Procedure and Protest Sample Clauses

Procedure and Protest. A Change Order approved by the City may be issued to the Contractor at any time. Should the Contractor disagree with any terms or conditions set forth in an approved Change Order which he has not executed, he shall submit a written protest to the City Engineer within fifteen (15) working days after the receipt of such approved Change Order. The protest shall state the points of disagreement, contract specification references, and, if possible, the quantities and costs involved. If a written protest is not submitted, payment will be made as set forth in the approved Change Order, and such payment shall constitute full compensation for all work included therein or required thereby. Such un-protested approved Change Order will be considered an executed Change Order as that term is used in these Special Provisions. Where the protest concerning an approved Change Order relates to compensation, the compensation payable for the work specified or required by said Change Order to which such protest relates will be determined as provided in Section 3-2 of these Special Provisions. The Contractor shall keep full and complete records of the costs of such work and shall permit the City Engineer to have such access thereto as may be necessary to assist in the determination of the compensation payable for such work. Where the protest concerning an approved Change Order relates to the adjustment of the Contract Time for the completion of the work, the time to be allowed therefore will be determined as provided in Section 6-6 of the Standard Specifications. Proposed Change Orders may be presented to the Contractor for his consideration prior to approval by the City. If the Contractor signifies his acceptance of the terms and conditions of such proposed Change Order by executing such document, and if such Change Order is approved by the City and issued to the Contractor, payment in accordance with the provisions as to compensation therein set forth shall constitute full compensation for all work included therein or required thereby. A Change Order executed by the Contractor and approved by the City Engineer is an executed Change Order as that term is used in these Special Provisions. An approved Change Order shall supersede a proposed, but unapproved, Change Order covering the same work.
AutoNDA by SimpleDocs
Procedure and Protest. A Contract Change Order approved by the ENGINEER may be issued to CONTRACTOR at any time. Should CONTRACTOR disagree with any terms or conditions set forth in an approved Contract Change Order which has not been executed, CONTRACTOR shall submit a written protest to the ENGINEER. This written protest shall be submitted within 15 days after the receipt of such approved Contract Change Order. The protest shall state the points of disagreement, and, if possible, the Contract Specification references, quantities, and costs involved. If a written protest is not submitted, payment will be made as set forth in the approved Contract Change Order. Such payment shall constitute full compensation for all Work included therein or required thereby. Such unprotested approved Contract Change Orders will be considered as executed Contract Change Orders as that term is used in these Specifications, and in particular in Sections 4-3.2 to 4-3.4

Related to Procedure and Protest

  • Procedure and Time Limits Step Two 100 If the grievance is not adjusted at Step One, the Faculty Member or group of Faculty Members or the Association may, within five (5) working days of the Step One answer, which shall also be concurrently provided to the Assistant Vice President for Academic Affairs, appeal the grievance, in writing, to the appropriate Xxxx or other designated administrative agent, setting forth his/her (their) objections to the Step One answer. Upon receipt of the written appeal or at the signed written notice when initiation is at Step Two, the Xxxx or other designated administrative agent shall promptly arrange a meeting through the EMU-AAUP office to discuss the grievance with the grievant(s), the Association’s Grievance Officer, and such other persons as he/she deems appropriate. It is not appropriate at this level for the grieved department head or other grieved administrative agent involved at the Step One grievance hearing to be present at a Step Two grievance hearing. This discussion shall be completed within seven (7) working days after the filing of the grievance at Step Two. If the grievance is adjusted at this Step to the satisfaction of the grievant(s), the Association’s Grievance Officer and the Xxxx or other designated administrative agent, the adjustment will be reduced to writing, signed by the parties, and a copy provided to each signatory, the EMU-AAUP office and the Assistant Vice President for Academic Affairs. If there is not adjustment, the Xxxx or other designated administrative agent must present his/her reasons in writing to the grievant(s) with a copy to the EMU-AAUP office and the Assistant Vice President for Academic Affairs. The Xxxx or administrative agent shall reduce the adjustment to writing or provide the reasons for denial of the grievance in writing to the grievant(s) within five (5) working days following the Step Two meeting. If, within five (5) working days of receipt thereof, XXX’s Assistant Vice President for Academic Affairs, or his/her designee, serves the Association’s Grievance Officer with written notice of objection to the adjustment on the grounds that the adjustment adds to, subtracts from, or modifies the terms of this agreement, said adjustment shall be deemed null and void and the grievance remanded for further review at Step Two. Within seven (7) working days of notice of remand, the parties’ Step Two representatives and the grievant(s) shall complete their review. The grievance shall thereafter be processed, adjusted or appealed within the timelines and procedures as set forth in this Grievance Procedure.

  • GRIEVANCE PROCEDURE AND ARBITRATION 8.01 For purposes of this Agreement, a grievance is defined as a difference arising between the parties relating to the interpretation, application, administration or alleged violation of the Agreement including any question as to whether a matter is arbitrable.

  • Disputes and Governing Law This Agreement shall be construed in accordance with the laws of the PRC. Any disputes that arise in connection with this Agreement shall be litigated in courts located within the Pudong New Area, Shanghai, the PRC.

  • Resolution of disputes and grievances (a) For the purpose of this clause 14, a dispute includes a grievance.

  • Nature and Scope of Obligations 1. The Parties recall their obligation to ensure the adequate and effective implementation of the international agreements dealing with intellectual property to which they are parties, including the WTO Agreement on Trade-Related Aspects of Intellectual Property Rights (“the TRIPS Agreement”). The provisions of this Chapter shall complement and further specify the rights and obligations between the Parties under the TRIPS Agreement and other international agreements in the field of intellectual property.

  • DISPUTES AND GRIEVANCES Section 1. This Agreement is intended to provide close cooperation between management and labor. Each of the Unions will assign a representative to this Project for the purpose of completing the construction of the Project economically, efficiently, continuously, and without interruptions, delays, or work stoppages.

  • Disputes and Arbitration 22. Any dispute concerning a question of fact arising under this contract shall be disposed of by good faith negotiation between duly authorized representatives of the County, the Office of the State Auditor, and the Firm. Such a resolution shall be reduced to writing and a copy thereof mailed or furnished to the Firm and shall be final and conclusive. If a resolution cannot be reached, the Firm shall mail or furnish to the Board of Supervisors of the County and the Office of the State Auditor a written request for review. The Firm shall be afforded an opportunity to be heard and to offer evidence in support of his/her/its position on the issue in dispute and under review. The review will be handled under a three (3) person panel for arbitration composed of the Deputy State Auditor, the Director of Technical Assistance and the Director of the Financial and Compliance Audit Division. The decision of the Arbitration Panel of the Office of the State Auditor on the review shall be final and conclusive unless determined by a court of competent jurisdiction in Xxxxx County, State of Mississippi, to have been fraudulent, capricious, or so grossly erroneous as necessarily to imply bad faith, or not be supported by substantial evidence. Pending final decision of a dispute hereunder, the Firm shall proceed diligently with the performance of the duties and obligations of the contract.

  • Arbitration and Governing Law If a dispute arises out of or relates to this contract, or the breach thereof, and if the dispute cannot be settled through negotiation, the parties agree first to try in good faith to settle the dispute by mediation administered by the American Arbitration Association under its Commercial Mediation Procedures before resorting to arbitration, litigation, or some other dispute resolution procedure. If they do not reach such solution within a period of 60 days, then, upon notice by either party to the other, all disputes, claims, questions, or differences shall be finally settled by arbitration administered by the American Arbitration Association in accordance with the provisions of its Commercial Arbitration Rules. This Agreement and the legal relations among the Parties hereto shall be governed by and construed in accordance with the laws of the State of Florida, without regard to its conflict of law doctrine. The Parties agree that the venue for the resolution of all disputes arising under the terms of this Agreement and the transactions contemplated herein will be the County of Pinellas, State of Florida.

  • GRIEVANCE AND ARBITRATION Casual employees have access to the grievance and arbitration procedures. (Reference Article 9 - Grievances and Article 10 - Arbitration.)

  • Disclosure and Use 20.2.1 Each Receiving Party agrees that, from and after the Effective Date:

Time is Money Join Law Insider Premium to draft better contracts faster.