Sequences of construction or installation Sample Clauses

Sequences of construction or installation. The Contractor designs, supplies and installs the Works to comply with the Sectional Completion Dates and the commissioning sequence stated in the Employer’s Works Information.
AutoNDA by SimpleDocs
Sequences of construction or installation. Only prescribe sequences of work where absolutely necessary such as when Contractor has to give access to Others (without take over) and for technical reasons such as under tidal conditions and in rivers.
Sequences of construction or installation. To be supplied by contractor as part of the program that needs to be submitted to the project manager for approval prior to commencing construction
Sequences of construction or installation. Not Applicable
Sequences of construction or installation. As per the approved construction programme and in conjunction with the Quality Control Plan.
Sequences of construction or installation. Sequencing of construction activities are established as part of the Work Plan development and submitted with the Work Plan. Other modifications and maintenance of equipment will be taking place by Others on the Site during the Implementation of the works of this contract. The Project Manager will sequence the activities of the Contractor and Others to ensure best utilisation of space, resources and equipment.
Sequences of construction or installation. Any modification to the existing hoppers can only be done while the xxxxxx is not in operation. The fabric filter plant is divided in cells which can be isolated individually while the rest of the plant is still in operation. The Contractor performs all the work on a specific cell at the same time to minimise the impact on the operations of the plant.
AutoNDA by SimpleDocs
Sequences of construction or installation. The Employer requests that the testing in critical areas be prioritised. Interface with others is required to ensure that the works progress in a sequenced manner. The schedule milestones for phasing will be determined by the Employer and the Contractor post contract award.
Sequences of construction or installation. (1) The sequence of the works is to be accepted by the Project Manager.
Sequences of construction or installation. The Contractor is to provide the Project Manager with the programme in MS Project format, showing the sequence of construction activities from beginning to the end of the construction project. Should the programme or the sequence of activities change, the Contractor needs to notify and provide the Project Manager with the revised programme, for approval by the Project Manager.