Method of Measurement. The emission of voltage changes, voltage fluctuations and flicker on AC power lines generated by the vehicle representative of its type shall be measured using the method described in Annex 12. The method of measurement shall be defined by the vehicle manufacturer in accordance with the Technical Service.
AutoNDA by SimpleDocs
Method of Measurement. 12.10 All linear and area measurements under this Agreement are measured on the horizontal plane, unless specified otherwise in an attached Schedule.
Method of Measurement. The electromagnetic radiation generated by the vehicle representative of its type shall be measured using the method described in Annex 4. The method of measurement shall be defined by the vehicle manufacturer in accordance with the Technical Service.
Method of Measurement. The electromagnetic radiation generated by the ESA representative of its type shall be measured by the method described in Annex 7.
Method of Measurement. The emission of radiofrequency conducted disturbances on AC or DC power lines generated by the vehicle representative of its type shall be measured using the method described in Annex 13. The method of measurement shall be defined by the vehicle manufacturer in accordance with the Technical Service.
Method of Measurement. The emission of radiofrequency conducted disturbances on wired network port generated by the vehicle representative of its type shall be measured using the method described in Annex 14. The method of measurement shall be defined by the vehicle manufacturer in accordance with the Technical Service.
Method of Measurement. The weight of reinforcing steel incorporated in concrete and actually in place or shown on the plans or as directed by the Superintending Engineer will be determined correct to one kilogram on the following basis. The lengths of various sizes of rods will be measured after placing in position and weight calculated. For the purpose of calculating the weight 0 rods placed in position the weight per foot length of the rods of each size shall be determined by actual weighment of sample taken from each consignment of approximately 10 tones. When the bars are supplied by the manufacturers on the basis of section weight, then section weight shall apply
AutoNDA by SimpleDocs
Method of Measurement. Supplying, spreading and consolidation of materials will be measured by area in m2 (sqare feet), the length actually being taken along the centre line of the metalling and the width along the line at right angle to the centre line.
Method of Measurement. (2/D/6) The prices throughout this Document are to include for digging in any type of ground including loose or compacted hardcore, rubble debris and the like, roots, or normal obstructions, with the exception of rock as defined herein and excluding any existing foundations, walls and similar hard substances. The Contractor must give notification to the Architect or his representatives as soon as he considers rock as defined herein or existing foundations are encountered so that its extent can be agreed with the Architect, Clerk of Works, or Quality Surveyor before the work is carried out or covered up. Payment for such excavation will not be allowed unless this procedure is followed. The formation and removal of temporary spoil heaps and multiple handling or excavated material shall be deemed to be included in the prices for returning excavated material around foundations, earth filling and removing surplus excavated material from site. Excavation for plain concrete foundation has been measured to the net sizes required by concrete dimensions. Formwork has been measured to the sides of all reinforced concrete foundations or bases, together with the necessary working space allowance required under the provisions of SMM Clause D5(f). should the Architect direct or approve the pouring of concrete to reinforced foundations or bases against the face of excavations, such adjustment will be measured and valued in accordance with the Conditions of Contract. Rates for excavation shall be deemed to include for leveling, trimming and compacting bottoms and any additional excavation required for planking and strutting. Specification Excavation and Earthwork (2/D/7) CONCRETE WORK LIST OF CLAUSES QUALIFICATIONS OF THE RULES OF THE SMM F.1 Beds or the like laid in bays F.2 Steel bar reinforcement F.3 Wrought formwork F.4 Formwork to grooves, chases, chamfers and mould F.5 Making good DEFINITIONS F.6 Designations of concrete mixes F.7 Tamping F.8 keying F.9 Precast concrete units GENERALLY F.10 Standards F.11 Bar bending schedules MATERIALS F.12 Samples F.13 Cement F.14 Aggregates F.15 Reinforcement F.16 Expansion joint material F.17 Expansion joint sealer F.18 Wall ties F.19 Water F.20 Storage of materials F.21 Proportions of concrete mix F.22 Testing of materials generally Specification Concrete Work (2/F/1) F.23 Testing of cement F.24 Testing of aggregate F.25 Testing of reinforcement F.26 Testing of concrete in the field F.27 Damage or unsatisfactory materials WORKMA...
Method of Measurement. Prices are to include for working concrete around pipes and electric conduits or cable, including provision for support of same while concrete is placed. The prices for insitu work are to include for filling into, or on to, formwork where necessary, and where concrete is described as reinforced for well tamping reinforcement. Unless otherwise described, all formwork and reinforcement are measured separately. Prices for precast concrete work; including items described as precast or insitu, shall include for all moulds, for hoisting and for placing in position, bedding, jointing or building in with cement mortar. All reinforcing bars are of round section unless otherwise stated and no allowance has, or will be, made for rolling margin. Prices for holes shall include for them being on rake where so required and shall include the necessary holes through formwork. The cost of all construction joints, as described herein and not specifically shown on the drawings and measured separately in this Document, shall be deemed to be included in the rates set against the other items in this Document. The cost of providing all samples described herein shall be deemed to be included in the contract sum. The cost of performing all tests described herein shall be deemed to be included in the contract sum except the net invoiced cost of testing items or samples at authorized testing laboratories as instructed by the Architect or Engineer, which costs will be reimbursed from the Provisional Sum included elsewhere in this document. Xxxxxx purchased for the fabrication of formwork will be regarded as construction plant and will not be paid for as materials on site. Specification Concrete Work (2/F/19) XXXXXXX LIST OF CLAUSES