Date of Commissioning definition

Date of Commissioning means the date of issue of the certificate by the BUYER to SELLER about the acceptability of ( details of items ) and other ancillary and allied equipments purchased alongwith;
Date of Commissioning or "COD" means the date notified by Corporation as the date on which the Plant is ready to commence commercial operations after successfully completing the testing, which shall be a date no later than three months of the date of Mechanical Completion of the Plant.
Date of Commissioning means the date on which supply of Energy is commercially commenced by the Generating Plant to ABCL and includes COD.

Examples of Date of Commissioning in a sentence

  • After the Inspection and approval of the Electrical Inspectorate, date of Energisation to the Grid will be considered as the official Date of Commissioning (CoD) of the project.

  • Restoration The development shall be restored in accordance with the following details: (i) The Development will cease to generate electricity by no later than the date falling 35 years from the Date of Commissioning (as per the stipulations of condition 1 of this permission).

  • The stipulated time of completion is specified in DPRs. Also, Date of Commissioning depends on stipulated time of completion and date of “in-principle” approval.


More Definitions of Date of Commissioning

Date of Commissioning means the date on which all conditions for commissioning of power plant are met, namely the date of completion of technical inspection, provision of power plant operating licence and licence for production of electricity [ specify licence if a licence for power plant operation is required according to the relevant regulations], power plant connected to transmission or distribution systems by the competent system operator, as evidenced by the Seller to the Buyer in writing;
Date of Commissioning. (COD), means the date on which the Concessionaire receives the completion certificate, for completion of development of the facilities as approved / agreed by Concessioning Authority, in accordance with the provisions of this Agreement.
Date of Commissioning means the date on which the technical solution is commissioned into service for Customer’s operation or use after testing required performances as per the requirements of this Agreement.
Date of Commissioning means the date of commissioning declared by a Generating Company in relation to a Unit of its Generating Station:
Date of Commissioning or“COD”shall mean the date notified by Concessionaire as the date on which the Plant is ready to commence commercial operations after issuance of test certificate of the Independent Engineer certifying successful completion of Commissioning Tests;
Date of Commissioning means the date on which the whole of the projected installed capacity of the [Windfarm / Hydroelectric scheme / Other – DELETE AS APPROPRIATE] is fully operational, fully tested, and supplying electricity to the national electricity transmission system;
Date of Commissioning means the date of commissioning declared by a Generating Company in relation to a Unit of its Generating Station:Provided that date of commissioning shall be certified based on joint inspection by RE Generator and concerned Distribution Licensee or SLDC as may be applicable;