Impact of Construction Activities Sample Clauses

Impact of Construction Activities. The Contractor recognizes that from time to time during the period of this Contract, it will be necessary for the Authority to initiate and carry forward extensive programs of construction, reconstruction, expansion, relocation, maintenance and repair on the Airport, and that such construction, reconstruction, expansion, relocation, maintenance and repair may inconvenience or impair the Contractor in its operation at the Airport. The Contractor agrees that no liability shall attach to the Authority, its officers, agents, employees, contractors, subcontractors and representatives by way of such inconveniences or impairment, and the Contractor waives any right to claim damages or other consideration for such inconveniences or impairment.
AutoNDA by SimpleDocs
Impact of Construction Activities. Xxxxxx recognizes that from time to time during the period of the Lease, it will be necessary for the Authority to initiate and carry forward extensive programs of construction, reconstruction, expansion, relocation, maintenance and repair on the Airport, and that such activities may inconvenience or impair the Lessee in its operation. Lessee agrees that no liability shall attach to the Authority, its officers, agents, employees, contractors, subcontractors, and representatives by way of such inconveniences or impairments and the Lessee waives any right to claim damages or other consideration for such inconveniences or impairment.

Related to Impact of Construction Activities

  • ICIF Construction The ICIF shall be designed and constructed in accordance with Good Utility Practice. Within one hundred twenty (120) Calendar Days after the Commercial Operation Date, unless the Parties agree on another mutually acceptable deadline, Interconnection Customer shall deliver to Transmission Provider and Transmission Owner “as-built” drawings, information and documents for the ICIF, such as: a one-line diagram, a site plan showing the Generating Facility and the ICIF, plan and elevation drawings showing the layout of the ICIF, a relay functional diagram, relaying AC and DC schematic wiring diagrams and relay settings for all facilities associated with the Interconnection Customer’s step-up transformers, the facilities connecting the Generating Facility to the step-up transformers and the ICIF, and the impedances (determined by factory tests) for the associated step-up transformers and the Generating Facility. Interconnection Customer shall provide Transmission Provider and Transmission Owner with Interconnection Customer’s specifications for the excitation system, automatic voltage regulator, Generating Facility control and protection settings, transformer tap settings, and communications, if applicable.

  • Supervision of Construction The Recipient agrees to maintain competent and adequate engineering supervision at the construction site of any Project to ensure that the completed work conforms to the approved plans and specifications.

  • Cost of Construction 1. During the Schematic Design, Design Development, and Construction Document Phases, the ARCHITECT’s estimates of Construction Cost shall be reconciled against the Budget approved by the DISTRICT pursuant to Article IV, Section 2.

  • DAF Construction The DAF shall be designed and constructed in accordance with Good Utility Practice. Within one hundred twenty (120) Calendar Days after the Commercial Operation Date, unless the Developer and Connecting Transmission Owner agree on another mutually acceptable deadline, the Developer shall deliver to the Connecting Transmission Owner and NYISO “as- built” drawings, information and documents for the DAF, such as: a one-line diagram, a site plan showing the Large Generating Facility and the DAF, plan and elevation drawings showing the layout of the DAF, a relay functional diagram, relaying AC and DC schematic wiring diagrams and relay settings for all facilities associated with the Developer’s step-up transformers, the facilities connecting the Large Generating Facility to the step-up transformers and the DAF, and the impedances (determined by factory tests) for the associated step-up transformers and the Large Generating Facility. The Developer shall provide to, and coordinate with, Connecting Transmission Owner and NYISO with respect to proposed specifications for the excitation system, automatic voltage regulator, Large Generating Facility control and protection settings, transformer tap settings, and communications, if applicable.

  • Commencement of Construction Construction of the Project will start within thirty (30) days after notification to the Developer by the Owner, or as soon thereafter as weather and ground conditions permit.

  • Completion of Construction (a) For the purposes of this Agreement, the terms "

  • MONITORING OF CONSTRUCTION 13.1 Monthly progress reports During the Construction Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Authority and the Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Engineer.

  • ADDITIONAL CONSTRUCTIONS The Promoter undertakes that it has no right to make additions or to put up additional structure(s) anywhere in the Project after the building plan has been approved by the competent authority(ies) except for as provided in the Act.

  • Principles of Construction All references to sections and schedules are to sections and schedules in or to this Agreement unless otherwise specified. All uses of the word “including” shall mean “including, without limitation” unless the context shall indicate otherwise. Unless otherwise specified, the words “hereof,” “herein” and “hereunder” and words of similar import when used in this Agreement shall refer to this Agreement as a whole and not to any particular provision of this Agreement. Unless otherwise specified, all meanings attributed to defined terms herein shall be equally applicable to both the singular and plural forms of the terms so defined.

  • Commencement and Completion of Construction The Company shall begin Construction Activities no later than January 1, 2014 (“Commencement Date”) and secure a final Certificate of Compliance by June 30, 2015 (hereinafter, “Completion Date”).