VALUE OF CHANGE ORDER WORK Sample Clauses

VALUE OF CHANGE ORDER WORK. 18.1 The value of any work covered by a Change Order or of any claim for an increase or decrease in the Contract Price shall be determined in one of the following ways:
AutoNDA by SimpleDocs
VALUE OF CHANGE ORDER WORK. The value of any Work covered by a Change Proposal Request or of any claim for an increase or decrease in the Contract Price shall be determined in one of the following ways:  Where the Work involved is covered by unit prices contained in the Contract, by application of unit prices to the quantities of items involved.  By mutual acceptance of a lump sum which Design-Build Firm and Project Manager acknowledge contains a component for overhead and profit.  On the basis of the "cost of Work," determined as provided in this, plus a Design-Build Firm‟s fee for overhead and profit which is determined as provided in this Article.
VALUE OF CHANGE ORDER WORK. The value of any Work to be covered by a Change Order, or for any claim for an increase or decrease in the GMP, or use of the Construction Manager’s Contingency shall be determined in one of the following ways: Where the work involved is covered by unit prices contained in the Schedule of Values, by application of unit prices to the quantities of items involved. By mutual acceptance of a lump sum which Construction Manager and City acknowledge contains a component for overhead and profit. As the Construction Manager’s Contingency already includes overhead and profit no additional sum(s) will be added for overhead and profit where the change order is issued against the Construction Manager’s Contingency. On the basis of the "cost of work," determined as provided in this Article, plus a proportional rate for the Construction Manager’s fee for general conditions, overhead and profit, except that not additional sums will be added for general conditions, overhead, and profit where the change order is issued from the Construction Manager’s Contingency.
VALUE OF CHANGE ORDER WORK. The value of any Work covered by a Change Proposal Request shall be determined in one of the following ways: • By mutual acceptance of a lump sum which Contractor and City’s Project Manager acknowledge contains a component for overhead and profit. • On the basis of the "cost of Work," determined as provided in this, plus a Contractor’s fee for overhead and profit which is determined as provided in this Article.

Related to VALUE OF CHANGE ORDER WORK

  • Value of Completed Work If the Engineer defaults in the performance of this contract or if the State terminates this contract for fault on the part of the Engineer, the State will give consideration to the following when calculating the value of the completed work: (1) the actual costs incurred (not to exceed the rates set forth in Attachment E, Fee Schedule) by the Engineer in performing the work to the date of default; (2) the amount of work required which was satisfactorily completed to date of default; (3) the value of the work which is usable to the State; (4) the cost to the State of employing another firm to complete the required work; (5) the time required to employ another firm to complete the work; and (6) other factors which affect the value to the State of the work performed.

  • Rental Rates and Wage Rates for Change Orders As soon as is practical, but prior to the completion of the Construction Preparation Period and in any event prior to the commencement of any Work on the Site, the Contractor shall submit in accordance with the style and format of a specimen to be furnished by the Owner for consideration of the Owner the following: (1) a proposal for rental rates on heavy construction equipment that shall apply in the event Change Order Work is performed, and (2) a proposal for wage rates for the types of project labor that shall apply in the event of the execution of any Change Order Work. Under penalty of false swearing, a principal of the contracting firm shall certify that the proposal for rental rates and proposal for wage rates do not exceed current costs for like services. The Owner will in no event consider a rental rate in excess of eighty percent of the rate set forth in the latest edition of the "Compilation of Nationally Averaged Rental Rates for Construction Equipment" of the Associated Equipment Distributors unless the rates proposed in excess of eighty percent are supported by proof satisfactory to the Owner that the excess rates are reasonable. If the equipment is owned by the Contractor the costs shall be charged at a maximum of eighty percent of market monthly rental rates for the amount of time used. If applicable, transportation costs may be included. The decision of the Owner shall be final, binding and conclusive on all parties. Rental rates shall be payable only for the actual time the equipment is required on the Site.

  • Change Orders Any alteration or deviation from the Services mentioned or any other contractual specifications that result in a revision of this Agreement shall be executed and attached to this Agreement as a change order (“Change Order”).

  • Change Order Formats Formats for Lump Sum Change Orders and for Change Orders based upon either a force account or upon unit pricing with an indeterminate number of units are in Section 7, Forms.

  • For Lump Sum Change Order The payment and extension of time (if any) provided by this Change Order constitutes compensation in full to the Contractor and its Subcontractors and Suppliers for all costs and markups directly and indirectly attributable to the Change Order herein, for all delays related thereto and for performance of changes within the time stated.

  • Project Schedule Construction must begin within 30 days of the date set forth in Appendix A, Page 2, for the start of construction, or this Agreement may become null and void, at the sole discretion of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame.

  • Change Order (5) The Change Order is then submitted to the Project Manager who immediately processes the CO with OPC as required by Bulletin 3.5 and BGS’ Contracting Plan.

  • Modified Work/Return to Work (a) The parties recognize the duty of reasonable accommodation for individuals under the Human Rights Code of Ontario and agree that this Collective Agreement will be interpreted in such a way as to permit the Employer and the Union to discharge that duty.

  • Change Order Procedure The Agency may at any time request a modification to the Scope of Work using a change order. The following procedures for a change order shall be followed:

  • Development Schedule The Project shall substantially comply with the specific timetables and triggers for action set forth in Article 5 of this Agreement. The parties acknowledge that, as provided in G.S. 160A-400.25(b), the failure to meet a commencement or completion date shall not, in and of itself, constitute a material breach of this Agreement pursuant to G.S. 160A-400.27 but must be judged based upon the totality of the circumstances.