Examples of Preliminary Project Schedule in a sentence
Completely cost load the Preliminary Project Schedule to balance the contract award CLINS shown on the Price Schedule.
The approved Preliminary Project Schedule will be used for payment purposes not to exceed 90 calendar days after NTP.
E.4.7 Preliminary Project Schedule Each Offeror should prepare a preliminary project schedule that shows how the Offeror intends to complete the project in a timely manner.
The Preliminary Project Schedule may be summary in nature for the remaining performance period.
Submit the Preliminary Project Schedule, defining the Contractor's planned operations for the first 90 calendar days for approval within 15 calendar days after the NTP is acknowledged.
Within 15 calendar days after the NTP is acknowledged submit the Preliminary Project Schedule defining the planned operations detailed for the first 90 calendar days for approval.
E.4.1.7 Preliminary Project Schedule Each Offeror should prepare a preliminary project schedule (the “Baseline Schedule”) that shows how the Offeror intends to complete the Project in a timely manner.
A Preliminary Project Schedule (PPS) within twenty-one (21) days after receiving the Notice to Proceed (NTP).
Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES: SD-01 Preconstruction Submittals Project Scheduler Qualifications; G Preliminary Project Schedule; G Initial Project Schedule; G Periodic Schedule Update; G1.3 PROJECT SCHEDULER QUALIFICATIONS Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports.
Within the timeframe established in Section 2.01.B, Design Builder shall submit a Preliminary Project Schedule that reflects Design Builder’s sequence of design, procurement and construction activities including the interrelationships of the Demolition and Construction Packages.