Baseline Schedule definition

Baseline Schedule means the initial time schedule prepared by Contractor for Owner’s information and acceptance that conveys Contractor’s and Subcontractors’ activities (including coordination and review activities required in the Contract Documents to be performed by A/E and ODR), durations, and sequence of work related to the entire Project to the extent required by the Contract Documents. The schedule clearly demonstrates the critical path of activities, durations and necessary predecessor conditions that drive the end date of the schedule. The Baseline Schedule shall not exceed the time limit current under the Contract Documents.
Baseline Schedule means the accepted comprehensive work progress schedule, taking into account subcontractor and supplier input, incorporating all prior comments received from the ODR on the previous work progress schedules. This Baseline Schedule shall be submitted by the contractor within 90 days of the NTP. This schedule is prepared by the Contractor for the Owner’s information and acceptance which conveys Contractor’s and its Subcontractors’ activities (including coordination and review activities required in the Contract Documents to be performed by A/E and ODR), durations, and sequence of work related to the entire Project to the extent required by the Contract Documents. The schedule clearly demonstrates the critical path of activities, durations and necessary predecessor conditions which drive the end date of the schedule. The Baseline Schedule shall not exceed the time limit current under the Contract Documents. All subsequent Work Progress Schedules shall make comparisons to the Baseline Schedule as a means of analyzing progress.
Baseline Schedule means an initial comprehensive baseline design and construction schedule for the D&C Work prepared by the Lessee in accordance with the requirements of the General Provisions and approved by the Port Authority in form and substance. The Lessee shall update the Baseline Schedule in accordance with the General Provisions and provide each update for the Port Authority’s review and comment (if any).

Examples of Baseline Schedule in a sentence

  • Proposer shall indicate the number of calendar days between NTP1 and its proposed Substantial Completion date for each of Segments F-1, F-2 and G from the Preliminary Project Baseline Schedule on Form O.

  • All Float contained in the Project Schedule, as shown in the initial Project Baseline Schedule or as generated thereafter, shall be considered a Project resource available to either Party or both Parties as needed to absorb delays caused by any event, achieve schedule milestones, interim completion dates and/or Completion Deadlines.

  • Float time contained in the Baseline Schedule is not for the exclusive benefit of the Contractor or the Owner, but belongs to the Project and may be consumed by either party.

  • Unless indicated otherwise in the Contract Documents, the Contractor shall develop the Baseline Schedule and its execution plan to provide a minimum of 10 percent total float at the project level at acceptance of the Baseline Schedule.

  • Contractor shall identify all proposed changes to schedule logic to Owner and to A/E via an executive summary accompanying the updated schedule for review prior to final implementation of revisions into a revised Baseline Schedule.


More Definitions of Baseline Schedule

Baseline Schedule means the initial time schedule prepared by Contractor for Owner’s information and acceptance that conveys Contractor’s and Subcontractors’ activities (including coordination and review activities required in the Contract Documents to be performed by Project A/E and ODR), durations, and sequence of work related to the entire Project to the extent required by the Contract Documents. The schedule clearly demonstrates the critical path of activities, durations and necessary predecessor conditions that drive the end date of the schedule. The Baseline Schedule shall not exceed the time limit current under the Contract Documents.
Baseline Schedule means the initial time schedule of Work for the entire Project prepared by the DB in accordance with the requirements set forth in UGC Section 1.6. Bid Bond has the same meaning as Security Bond as described in UGC Sections 5.1 and 5.1.2, and shall be in the form of an approved surety bond, cash, or other immediately available funds.
Baseline Schedule means the time-scaled and precedence diagramming network construction schedule prepared by the Contractor. The Baseline Schedule is produced using the critical path method;
Baseline Schedule means the time-scaled and cost/resource-loaded Critical Path network, updated from monthly in accordance with the Contract and depicting the Price Items and subordinate activities and their respective prices (distributed over time), durations, sequences, and interrelationships that represent DFIM Contractor’s Work plans, DFIM Contractor’s Work Breakdown Structure (WBS) for designing, constructing, and completing the Project and the Contract Price distributed over the period of the Contract.
Baseline Schedule. A project schedule accepted by the CA that is the standard by which Project performance is measured. The Baseline Schedule must include all contractual start and finish dates and critical interim milestones, and demonstrate how these dates are achieved through the sequencing of project activities, The Baseline Schedule requirements are further described in Division 1 Specifications or other contract provisions within the Contract Documents.
Baseline Schedule. Means the approved version of a project schedule set forth in the Statement of Work that can be changed only through formal change control procedures and is used as a basis for comparison to actual results. Benchmarker Has the meaning given in Section 9.2(a) of the Agreement. Business Day Means each day from Monday through Friday 7:00 a.m. through 6:00 p.m. (Central Time), excluding national holidays as defined by Tex. Gov’t Code § 662.003(a). CAP Notice Has the meaning set forth in Section 5.3(b) of the Agreement. Cardholder Data Means any personally identifiable information associated with the holder of a credit or debit card. Change Request Means a written instrument in a form approved by OCA that states a change in or an addition to any Contractor’s obligation under the Agreement. Charges Means the fixed charges and fees for Contractor’s provision of the Services and the charges and fees for the Deliverables. Charges Benchmarking Has the meaning set forth in Section 9.2(a) of the Agreement. Commencement Date Means 12:00 a.m., Central Time, on the day following the date of the first site deployed into production, or such other date as the Parties may agree upon in writing.
Baseline Schedule has the meaning set forth in Section 4.3(a)(i).