Commercial Operation Date Deadline Sample Clauses

Commercial Operation Date Deadline. The Commercial Operation Date shall occur (i) no earlier than the PUC Approval Date described in Section 25.14 (PUC Approval), and (ii) no later than the later of December 30, 2011 or PUC Approval Date. A failure to achieve the Commercial Operation Date within the time specified in Section 8.1A(1) (Events of Default, Default by the Seller) shall be treated in accordance with the provisions of Section 2.4B (Failure to Meet Commercial Operation Date Deadline) applicable to such failure.
AutoNDA by SimpleDocs
Commercial Operation Date Deadline. If the System has not achieved Commercial Operation by September 8, 2017, subject to a day-for-day extension for any Material Event or cure as described below, and only until the System has achieved Commercial Operation, Buyer may terminate this PPA without penalty subject to Section 2.5 by providing Seller with notice pursuant to Section 16.1. Alternatively, in the event that the System has not achieved Commercial Operation by September 8, 2017, the Parties may mutually agree to amend this Agreement.
Commercial Operation Date Deadline. The Commercial Operation Date shall occur no later than (i) [__], or (ii) [__] months after receipt of the PUC Approval Order described in Section 25.12 (PUC Approval), whichever is later (the “Commercial Operation Date Deadline”), unless deferred pursuant to Section 3.3(B) (Company Right to Defer the Commercial Operation Date). A failure to achieve the Commercial Operation Date by the Commercial Operation Date Deadline shall be treated in accordance with the provisions of Section 2.4(B) (Failure to Meet Commercial Operation Date Deadline).
Commercial Operation Date Deadline. The Commercial Operation Date shall occur no later than the date set forth in Attachment B (Milestone Events) (the “Commercial Operation Date Deadline”). A failure to achieve the Commercial Operation Date by the Commercial Operation Date Deadline shall be treated in accordance with the provisions of Section 2.4(B) (Failure to Meet Commercial Operation Date Deadline).
Commercial Operation Date Deadline. A condition or event of Force Majeure affecting the achievement of the Commercial Operation Date Deadline shall not relieve Seller from liability for any of the following: Milestone Delay Damages under Section 2.4(A)(1)(b) (Milestone Delay Damages), Daily Delay Damages under Section 2.4(B)(3) (Daily Delay Damages and Termination Right) and Section 9.4(C) (Daily Delay), or Pre-COD Termination Damages for early termination under Section 2.4(A)(1)(c) (Termination and Pre-COD Termination Damages) and Section 9.3(A) (Pre-COD Termination Damages), although such a condition or event of Force Majeure shall, if and for so long as the conditions or event of Section 18.2(A) (No Liability) are satisfied, have the effect of deferring such liability to the extent of the applicable grace period provided in Section 2.4(B)(1)(a) (Failure to Meet Commercial Operation Date Deadline, Force Majeure).
Commercial Operation Date Deadline. Construction of the Interconnection Facilities and Interconnection Acceptance Test shall be completed in accordance with the requirements of this Interconnection Agreement and the PPA by 60-days prior to the Commercial Operation Date Deadline, as extended for Force Majeure, if applicable.

Related to Commercial Operation Date Deadline

  • Commercial Operation Date 6.4.1 The SPV shall ensure that the Project Commercial Operation Date is achieved on or prior to the Scheduled Commercial Operation Date. The SPV shall provide a written notice to MSEDCL at least 30 (thirty) days in advance intimating MSEDCL of the proposed date on which the Commercial Operation Date of a Unit or the Project is proposed to be achieved.

  • Commercial Operation On or before December 31, 2023, Interconnection Customer must demonstrate commercial operation of all generating units. Demonstrating commercial operation includes achieving Initial Operation in accordance with Section 1.4 of Appendix 2 to this ISA and making commercial sales or use of energy, as well as, if applicable, obtaining capacity qualification in accordance with the requirements of the Reliability Assurance Agreement Among Load Serving Entities in the PJM Region.

  • Final Completion Date Final Completion for the Work as defined in Article 6.1.3 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by September 30, 2022.

  • Post-Commercial Operation Date Testing and Modifications Each Party shall at its own expense perform routine inspection and testing of its facilities and equipment in accordance with Good Utility Practice as may be necessary to ensure the continued interconnection of the Large Generating Facility with the Participating TO’s Transmission System in a safe and reliable manner. Each Party shall have the right, upon advance written notice, to require reasonable additional testing of the other Party’s facilities, at the requesting Party’s expense, as may be in accordance with Good Utility Practice.

  • Substantial Completion Date Substantial Completion of the Work as defined in Article 6.1.2 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by July 31, 2022.

  • Termination Date Determination Seller will not designate the Termination Date (as defined in the Receivables Sale Agreement), or send any written notice to Originator in respect thereof, without the prior written consent of the Agent, except with respect to the occurrence of such Termination Date arising pursuant to Section 5.1(d) of the Receivables Sale Agreement.

  • Start Date The parental leave must begin no later than 52 weeks after the day the child is born or comes into the custody, care and control of the parent for the first time for provincially or federally regulated employees. The parental leave of an employee who takes a pregnancy leave must begin when the pregnancy leave ends unless the child has not yet come into the care and control of the parent for the first time.

  • Project Completion Date It is agreed between the Parties that the Project Completion Date is <END DATE, YEAR>. If the Project is not completed by such date then, subject to an amendment agreed to between the Parties, Alberta Innovates may elect to terminate this Investment Agreement. In such event, Alberta Innovates will notify the Applicant of its decision to terminate as soon as reasonably practical and shall advise the Applicant of the effective date of termination. Alberta Innovates will have no liability or obligation to reimburse the Applicant for any Project Costs incurred after the effective date of termination and may require the Applicant to return any portions of the Investment which were spent on Ineligible Expenses. Additionally, any portion of the Investment not used and accounted for in accordance with this Agreement as of the Project Completion Date or earlier termination is repayable by the Applicant to AI at AI’s request.

  • Termination Date, Etc “Termination Date” shall mean in the case of the Executive’s death, his date of death, or in all other cases, the date specified in the Notice of Termination subject to the following:

  • Completion Date The Work under this Contract shall be completed by midnight of the date required in the Contract as the Material Completion and Occupancy Date unless extended by approved requests for extension of time.