Boil Off Gas Recycle Compressors Sample Clauses

Boil Off Gas Recycle Compressors. This first test will consist of verifying the manufacturer’s performance curve for the design point for each compressor. Each compressor will be observed for safe operation for its normal operating envelope. Actual flow rate, gas composition, pressure and temperature at the machine’s suction and discharge will be recorded. The second test will consist of operating all installed units in parallel during ship loading operations (operation throughout the range of vapor return rates) with all gas from the Boil Off Gas Recycle Compressor recovered to the process and no flaring and with all controls in automatic. This test will be done to evaluate stability and controllability for the expected range of flows.
AutoNDA by SimpleDocs
Boil Off Gas Recycle Compressors. This first test will consist of verifying the manufacturer’s performance curve for the design point for each compressor. Each compressor will be observed for safe operation for its normal operating envelope. Actual flow rate, gas composition, pressure and temperature at the machine’s suction and discharge will be recorded.
Boil Off Gas Recycle Compressors. This test is not required for the Stage 2 Liquefaction Facility.

Related to Boil Off Gas Recycle Compressors

  • Fuel Upon redelivery of the Aircraft to Lessor, an adjustment will be made in respect of fuel on board on the Previous Delivery Date and the Expiry Date at the price then prevailing at the Redelivery Location.

  • Underground Storage Tanks Borrower shall not install or permit to be installed on the Property any underground storage tank.

  • Delivery Point Once Manufacture of the Products has been completed, Contractor shall be responsible for delivering the Finished Goods FCA, (as defined in Incoterms (2000) published by the International Chamber of Commerce) and to a freight forwarder specified by Company in its Order, or otherwise approved by Company. “Delivery Point” as used in this Agreement shall mean the specific time and location that the Product is delivered to the shipper specified on the Order.

  • Delivery Points The measurement of and tests for quality of Shipper's Gas redelivered at the Delivery Points shall be governed by and determined in accordance with the requirements of the receiving pipeline at each Delivery Point.

  • Mission Block Fuel The block fuel for a stage length of 2,050 nautical miles in still air (representative of a route with a 4.4 hour flight time from a sea level airport) with a zero fuel weight of 154,221 kilograms, using the conditions and operating rules defined below, shall not be more than the following guarantee value: NOMINAL: [*] Kilograms TOLERANCE: [*] Kilograms GUARANTEE: [*] Kilograms Conditions and operating rules:

  • STORAGE TANKS AND SUMPS 3.1 Is any above or below ground storage of gasoline, diesel, petroleum, or other Hazardous Materials in tanks or sumps proposed in, on or about the Premises? Existing Tenants should describe any such actual or proposed activities. Yes [ ] No [ ] If yes, please explain:

  • Storage Tanks If storage tanks storing Hazardous Materials located on the Premises or the Project are used by Tenant or are hereafter placed on the Premises or the Project by Tenant, Tenant shall install, use, monitor, operate, maintain, upgrade and manage such storage tanks, maintain appropriate records, obtain and maintain appropriate insurance, implement reporting procedures, properly close any storage tanks, and take or cause to be taken all other actions necessary or required under applicable state and federal Legal Requirements, as such now exists or may hereafter be adopted or amended in connection with the installation, use, maintenance, management, operation, upgrading and closure of such storage tanks. Notwithstanding anything to the contrary contained herein, Tenant shall have no right to use or install any underground storage tanks at the Project.

  • Plant An electrical generating alternative energy resource facility developed by Producer for which IID shall provide transmission service, as specified in Exhibit(s) II, Transmission Service, and in any subsequent Plant Amendments.

  • Underground Tanks If underground or other storage tanks storing Hazardous Materials located on the Premises or the Project are used by Tenant or are hereafter placed on the Premises or the Project by Tenant, Tenant shall install, use, monitor, operate, maintain, upgrade and manage such storage tanks, maintain appropriate records, obtain and maintain appropriate insurance, implement reporting procedures, properly close any underground storage tanks, and take or cause to be taken all other actions necessary or required under applicable state and federal Legal Requirements, as such now exists or may hereafter be adopted or amended in connection with the installation, use, maintenance, management, operation, upgrading and closure of such storage tanks.

  • Transportation Costs The cost of transporting a Warranted Part claimed to be defective to the facilities designated by the Seller and for the return therefrom of a repaired or replaced Warranted Part shall be borne by the Buyer.

Time is Money Join Law Insider Premium to draft better contracts faster.