Outside Substantial Completion Date definition

Outside Substantial Completion Date means, with respect of any Property, June 30, 2001, subject to extension of such date on account of force majeure.
Outside Substantial Completion Date means, with respect of any Property, ninety (90) days prior to the Required Completion Date (as defined in the DCCRO encumbering such Property) inclusive of any extension of such date on account of force majeure or otherwise pursuant to the terms of the DCCRO encumbering such Property.
Outside Substantial Completion Date means March 31, 2001.

More Definitions of Outside Substantial Completion Date

Outside Substantial Completion Date means August 31, 2020, as such date is extended on a day-for-day basis for each day that Substantial Completion is delayed as a result of XX Xxxxx.

Related to Outside Substantial Completion Date

  • Substantial Completion Date means the required date for Substantial Completion of the Project. The Substantial Completion Date can be adjusted only by written Change Order.

  • Substantial Completion means the stage in the progress of the work as determined and certified by the Contracting Officer in writing to the Contractor, on which the work (or a portion designated by the Government) is sufficiently complete and satisfactory. Substantial completion means that the property may be occupied or used for the purpose for which it is intended, and only minor items such as touch-up, adjustments, and minor replacements or installations remain to be completed or corrected which:

  • Completion Date means the date of completion of the Services by the Service Provider as certified by the Procuring Entity

  • Guaranteed Substantial Completion Date or “Guaranteed Substantial Completion Dates” has the meaning set forth in Section 5.3B.

  • Project Completion Date means the date on which the Completion Certificate is issued;

  • Final Completion Date means the date on which Final Completion occurs.

  • Substantial Completion Certificate means the certificate issued and approved by the Authority indicating the date upon which the Trade Contractor Work (or a designated portion thereof) is Substantially Complete.

  • Construction Completion Date means the date by which the overall development of the Project is completed in accordance with the provisions of this Agreement and when the Construction Completion Certificate is issued by the Independent Engineer as per Article 14.1.

  • Substantial compliance means a level of compliance with these rules where any deficiencies pose no greater risk to resident health or safety than the potential for causing minor harm.

  • Target Completion Date has the meaning given such term in Section 3.3(b).

  • Completion Period means the period starting from the date of issue of "Order" and required to complete the work in all respect.

  • Final Completion means the date determined and certified by A/E and Owner on which the Work is fully and satisfactorily complete in accordance with the Contract.

  • The Completion Date means the date of completion of the Works as certified by the Employer’s Representative.

  • Outside Completion Date shall have the meaning assigned to such term in Section 6.3(d).

  • Certificate of Substantial Completion means the certificate executed by the A/E, ODR and Contractor that documents to the best of A/E’s and ODR’s knowledge and understanding, Contractor’s sufficient completion of the work in accordance with the Contract, so as to be operational and fit for the use intended.

  • Project Completion means completion of the Redevelopment in accordance with this Agreement to the state where the whole of the Morley Shopping Centre, as so redeveloped, is capable of occupation for its intended purpose;

  • Construction Period means the period commencing from the Appointed Date and ending on the date of the Completion Certificate;

  • Occupancy Date means the date on which occupancy of all Units in a Project is permitted;

  • Scheduled Completion Date shall be the date set forth in Clause 10.3;

  • Ready for Occupancy means the date upon which (i) the Leased Premises are available for Tenant's occupancy in a broom clean condition and (ii) the improvements, if any, to be made to the Leased Premises by Landlord as a condition to Tenant's obligation to accept possession of the Leased Premises have been substantially completed and the appropriate governmental building department (i.e., the City building department, if the Property is located within a City, or otherwise the County building department) shall have approved the construction of such improvements as substantially complete or is willing to so approve the construction of the improvements as substantially complete subject only to compliance with specified conditions which are the responsibility of Tenant to satisfy or is willing to allow Tenant to occupy subject to its receiving assurances that specified work will be completed.

  • Mechanical Completion means that (a) all components and systems of the Project have been properly constructed, installed and functionally tested according to EPC Contract requirements in a safe and prudent manner that does not void any equipment or system warranties or violate any permits, approvals or Laws; (b) the Project is ready for testing and commissioning, as applicable; (c) Seller has provided written acceptance to the EPC Contractor of mechanical completion as that term is specifically defined in the EPC Contract.

  • Final Completion Certificate has the meaning set forth in Section 11.6.

  • Tenant Improvement Work means the construction of the Tenant Improvements, together with any related work (including demolition) that is necessary to construct the Tenant Improvements.