Requirements for Substantial Completion Sample Clauses

Requirements for Substantial Completion. Substantial Completion of the required Work shall occur when, in the sole determination of the Director, all of the conditions set forth below have been satisfied.
AutoNDA by SimpleDocs
Requirements for Substantial Completion. The Work (or a designated portion thereof) shall be deemed Substantially Completed on the date when all of the following events or conditions shall have occurred:
Requirements for Substantial Completion. (i) Phase I of the Work shall be deemed Substantially Completed (“Substantial Completion”) on the date when such Work shall be sufficiently completed and all of the following shall have occurred: (a) Owner may use and occupy the Phase I area (as set forth in Exhibit “H”); (b) only minor Punch List items (as such term is defined in Section 7.02(bb) hereof), if any, remain incomplete provided they do not interfere with such use and occupancy; (c) a temporary certificate of occupancy (“TCO”) shall have been issued by the appropriate local governmental authority for the Phase I area, unless such TCO is not issued for reasons outside Construction Manger’s reasonable control; and (d) Construction Manager has performed all services and provided all documentation necessary to enable the commencement or continuationof commissioning and validation activities.
Requirements for Substantial Completion. The following are the conditions precedent for the Project to achieve Substantial Completion: the Project is Mechanically Complete; the [_________] Tests have been Successfully Run; Contractor shall have paid all Delay Liquidated Damages calculated pursuant to Section 15.1.1; Owner has received all Contractor Deliverables which are either necessary for the operation of the Project or are required to be delivered by the applicable Substantial Completion Date as set forth in the Contractor Deliverables Table;
Requirements for Substantial Completion. The Design Consultant and the Authority shall determine the date that the Contractor achieves Substantial Completion for the Project. In order to achieve Substantial Completion, the Contractor must have achieved the following on the Project: (i) all essential requirements of the Contract Documents have been performed so that the purpose of the Contract Documents have been accomplished, (ii) a Temporary Certificate of Occupancy (or Temporary Certificate of Acceptance, if applicable) has been issued by the Department of Community Affairs, (iii) a Punchlist has been created by the Design Consultant and approved by the Authority, (iv) [deliberately omitted] (v) there are no material omissions or technical defects or deficiencies, identified by the Authority or the CM or Design Consultant, and (vi) the Project is one- hundred percent (100%) ready for occupancy in accordance with its intended use.
Requirements for Substantial Completion. (i) The Work shall be deemed Substantially Completed (“Substantial Completion”) on the date when such Work shall be sufficiently completed and all of the following shall have occurred: (a) Owner may use and occupy the the Work; (b) only minor Punch List items (as such term is defined in Section 7.02(bb) hereof), if any, remain incomplete provided they do not interfere with such use and occupancy; (c) a temporary certificate of occupancy (“TCO”) shall have been issued by the appropriate local governmental authority for the Work, unless such TCO is not issued for reasons outside Construction Manger’s reasonable control; and (d) Construction Manager has performed all services and provided all documentation necessary to enable the commencement or continuation of commissioning and validation activities.

Related to Requirements for Substantial Completion

  • Upon Substantial Completion of the Work or designated portion thereof and upon application by the Contractor and certification by the Architect, the State shall make payment, reflecting adjustment in retainage, if any, for such Work or portion thereof, as provided in the Contract Documents.

  • Substantial Completion “Substantial Completion” means the stage in the progress of the Work when the Work, or designated portions thereof, may still require minor modifications or adjustments but, in the Owner’s opinion, the Work has progressed to the point such that all parts of the Work under consideration are fully operational and usable for intended purposes, as evidenced by a Certificate of Substantial Completion approved by the Owner. If a Certificate of Occupancy is required by public authorities having jurisdiction over the Work, said certificate shall be issued before the Work or any portion thereof is considered substantially complete. When the Contractor considers that the Work, or a portion thereof which the Owner agrees to accept separately, is substantially complete, the Contractor shall notify Owner’s Designated Representative (sometimes referred to as the “ODR”) and request a determination as to whether the Work or designated portion thereof is substantially complete. If the ODR does not consider the Work substantially complete, the ODR will notify the Contractor giving reasons therefore. Failure on the Owner’s part to list a reason does not alter the responsibility of the Contractor to complete all Work in accordance with the terms of this Agreement. After satisfactorily completing items identified by Owner’s Designated Representative, the Contractor shall then submit another request for the ODR to determine Substantial Completion. If The ODR considers the Work substantially complete, The ODR will prepare and deliver a certificate of Substantial Completion which shall establish the date of Substantial Completion, shall include a punch list of items to be completed or corrected before final completion and final payment, shall establish the time within which the Contractor shall finish the punch list, and shall establish responsibilities of the Owner and the Contractor for security, maintenance, heat, utilities, damage to the Work, warranty and insurance. Failure to include an item on the punch list does not alter the responsibility of the Contractor to complete all Work in accordance with the terms and conditions of this Agreement. The certificate of Substantial Completion shall be signed by the Owner and the Contractor to evidence acceptance of the responsibilities assigned to them in such certificate. Substantial Completion (as defined in this agreement) for all stages of the Work shall be achieved on or before the following Substantial Completion date: DATE FOR SUBSTANTIAL COMPLETION: TBD Under no circumstances will the time for Substantial Completion exceed this date without a written amendment to this Agreement. THE TIMES SET FORTH IN THE CONSTRUCTION DOCUMENTS ARE AN ESSENTIAL ELEMENT OF THE AGREEMENT. TIME LIMITS STATED IN THE CONTRACT DOCUMENTS ARE OF THE ESSENCE OF THIS AGREEMENT.

  • Certificate of Substantial Completion The Date of Substantial Completion of the Work or designated portion thereof is the Date certified by the City when construction is sufficiently complete, in accordance with the Contract Documents, so the City of Roanoke, Virginia (City or Owner) can occupy or utilize the Work or designated portion thereof for the use for which it is intended, as expressed in the Contract Documents. ITB NO.: PROJECT: CONTRACTOR: PROJECT OR DESIGNATED PORTION SHALL INCLUDE: . The Work or portion thereof designated above performed under this Contract has been reviewed and found to be substantially complete. The Date of Substantial Completion of the Project or portion thereof designated above is hereby established as . The City will assume possession thereof at a.m./p.m. on that date. A list of items ("punch list"), prepared by the A/E and/or Director, Department of Public Works, to be completed or corrected by the Contractor, is attached hereto. The failure to include any items on such list does not alter the responsibility of the Contractor to complete all Work in accordance with the Contract Documents. The Contractor will complete any portion of the Work that is not substantially complete and will complete or correct the work on the punch list in accordance with the Contract Documents. The establishment of a date of substantial completion and/or the acceptance of the Work or designated portion thereof does not relieve the Contractor of any responsibility for any faulty materials or workmanship or operate to relieve the Contractor or its Surety from any obligation under the Contract with the City or the Performance Bond or Labor and Material Payment Bond. This Certificate is subject to the terms and conditions of the Contract Documents, including but not limited to Section 20.8 of the General Conditions. Contractor By Date City of Roanoke, Virginia City By Date CITY OF ROANOKE, VIRGINIA AFFIDAVIT OF PAYMENT OF CLAIMS By: (Insert Exact Name and Address of Firm) This day personally appeared before me, , a Notary Public in and for the City (County) of , and, being by me first duly sworn states that all subcontractors and suppliers of labor and materials have been paid all sums due them for work performed or materials furnished in the performance of the Contract between the City of Roanoke, Virginia, and ,Contractor, dated , 20 , for or arrangements have been made by the Contractor satisfactory to such subcontractors and suppliers with respect to the payment of such sums as may be due from the Contractor to the subcontractors and suppliers. CONTRACTOR: BY: PRINTED OR TYPED NAME AND TITLE: COMMONWEALTH OF VIRGINIA CITY/COUNTY OF I, , a Notary Public in and for the Commonwealth of Virginia, do hereby certify that , whose name is signed to the foregoing, has subscribed, sworn to and acknowledged the same before me this day of , 20 . Seal: Notary Public Registration #: My Commission Expires: CITY OF ROANOKE, VIRGINIA

  • Substantial Completion Date Substantial Completion of the Work as defined in Article 6.1.2 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by July 31, 2022.

  • Completion of Improvements Within 90 days of completion of any construction herein permitted, Company will cause to be prepared and delivered to Authority record documents as required under the Tenant Work Permit process, including but not limited to as-builts, legal descriptions, boundary surveys, and certified final cost of construction. The submission of record document electronic media will be in accordance with Authority’s Standard Procedure for computer aided design and drafting and drawings, as may be revised from time to time.

  • Additional Requirements for Sleeping Rooms The Contractor shall provide departing Attendees a secured area for storing belongings.

  • Completion of Repairs Borrower will commence any Repairs as soon as practicable after the date of this Loan Agreement and will diligently proceed with and complete such Repairs on or before the Completion Date. All Repairs and Capital Replacements will be completed in a good and workmanlike manner, with suitable materials, and in accordance with good building practices and all applicable laws, ordinances, rules, regulations, building setback lines and restrictions applicable to the Mortgaged Property. Borrower agrees to cause the replacement of any material or work that is defective, unworkmanlike or that does not comply with the requirements of this Loan Agreement, as determined by Lender.

  • Final Completion The full and final completion of all Work in accordance with the Contract Documents.

  • DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION § 3.1 The date of commencement of the Work shall be: (Check one of the following boxes.) [ « » ] The date of this Agreement. [ « » ] A date set forth in a notice to proceed issued by the Owner. [ « » ] Established as follows: (Insert a date or a means to determine the date of commencement of the Work.) « » If a date of commencement of the Work is not selected, then the date of commencement shall be the date of this Agreement.

  • Upon completion of the Project the Recipient shall make a full and complete accounting to the OPWC of the Eligible Project Cost.

Time is Money Join Law Insider Premium to draft better contracts faster.