Costs to Be Reimbursed. § 7.1.1 The term Cost of the Work shall mean costs necessarily incurred by the Construction Manager in the proper performance of the Work. The Cost of the Work shall include only the items set forth in Sections 7.1 through 7.7.
AutoNDA by SimpleDocs
Costs to Be Reimbursed. The term Cost of the Work shall mean all costs necessarily and reasonably incurred by Construction Contractor in the proper performance of the Construction Phase Services portion of the Work. Such costs shall be at rates not higher than the standard paid at the place of the Project except with the prior written consent of Owner only after Construction Contractor has provided sufficient support in writing that exceptional circumstances exist, which justify the payment of rates higher than the standard. The Cost of the Work shall include only those items set forth below in this subsection A:
Costs to Be Reimbursed. 6.1.1 The term
Costs to Be Reimbursed. 6.1.1 The term Cost of the Work shall mean costs necessarily incurred by XXXX in the proper performance of the Work. Such costs shall be at rates not higher than the standard paid at the place of the Project except with prior consent of County. The Cost of the Work shall include only the items set forth in Sections 6.1 through 6.5.
Costs to Be Reimbursed. 5.1 The term "
Costs to Be Reimbursed. The term Cost of the Work shall mean all costs necessarily and reasonably incurred by Construction Contractor in the proper performance of the Construction Phase Services portion of the Work. Cost of the Work shall not include any costs ore expenses incurred by the Construction Contractor related to or incurred during the performance of the Pre-Construction Phase Services. Such costs shall be incurred at rates not higher than the standard industry rates paid at the place of the Project except with the prior written consent of Owner only after Construction Contractor has provided sufficient support in writing that exceptional circumstances exist, which justify the payment of rates higher than the standard. Items of Work not included in this Subsection 5.A. are compensable only as part of the Construction Management Fee and are otherwise not reimbursable. The Cost of the Work shall include only those items set forth below in this Subsection 5.A:
Costs to Be Reimbursed. The costs to be reimbursed under this agreement are those costs that are directly related to the Project, as set out in Section 261-45.2 of Iowa Administrative Code. Those costs specifically do not include expenditures for furnishings, appliances, accounting services, legal services, loan origination and other financing costs, syndication fees and related costs, developer fees, or the costs associated with selling or renting dwelling unites whether incurred before or after completion of the Project.
AutoNDA by SimpleDocs
Costs to Be Reimbursed. § 6.1.1 The term Cost of the Work shall mean the items set forth in this Section 6.1. Such costs shall be at rates not higher than those customarily paid at the place of the Project except with prior consent of the Owner. The Cost of the Work shall include only the items set forth in Sections 6.1 through 6.7 and are subject to review and verification by the owner or Architect at the Owner’s discretion, prior to reimbursement by Owner to Construction Manager.
Costs to Be Reimbursed. § 6.1.1 The term Cost of the Work shall mean costs necessarily incurred by the Construction Manager in the proper performance of the Work. Such costs shall be at rates not higher than the standard paid at the place of the Project except with prior consent of the Owner. The Cost of the Work shall include only the items set forth in Sections 6.1 through 6.7. Items included in the General Conditions Lump Sum Amount established as part of TA 2 for General Conditions and General Requirements shall be paid in equal monthly payments, as set forth in Section 1.6.1.1 for Task 1 and Task 2, as part of the Cost of the Work pursuant to Article 7 and not billed separately under this Section. To the extent relevant for extra work or change orders, attached as Schedule D is a listing of the Construction Manager's fully burdened rates for trade labor and supervisory, administrative, and professional staff.
Costs to Be Reimbursed. The term "COST OF THE WORK" shall mean reasonable costs necessarily incurred in the proper performance of Construction Services for the DC Project work which are actually incurred by Bechtel. Such costs shall include the items set forth in this Section 2.5.5, subject to Section 2.5.6: