Delivery Point Sample Clauses

Delivery Point. (a) All Energy shall be Delivered hereunder by Seller to Buyer at the Delivery Point. Seller shall be responsible for the costs of delivering its Energy to the Delivery Point consistent with all standards and requirements set forth by the FERC, ISO-NE, the Interconnecting Utility and any other applicable Governmental Entity and any applicable tariff.
Delivery Point. The Delivery Point for energy delivered pursuant to the terms of this Schedule shall be at one of three points of Interconnection between the NYISO Balancing Authority Area and the ISO-NE Balancing Authority Area, and at such other points of Interconnection as may be established. These three points of Interconnection are as follows: (1) the NY/NE Northern AC Interconnection2; (2) the NNC Interconnection; and (3) the Cross Sound Cable (CSC) Interconnection, which is a HVDC facility. Unless otherwise agreed by the Coordination Committee, the price for energy for an hour delivered pursuant to this Schedule shall include all transmission costs of delivering such energy to the Delivery Point in that hour, and the Party taking delivery of such energy for the hour shall be responsible for all transmission costs beyond the Delivery Point for that hour.
Delivery Point. The delivery point is the point of delivery of the Power Product to the CAISO Controlled Grid (the “Delivery Point”). Seller shall provide and convey to Buyer the Power Product from the Generating Facility at the Delivery Point. Title to and risk of loss related to the Power Product transfer from Seller to Buyer at the Delivery Point.
Delivery Point. The Delivery Point shall be the PNode designated by the CAISO for the Project.
Delivery Point. The delivery point is the point where Seller’s facilities connect with facilities owned by Buyer (the “Delivery Point”). Seller shall convey to Buyer and Buyer shall accept all the As-Available Contract Capacity and associated electric energy from the Generating Facility at the Delivery Point. Title to and risk of loss related to the Power Product shall transfer from Seller to Buyer at the Delivery Point. Buyer shall pay any transmission or distribution costs to deliver the power from the Generating Facility’s bus bar to the point of interconnection of the Generating Facility to the CAISO-Controlled Grid (Interconnection Point); Seller shall be responsible for interconnection costs, including necessary facility upgrades (consistent with Applicable Laws and the Interconnection Agreement), and line losses from the Delivery Point to the Interconnection Point.
Delivery Point. All Energy shall be Delivered hereunder by Seller to Buyer at the Delivery Point. Seller shall be responsible for the costs of delivering its Energy to the Delivery Point consistent with all standards and requirements set forth by the FERC, Buyer, ISO-NE and any other applicable Governmental Entity or tariff. Seller shall be responsible for all applicable losses and charges associated with interconnection, service and delivery charges, including all related ISO‑NE administrative fees and other FERC-approved charges and Interconnection Tariff charges in connection with the Delivery of Energy to and at the Delivery Point.
Delivery Point. (a) All Qualified Clean Energy shall be Delivered hereunder by Seller to Buyer at the Delivery Point. Except as set forth in Article 20, Seller shall be responsible for delivering its Qualified Clean Energy to the Delivery Point, and all Deliveries of Qualified Shortfall Energy as provided herein, in each case, consistent with all standards and requirements set forth by the FERC, ISO-NE, other Independent System Operators, as applicable, and any other applicable Governmental Entity or applicable tariff.
Delivery Point. [For Project with transmission level interconnection, insert: “The Delivery Point shall be the point of interconnection of the Project to the CAISO Grid (and, for payment purposes, the corresponding PNode for the Project).”] [For Project with distribution level interconnection, insert: “The Delivery Point shall be the point on the CAISO Grid where the Participating Transmission Owner’s distribution system interconnects to the CAISO Grid as set forth in their Meter Services Agreement, as may be acceptable to Buyer in its reasonable discretion (and, for payment purposes, the corresponding PNode for the Project).”] [For Projects located outside of the CAISO, insert: “The Delivery Point shall be the point on the CAISO Grid where the Native Balancing Authority’s grid is interconnected to the CAISO Grid at the [identify the local CAISO substation to which the Project has firm transmission rights] Substation (and, for payment purposes, the corresponding PNode for the Project, or if none exists, the PNode corresponding to the point on the CAISO Grid where the Native Balancing Authority’s grid is interconnected to the CAISO Grid at the Delivery Point).”] The Delivery Point shall be [the point of interconnection of the Project to the CAISO Grid] [Seller may specify another delivery point; for a Project located outside the CAISO Grid, the Delivery Point should be a CAISO Scheduling Point as defined by the CAISO] and for financial settlement purposes under the applicable CAISO market, the PNode corresponding to such point.