Baseline Schedule definition

Baseline Schedule means the initial time schedule prepared by Contractor for Owner’s information and acceptance that conveys Contractor’s and Subcontractors’ activities (including coordination and review activities required in the Contract Documents to be performed by A/E and ODR), durations, and sequence of work related to the entire Project to the extent required by the Contract Documents. The schedule clearly demonstrates the critical path of activities, durations and necessary predecessor conditions that drive the end date of the schedule. The Baseline Schedule shall not exceed the time limit current under the Contract Documents.
Baseline Schedule means the accepted comprehensive work progress schedule, taking into account subcontractor and supplier input, incorporating all prior comments received from the ODR on the previous work progress schedules. This Baseline Schedule shall be submitted by the contractor within 90 days of the NTP. This schedule is prepared by the Contractor for the Owner’s information and acceptance which conveys Contractor’s and its Subcontractors’ activities (including coordination and review activities required in the Contract Documents to be performed by A/E and ODR), durations, and sequence of work related to the entire Project to the extent required by the Contract Documents. The schedule clearly demonstrates the critical path of activities, durations and necessary predecessor conditions which drive the end date of the schedule. The Baseline Schedule shall not exceed the time limit current under the Contract Documents. All subsequent Work Progress Schedules shall make comparisons to the Baseline Schedule as a means of analyzing progress.
Baseline Schedule means an initial comprehensive baseline design and construction schedule for the D&C Work prepared by the Lessee in accordance with the requirements of the General Provisions and approved by the Port Authority in form and substance. The Lessee shall update the Baseline Schedule in accordance with the General Provisions and provide each update for the Port Authority’s review and comment (if any).

Examples of Baseline Schedule in a sentence

  • Float time contained in the Baseline Schedule is not for the exclusive benefit of the Contractor or the Owner, but belongs to the Project and may be consumed by either party.

  • The Contractor shall re-submit initial Schedule as required to address review comments from A/E and ODR until such Schedule is accepted as the Baseline Schedule.

  • Unless indicated otherwise in the Contract Documents, the Contractor shall develop the Baseline Schedule and its execution plan to provide a minimum of 10 percent total float at the project level at acceptance of the Baseline Schedule.

  • Contractor shall identify all proposed changes to schedule logic to Owner and to A/E via an executive summary accompanying the updated schedule for review prior to final implementation of revisions into a revised Baseline Schedule.

  • When acceptable to the Owner, the initially accepted schedule shall be the Baseline Schedule for comparison to actual conditions throughout the Contract duration.


More Definitions of Baseline Schedule

Baseline Schedule means the initial time schedule prepared by Contractor for ODR’s information and acceptance that conveys Contractor’s and Subcontractors’ activities (including coordination and review activities required in the Contract Documents to be performed by A/E and ODR), durations, and sequence of work related to the entire Project to the extent required by the Contract Documents. The schedule clearly demonstrates the critical path of activities, durations and necessary predecessor conditions that drive the end date of the schedule. The Baseline Schedule shall not exceed the time limit current under the Contract Documents.
Baseline Schedule means the initial time schedule of Work for the entire Project prepared by the DB in accordance with the requirements set forth in UGC Section 1.6. Bid Bond has the same meaning as Security Bond as described in UGC Sections 5.1 and 5.1.2, and shall be in the form of an approved surety bond, cash, or other immediately available funds.
Baseline Schedule means the time-scaled and precedence diagramming network construction schedule prepared by the Contractor. The Baseline Schedule is produced using the critical path method;
Baseline Schedule means the time-scaled and cost/resource-loaded Critical Path network, updated from monthly in accordance with the Contract and depicting the Price Items and subordinate activities and their respective prices (distributed over time), durations, sequences, and interrelationships that represent DFIM Contractor’s Work plans, DFIM Contractor’s Work Breakdown Structure (WBS) for designing, constructing, and completing the Project and the Contract Price distributed over the period of the Contract.
Baseline Schedule means the initial time schedule prepared by Contractor for Owner’s information and acceptance that conveys Contractor’s and Subcontractors’ activities (including coordination and review activities required in the Contract Documents to be performed by A/E and ODR), durations, and sequence of Work related to the entire Project to the extent required by the Contract Documents. The schedule clearly demonstrates the critical path of activities, using longest duration methodology, durations and necessary predecessor conditions that drive the end date of the schedule. The Baseline Schedule shall include commissioning and functional testing of all building automation systems (BAS), lighting control systems, and all activities such as TAB, Commissioning, installation of all IT, AV, wireless devices, security systems, access controls installation and functional testing. The Baseline Schedule shall not exceed the time limit current under the Contract Documents.
Baseline Schedule means the plan and critical path schedule that the Contractor intends to use to perform and complete the work. Upon approval by Authority, the Baseline Schedule shall be the schedule of record from which entitlement for adjustments in the Completion Deadline shall be measured until a Revised Baseline Schedule is approved by Authority..
Baseline Schedule has the meaning set forth in Section 4.3(a)(i).