Examples of Accepted Programme in a sentence
C.2.1.1.3 Use is made of method related charges for Equipment applied to Providing the Works based on durations shown in the Accepted Programme, fixed charges for the use of Equipment that is required throughout the construction phase, time related charges for people working in a supervisory capacity for the period required, and lump sum charges for other facilities or services not directly related to performing work items typically included in other parts of the bill.
The Service Manager may request a detailed workshop or bar charts which fit into the logic and time span of the Accepted Programme, and reflects the required manufacturing completion dates.
A6.1.2.11 It should also be noted that, without an Accepted Programme, the Project Managerwill assess a compensation event by his own assessment as per NEC clause 64.2. A6.1.2.12 If the Project Manager chooses not to accept the programme for reasons not listed under NEC clause 31.3, or if he does not reply within the stipulated time frame, then that would become a compensation event under NEC clause 60.1(9) or 60.1(6).
The time allowed for the Project Manager to assess the programme may not be adequate for him to make the decision, even if the submitted programme satisfies NEC clause 31.2. A6.1.2.9 If, after several rounds of correspondence, the programme is still considered to be substandard, this would become an issue to project management as an Accepted Programme is not in place.
If such sub-programme is considered practicable and realistic, the Project Manager may accept this sub-programme with condition(s) for separate submission and acceptance of detailed planning and programming of later activities and the full programme may be accepted first and taken as an Accepted Programme if no major observation is identified.
The NEC approach to the P & G bill assumes use will be made of method related charges for Equipment applied to Providing the Works based on durations shown in the Accepted Programme, fixed charges for the use of Equipment that is required throughout the construction phase, time related charges for people working in a supervisory capacity for the period required, and lump sum charges for other facilities or services not directly related to performing work items typically included in other parts of the bill.
Access and use is allowed on or before the later of its access date and the date for access shown on the Accepted Programme.
In accordance with Accepted Programme Submitted to Project Manager.
A6.3.1.14 If utility undertakings do not work within the times shown in the Accepted Programme or the conditions stated in the Works Information, the Contractor may be entitled to compensation in accordance with the first or second bullet point of NEC clause 60.1(5).
Activities in multiple currencies are separately identified on both the Activity Schedule and the Accepted Programme for each currency.