Capital Spares Sample Clauses

Capital Spares. Not later than three hundred sixty days (360) Days prior to the Guaranteed Substantial Completion Date, Contractor shall deliver to Owner a detailed list of all manufacturer and Contractor-recommended capital spare parts for operating and maintaining all Equipment (including components and systems of such Equipment) for two (2) years following Substantial Completion (“Capital Spare Parts”). Within thirty (30) Days from Contractor’s submission of such list, Owner shall specify in writing which items on the list it wishes Contractor to purchase and whether such items are requested to be delivered to the Site prior to Substantial Completion or Final Completion. Within a further thirty (30) Days, Contractor shall confirm the extent to which it is able to comply with Owner’s request and shall submit to Owner the final list of Capital Spare Parts to be purchased. The list of Capital Spare Parts to be procured by Contractor and delivered to Owner (“Capital Spare Parts List”) shall be mutually agreed upon via a Change Order. Notwithstanding anything to the contrary in this Agreement, delivery of all Capital Spare Parts is not a condition precedent to Substantial Completion, and Contractor shall not be deemed in default if such Capital Spare Parts are not delivered to the Site prior to Substantial Completion. Prior to and as a condition to achieving Final Completion, Contractor shall deliver to the Site all Capital Spare Parts required to be delivered to the Site prior to Final Completion as set forth in the Capital Spare Parts List. The Capital Spare Parts List shall include all information specified in Attachment 23. A Provisional Sum for the cost of Capital Spare Parts is included in the Contract Price as set forth in Attachment 31.
AutoNDA by SimpleDocs
Capital Spares. Unit Price If Unit Price If Recommended Purchased With Supplied At Item Description Quantity Main Order Later Date LGL EQUIPMENT SUPPLY TENDER AVAILABILITY GUARANTEES Equipment Tender # and Description Tenderer’s Name: Equipment Availability Guarantees Year 1 % Year 2 % Year 3 % Year 4 % Year 5 % Compensation for availability guarantee(s) not being met: Conditions of availability guarantees(s): LGL EQUIPMENT SUPPLY TENDER SERVICE & SUPPORT Equipment Tender # and Description Tenderer’s Name: Technical On-Site Personnel (if Applicable) Reimbursable Sum per Person from X to Cairns or return (detail point of origin) 0.00 Daily Rates for technical on-Site personnel — detail skills/trades 0.00 Equipment (List required equipment) 0.00 Location of Representation Number of Representatives Estimated length of stay Number/Frequency of visits Additional Items/Details Number of Technical On-Site Personnel days available at no cost to Buyer Emergency Contact for Technical On-Site requirements (Provide details)
Capital Spares. The Contract Price includes a $1.9 Million allowance for capital spares. Capital spares purchases shall be subject to NSPI’s approval, not to be unreasonably withheld or delayed.
Capital Spares. All capital spares shall have been procured and stored at the agreed locations in accordance with the Project Equipment Supply Agreement.

Related to Capital Spares

  • Capital Equipment Collaborator’s commitment, if any, to provide IC with capital equipment to enable the research and development activities under the Research Plan appears in Appendix B. If Collaborator transfers to IC the capital equipment or provides funds for IC to purchase it, then IC will own the equipment. If Collaborator loans capital equipment to IC for use during the CRADA, Collaborator will be responsible for paying all costs and fees associated with the transport, installation, maintenance, repair, removal, or disposal of the equipment, and IC will not be liable for any damage to the equipment.

  • Capital Budget Any amendment that is mutually agreed upon shall be set forth in writing and signed by both parties. It is acknowledged by Owner that capital expenditures required as a result of an emergency situation shall not reduce amounts available pursuant to the Capital Budget or otherwise hereunder, other than to the extent a Capital Budget item is subsumed within the capital expenditures required as a result of the occurrence of the emergency;

  • Capital Improvements The Department has identified the following possible opportunities for Capital Improvements:

  • New Equipment Where new types of equipment and/or operations, for which rates of pay are not established by this Agreement, are put into use after the ratification date of this Agreement within operations covered by this Agreement, rates governing such operations shall be subject to negotiations between the parties. This paragraph shall apply to all new types of equipment including office and clerical equipment. In the event agreement cannot be reached within sixty (60) days after the date such equipment is put into use, the matter may be submit- xxx to the National Grievance Committee for final disposition. Rates agreed upon or awarded shall be effective as of the date equipment is put to use.

  • Rental Equipment 7.1 We will at all times own all Rental Equipment supplied to you. You will not let, sell, charge, assign, sub-license or allow a third party to use the Rental Equipment nor remove any labels, and shall not prejudice our rights in the Rental Equipment in any way. We may replace the Rental Equipment from time to time either with your prior consent or provided that the replacement Rental Equipment is of a specification that is at least equal to the Rental Equipment originally supplied and such change does not materially disrupt the provision of the Services.

  • Meeting Space and Facilities The Employer’s offices and facilities may be used by the Union to hold meetings, subject to the agency’s policy, availability of the space and with prior authorization of the Employer.

  • Office Space, Equipment and Facilities Provide such office space, office equipment and office facilities as are adequate to fulfill the Adviser’s obligations hereunder.

  • Capital Expenditure Make or incur any Capital Expenditure if, after giving effect thereto, the aggregate amount of all Capital Expenditures by Borrower in any fiscal year would exceed the amount set forth on the Schedule;

  • Construction Contract; Cost Budget Prior to execution of a construction contract, Tenant shall submit a copy of the proposed contract with the Contractor for the construction of the Tenant Improvements, including the general conditions with Contractor (the “Contract”) to Landlord for its approval, which approval shall not be unreasonably withheld, conditioned or delayed. Following execution of the Contract and prior to commencement of construction, Tenant shall provide Landlord with a fully executed copy of the Contract for Landlord’s records. Prior to the commencement of the construction of the Tenant Improvements, and after Tenant has accepted all bids and proposals for the Tenant Improvements, Tenant shall provide Landlord with a detailed breakdown, by trade, for all of Tenant’s Agents, of the final estimated costs to be incurred or which have been incurred in connection with the design and construction of the Tenant Improvements to be performed by or at the direction of Tenant or the Contractor (the “Construction Budget”), which costs shall include, but not be limited to, the costs of the Architect’s and Engineers’ fees and the Landlord Coordination Fee. The amount, if any, by which the total costs set forth in the Construction Budget exceed the amount of the Tenant Improvement Allowance is referred to herein as the “Over Allowance Amount”. In the event that an Over-Allowance Amount exists, then prior to the commencement of construction of the Tenant Improvements, Tenant shall supply Landlord with cash in an amount equal to the Over-Allowance Amount. The Over-Allowance Amount shall be disbursed by Landlord prior to the disbursement of any of the then remaining portion of the Tenant Improvement Allowance, and such disbursement shall be pursuant to the same procedure as the Tenant Improvement Allowance. In the event that, after the total costs set forth in the Construction Budget have been delivered by Tenant to Landlord, the costs relating to the design and construction of the Tenant Improvements shall change, any additional costs for such design and construction in excess of the total costs set forth in the Construction Budget shall be added to the Over-Allowance Amount and the total costs set forth in the Construction Budget, and such additional costs shall be paid by Tenant to Landlord immediately as an addition to the Over-Allowance Amount or at Landlord’s option, Tenant shall make payments for such additional costs out of its own funds, but Tenant shall continue to provide Landlord with the documents described in items (i), (ii), (iii) and (iv) of Section 2.2.2.1 of this Tenant Work Letter, above, for Landlord’s approval, prior to Tenant paying such costs. All Tenant Improvements paid for by the Over-Allowance Amount shall be deemed Landlord’s property under the terms of the Lease.

  • Office Equipment The Client must not install any cabling, IT or telecom connections without the Provider’s consent, which the Provider may refuse at its absolute discretion. As a condition to the Provider’s consent, the Client must permit the Provider to oversee any installations (for example IT or electrical systems) and to verify that such installations do not interfere with the use of the accommodation(s) by other Clients or the Provider or any landlord of the building.