ADJUSTMENTS FOR CHANGE IN SCOPE Sample Clauses

ADJUSTMENTS FOR CHANGE IN SCOPE. APS may order changes in the Work within the general scope of the Work consisting of additions, deletions or other revisions. No claim may be made by the Contractor that the scope of the Work or of the Contractor's services has been changed requiring adjustments to the amount of compensation due the Contractor unless such adjustments have been made by a written amendment to the Contract signed by APS and the Contractor. If the Contractor believes that any particular work is not within the scope of the Work or is a material change or otherwise will call for more compensation to the Contractor, the Contractor must immediately notify the Project Officer after the change or event occurs and within ten (10) calendar days thereafter must provide written notice to the Project Officer. The Contractor’s notice must provide to the Project Officer the amount of additional compensation claimed, together with the basis therefore and supportive documentation for the amount. The Contractor will not be compensated for performing any work unless a Proposal complying with this subSection has been submitted in the time specified above and a written amendment has been signed by APS and the Contractor and an APS Purchase Order is issued covering the cost of the services to be provided under the amendment.
AutoNDA by SimpleDocs
ADJUSTMENTS FOR CHANGE IN SCOPE. The County may order additions, deletions and other revisions in the Work within the general scope of the project. If the Contractor believes that any change is not within the scope of the project or warrants additional compensation or additional time, the Contractor must notify the Project Officer as soon as the County requests the change; and the Contractor must then provide written notice of its position to the Project Officer within ten calendar days. The Contractor’s notice must detail and document the basis for the claimed amount of additional compensation or time. The Contractor will not receive any additional compensation or time pursuant to this paragraph unless the parties execute a written Contract amendment and the County issues a purchase order consistent with the amendment. This provision is applicable to all contracts. ACCESS TO RECORDS AND REPORTS DHS Standard Terms and Conditions v.3.0 (2013) Access to Records - The following access to records requirements apply to this Contract:
ADJUSTMENTS FOR CHANGE IN SCOPE. APS may order changes in the Work within the general scope of the Work consisting of additions, deletions, or other revisions. No claim may be made by the Contractor that the scope of the Work or of the Contractor's services has been changed requiring adjustments to the amount of compensation due the Contractor unless such adjustments have been made by a written amendment to the Contract signed by APS and the Contractor. If the Contractor proceeds with what it considers to be additional or changed Work for which it is entitled to additional compensation prior to either (i) receiving a written amendment to the Contract signed by APS and the Contractor or (ii) having submitted a timely claim for additional compensation and thereafter receiving a written directive from APS to proceed with the Work, any claim for additional compensation for such Work shall be conclusively barred. If the Contractor believes that any particular work is not within the scope of the Work or is a material change or otherwise will call for more compensation to the Contractor, the Contractor must immediately notify the Project Officer after the change or event occurs and within ten (10) calendar days thereafter must provide written notice to the Project Officer. The Contractor’s notice must provide to the Project Officer the amount of additional compensation claimed, together with the basis therefore and supportive documentation for the amount. The Contractor will not be compensated for performing any work unless a Proposal complying with this subsection has been submitted in the time specified above and a written amendment to the Contract has been signed by APS and the Contractor and a Purchase Order is issued covering the cost of the services to be provided under the Contract Amendment.
ADJUSTMENTS FOR CHANGE IN SCOPE. The County may order additions, deletions and other revisions in the Work within the general scope of the project. If the Contractor believes that any change is not within the scope of the project or warrants additional compensation, the Contractor must notify the Project Officer as soon as the County requests the change; and the Contractor must then provide written notice of its position to the Project Officer within ten calendar days. The Contractor’s notice must detail and document the basis for the claimed amount of additional compensation. The Contractor will not receive any additional compensation pursuant to this paragraph unless the parties execute a written Contract amendment, and the County issues a purchase order consistent with the amendment.
ADJUSTMENTS FOR CHANGE IN SCOPE. The County may order changes in the work as long as such changes remain within the scope of the work. If the Contractor believes that any work is not within the scope of the project, is a material change, or will otherwise call for additional compensation, then the Contractor must immediately notify the Project Officer in writing of this belief. If the County agrees with such belief, an adjustment will be made to the Contract by formal written Amendment. The Contractor shall not receive additional compensation until this written amendment has been signed by both Parties and a County purchase order covering the additional cost is issued. If it is determined that the work in question is within the scope of the Contract, then the Contractor shall continue work.
ADJUSTMENTS FOR CHANGE IN SCOPE. APS may order changes in the Work within the general scope of the Work consisting of additions, deletions or other revisions. No claim may be made by the Contractor that the scope of the Work or of the Contractor's services has been changed requiring adjustments to the amount of compensation due the Contractor unless such adjustments have been made by a written amendment to the Contract signed by APS and the Contractor. If the Contractor believes that any particular work is not within the scope of the Work or is a material change or otherwise will call for more compensation to the Contractor, the Contractor must immediately notify the Project Officer after the change or event occurs and within ten

Related to ADJUSTMENTS FOR CHANGE IN SCOPE

  • Payment for Change of Scope Payment for Change of Scope shall be made in accordance with the payment schedule specified in the Change of Scope Order.