Concurrent Delay definition

Concurrent Delay has the meaning provided in Section 4.4.2(a).
Concurrent Delay has the meaning given in clause 19.4 (“Suspension of obligations”).
Concurrent Delay means a situation where both City and Contractor are responsible for delays affecting the Critical Path where none of the delay events are utilizing available Project Float.

Examples of Concurrent Delay in a sentence

  • The Parties further acknowledge and agree that the damages for a Concurrent Delay are difficult or impossible to determine and that the damages calculated hereunder constitute a reasonable approximation of the harm or loss to Distribution Company as a result thereof.

  • Buyer shall be entitled to the remedies provided under the TSA with regard to any such Transmission Delay, and Seller shall have no liability to Buyer for Delay Damages solely as a result of any Owner Delay or Concurrent Delay (each as defined in the TSA).

  • A Concurrent Delay shall not affect Design-Builder’s right to a Completion Deadline adjustment hereunder.

  • The CMR may be allowed Days but the Department will have no liability for the following non- compensable items: .1 Abnormal or unusually severe weather; .2 Acts of God; .3 Force Majeure; .4 Concurrent Delay.

  • In the event of a Concurrent Delay, Design-Builder shall not be entitled to Delay Costs for the duration of the delay that is concurrent with a delay to the Critical Path for which Design-Builder is responsible.

  • By way of clarification, and not limitation, in no event shall the SI be entitled to Impact Costs attributable to a Concurrent Delay.

  • If the Consultant’s Work has been delayed pursuant to a Contemplated Delay and a separate delay also arises for all or a portion of the same period of time for which Consultant is not entitled to additional time (the “Concurrent Delay”), then the extension of time that Consultant would otherwise be entitled to as a result of the Contemplated Delay shall be reduced by the number of days that the Concurrent Delay exists during such Contemplated Delay.

  • Concurrent Delay Construction Cost Estimate Construction Cost Markup (or CM/GC Fee) Construction Documents Construction Pricing Documents Construction Provisions Construction Work Constructor A Principal Participant or Subcontractor that performs Construction Work for the Project.

  • SUBSTANTIAL COMPLETION DATE 33 13.1 Proposal and Baseline Schedules 33 13.2 Excusable Delays 34 13.3 Adjustment of Scheduled Substantial Completion Date 35 13.4 Force Majeure Events 36 13.5 Remedy for Concurrent Delay 36 13.6 Recovery Schedules.

  • In the event of a Concurrent Delay, Contractor shall not be entitled to Delay Costs for the duration of the delay that is concurrent with a delay to the Critical Path for which Contractor is responsible.


More Definitions of Concurrent Delay

Concurrent Delay is defined as the occurrence on a particular date of one or more instances of Owner Delay and Contractor Delay, Owner Delay and No-Fault Delay or Contractor Delay and No-Fault Delay.
Concurrent Delay has the meaning set out in Schedule 2 [General Conditions];
Concurrent Delay has the meaning assigned to it in Article 28.
Concurrent Delay is defined as a day on which the critical path of a Work Order Schedule is delayed and which delay is caused by both a Contractor Caused Delay and an Owner Responsible Delay.
Concurrent Delay means a delay caused by the occurrence of more than one unrelated event, each of which, independent of the other event(s), causes a delay to the then current critical path for completion of the Work or an Interface Milestone, without regard for which event occurred first in time, but only to the extent that the events overlap in time; and