Progress of Performance Sample Clauses

Progress of Performance. If at any time the Contractor’s actual progress falls behind the program referred to in GCC Sub- Clause 50.2 (Program of Performance), or it becomes apparent that it will so fall behind, the Contractor shall, at the request of the Employer or the Project Manager, prepare and submit to the Project Manager a revised program, taking into account the prevailing circumstances, and shall notify the Project Manager of the steps being taken to expedite progress so as to attain Completion of the Facilities within the Time for Completion under GCC Clause 22 (Time for Commencement and Completion), or any extended period as may otherwise be agreed upon between the Employer and the Contractor.
AutoNDA by SimpleDocs
Progress of Performance. If at any time the Contractor’s actual progress falls behind the program referred to in GC Sub-Clause 19.2, or it becomes apparent that it will so fall behind, the Contractor shall, at the request of the Employer or the Project Manager, prepare and submit to the Project Manager a revised program, taking into account the prevailing circumstances, and shall notify the Project Manager of the steps being taken to expedite progress so as to attain Completion of the Facilities within the Time for Completion under GC Sub-Clause 9.2, any extension thereof entitled under GC Sub-Clause 41.1, or any extended period as may otherwise be agreed upon between the Employer and the Contractor.
Progress of Performance. If at any time the Supplier's actual progress falls behind the Milestones referred to in Attachment E to the Specifications and/or the program referred to in Sub-Clause 18.2, or it becomes apparent that it will so fall behind, the Supplier shall, prepare and submit to the HPM a revised program, taking into account the prevailing circumstances, and shall notify the HPM of the steps being taken or to be taken to expedite progress so as to attain the Milestones and/or Acceptance of the Deliverables within the Time for Acceptance under Sub-Clause 8.2, including any extension thereof under Sub-Clause 38.1, if applicable, or any extended period as may otherwise be agreed upon between HPC and the Supplier. For the avoidance of doubt, any actions required to be taken by the Supplier under the revised program including, but not limited to, an increase to working hours and/or Supplier's Personnel and/or Supplier's Equipment and/or goods and materials etc., shall all be taken at the risk and cost of the Supplier. Nothing in this Sub-Clause 18.4 shall relieve the Supplier of any responsibility, obligation or liability imposed upon it by any provisions of the Contract, and nothing in this Sub-Clause 18.4 shall further derogate from any right and/or demand and/or claim reserved to HPC under this Contract and/or any Laws and Regulations.

Related to Progress of Performance

  • Time of Performance Time for performance of the Scope of Services under this Agreement shall begin with receipt of the Notice to Proceed and end no later than December 31, 2026. Consultant shall complete the tasks described in the Scope of Services, within this time or within such additional time as may be extended by the County.

  • Excuse of Performance Seller shall not be liable for delays in performance or for non-performance due to failure or interruption of computer or telecommunication systems, acts of God, war, riot, fire, terrorism, labor trouble, unavailability of materials or components, explosion, accident, compliance with governmental requests, laws, regulations, orders or actions, or other unforeseen circumstances or causes beyond Seller's reasonable control. In the event of such delay, the time for performance or delivery shall be extended by a period of time reasonably necessary to overcome the effect of the delay.

  • Standards of Performance A. The standard of care for all professional and related services performed or furnished by Contractor under this Agreement will be the care and skill ordinarily used by members of Contractor’s profession practicing under similar conditions and circumstances and in a similar locality.

  • PERIOD OF PERFORMANCE The period of performance for this contract begins , and ends . ARTICLE 4.

  • Limitations of Performance The Custodian shall not be responsible under this Agreement for any failure to perform its duties, and shall not be liable hereunder for any loss or damage in association with such failure to perform, for or in consequence of the following causes:

  • Prevention of Performance The Custodian will not be responsible for any failure to perform any of its obligations (nor will it be responsible for any unavailability of funds credited to the Cash Account) if such performance is prevented, hindered or delayed by a Force Majeure Event, in such case its obligations will be suspended for so long as the Force Majeure Event continues. “Force Majeure Event” means any event due to any cause beyond the reasonable control of the Custodian, such as restrictions on convertibility or transferability, requisitions, involuntary transfers, unavailability of communications system, sabotage, fire, flood, explosion, acts of God, civil commotion, strikes or industrial action of any kind, riots, insurrection, war or acts of government.

  • Manner of Performance Subject to the provisions of Article XII hereof, the Contractor shall perform all of the Work described in the Statement of Work, or cause such Work to be performed in an efficient and expeditious manner and in accordance with all of the terms and provisions of this Agreement. The Contractor shall perform the Work in accordance with the current professional standards and with the diligence and skill expected for the performance of work of the type described in the Statement of Work. The Contractor shall furnish such personnel and shall procure such materials, machinery, supplies, tools, equipment and other items as may reasonably be necessary or appropriate to perform the Work in accordance with this Agreement.

  • Standard of Performance Consultant represents and warrants that it has the qualifications, experience and facilities necessary to properly perform the services required under this Agreement in a thorough, competent and professional manner. Consultant shall at all times faithfully, competently and to the best of its ability, experience and talent, perform all services described herein. In meeting its obligations under this Agreement, Consultant shall employ, at a minimum, generally accepted standards and practices utilized by persons engaged in providing services similar to those required of Consultant under this Agreement.

  • Guaranty of Performance Each Guarantor also guaranties the full, prompt and unconditional performance of all obligations and agreements of every kind owed or hereafter to be owed by the Borrower to the Agent or the Lenders under the Credit Agreement and the other Loan Documents to which the Borrower is a party. Every provision for the benefit of the Agent or the Lenders contained in this Guaranty shall apply to the guaranty of performance given in this paragraph.

  • Suspension of Performance Notwithstanding any other provision hereof, if an Event of Default or a Potential Event of Default has occurred and is continuing, the Non-Defaulting Party, upon written notice to the Defaulting Party, has the right (i) to suspend performance under any or all Transactions and (ii) to the extent an Event of Default has occurred and is continuing, to exercise any remedy available at law or in equity, except as limited be Section 5.7.

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!