Any and all alterations, changes, and/or improvements built, constructed or placed on the Premises by Tenant shall, unless otherwise provided by written agreement between Landlord and Tenant, be and become the property of Landlord and remain on the Premises at the expiration or earlier termination of this Agreement.

  • Materials and Improvements Title to materials, improvements, and other property required of PURCHASER by this contract shall vest in and become the property of STATE at the time such are furnished by PURCHASER and accepted by STATE. Only materials, improvements, and property free and clear of liens, claims, and encumbrances shall be furnished by PURCHASER. All existing improvements located on State land, and any improvements placed on State land by PURCHASER which become the property of STATE, shall be safeguarded by PURCHASER. If such improvements are injured, damaged, or removed from the areas of operations by PURCHASER or by contractors of PURCHASER, such improvements shall be repaired (or replaced, in the event of removal,) as soon as possible by PURCHASER, without cost to STATE.

  • Environmental Conditions A Phase I environmental site assessment (or update of a previous Phase I and or Phase II environmental site assessment) and, with respect to certain Mortgage Loans, a Phase II environmental site assessment (collectively, an “ESA”) meeting ASTM requirements conducted by a reputable environmental consultant in connection with such Mortgage Loan within 12 months prior to its origination date (or an update of a previous ESA was prepared), and such ESA (i) did not identify the existence of Recognized Environmental Conditions (as such term is defined in ASTM E1527-05 or its successor, hereinafter “Environmental Condition”) at the related Mortgaged Property or the need for further investigation, or (ii) if the existence of an Environmental Condition or need for further investigation was indicated in any such ESA, then at least one of the following statements is true: (A) an amount reasonably estimated by a reputable environmental consultant to be sufficient to cover the estimated cost to cure any material noncompliance with applicable Environmental Laws or the Environmental Condition has been escrowed by the related Mortgagor and is held or controlled by the related lender; (B) if the only Environmental Condition relates to the presence of asbestos-containing materials, radon in indoor air, lead based paint or lead in drinking water, the only recommended action in the ESA is the institution of such a plan, an operations or maintenance plan has been required to be instituted by the related Mortgagor that can reasonably be expected to mitigate the identified risk; (C) the Environmental Condition identified in the related environmental report was remediated, abated or contained in all material respects prior to the date hereof, and, if and as appropriate, a no further action, completion or closure letter or its equivalent, was obtained from the applicable governmental regulatory authority (or the Environmental Condition affecting the related Mortgaged Property was otherwise listed by such governmental authority as “closed” or a reputable environmental consultant has concluded that no further action or investigation is required); (D) an environmental policy or a lender’s pollution legal liability insurance policy that covers liability for the Environmental Condition was obtained from an insurer rated no less than “A-” (or the equivalent) by Xxxxx’x, S&P and/or Fitch; (E) a party not related to the Mortgagor was identified as the responsible party for the Environmental Condition and such responsible party has financial resources reasonably estimated to be adequate to address the situation; or (F) a party related to the Mortgagor having financial resources reasonably estimated to be adequate to address the situation is required to take action. To Seller’s knowledge, except as set forth in the ESA, there is no Environmental Condition at the related Mortgaged Property.

  • REPAIRS AND IMPROVEMENTS 14.1 Prior to registration of transfer, the Purchaser shall not be entitled to effect any alterations to the Property without the prior written consent of the Seller.

  • Unsafe Working Conditions (a) No Employee shall be disciplined for refusal to work on a job which is deemed unsafe by:

  • Environmental Condition Except as set forth on Schedule 5.12 to the Information Certificate, (a) to each Loan Party’s knowledge, no properties or assets of any Loan Party or any of its Subsidiaries have ever been used by a Loan Party, its Subsidiaries, or by previous owners or operators in the disposal of, or to produce, store, handle, treat, release, or transport, any Hazardous Materials, where such disposal, production, storage, handling, treatment, release or transport was in violation, in any material respect, of any applicable Environmental Law, (b) to each Loan Party’s knowledge, after due inquiry, no Loan Party’s nor any of its Subsidiaries’ properties or assets have ever been designated or identified in any manner pursuant to any environmental protection statute as a Hazardous Materials disposal site, (c) no Loan Party nor any of its Subsidiaries has received notice that a Lien arising under any Environmental Law has attached to any revenues or to any Real Property owned or operated by a Loan Party or its Subsidiaries, and (d) no Loan Party nor any of its Subsidiaries nor any of their respective facilities or operations is subject to any outstanding written order, consent decree, or settlement agreement with any Person relating to any Environmental Law or Environmental Liability that, individually or in the aggregate, could reasonably be expected to result in a Material Adverse Change.

  • Alterations, Additions and Improvements Subject to the provisions of this Article IV, Lessee may make any alterations, additions, improvements or other changes to the Premises and the Relevant Assets as may be necessary or useful in connection with the operation of the Relevant Assets (collectively, the “Additional Improvements”). If such Additional Improvements require alterations, additions or improvements to the Premises or any of the Shared Access Facilities, Lessee shall notify Lessor in writing in advance and the parties shall negotiate in good faith any increase to the fees paid by Lessee under the Site Services Agreement by Lessee or otherwise provide for reimbursement of any material increase in cost (if any) to Lessor under the Site Services Agreement that results from any modifications to the Premises or the Shared Access Facilities necessary to accommodate the Additional Improvements, or as otherwise mutually agreed by the parties. Any alteration, addition, improvement or other change to the Premises, Relevant Assets or Additional Improvements (and, if agreed by Lessee and Lessor, to the Shared Access Facilities) by Lessee shall be made in a good and workmanlike manner and in accordance with all applicable Laws. The Relevant Assets and all Additional Improvements shall remain the property of Lessee and shall be removed by Lessee within one (1) year after termination of this Lease (provided that such can be removed by Lessee without unreasonable damage or harm to the Premises) or, at Lessee’s option exercisable by notice to Lessor, surrendered to Lessor upon the termination of this Lease. Lessee shall not have the right or power to create or permit any lien of any kind or character on the Premises by reason of repair or construction or other work. In the event any such lien is filed against the Premises, Lessee shall cause such lien to be discharged or bonded within thirty (30) days of the date of filing thereof.

Time is Money Join Law Insider Premium to draft better contracts faster.