Construction Period Reports Sample Clauses

Construction Period Reports. (i) The Concessionaire shall within 30 (Thirty) Days after the execution of the EPC Contract provide to the Authority / Nodal Officer/’Project Monitoring & Supervision Consultants’ a copy of the construction schedule created using network techniques. A detailed explanation of the construction methodology, outlining the quality assurance, safety and surveillance plan shall also be included.
AutoNDA by SimpleDocs
Construction Period Reports. (a) The Borrower shall promptly, and in any event within five Business Days, after receipt from the P1 CASA Advisor, deliver to the TCF Administrative Agent and the Independent Engineer a copy of any material written statement, budget, plan or reports delivered to the Borrower under the P1 CASA (including any such statements, budget, plan or report with respect to the Rio Grande Facility) and all lien and claim waivers with respect to the Rio Grande Facility required to be delivered pursuant to Section 3.10(c) (Other Services) of the P1 CASA.
Construction Period Reports. The Developer shall provide to DMA and the Independent Engineer a monthly progress report during the Construction Period for Project , which shall contain the following information
Construction Period Reports. The Licensee shall provide to the Authority and the Nominated official of HMDA a weekly progress report during the Construction Period, which shall contain the following information:
Construction Period Reports. The Concessionaire shall provide to the Concessioning Authority and the Zonal Manager, Cyberabad a weekly progress report during the Construction Period, which shall contain the following information:

Related to Construction Period Reports

  • Extended Reporting Period If any required insurance coverage is on a claims-made basis (rather than occurrence), Contractor shall maintain such coverage for a period of no less than three (3) years following expiration or termination of the Contract.

  • Required Reports (1) As required in Attachment H, Disadvantaged Business Enterprise or Historically Underutilized Business Program Requirements, the Engineer shall submit Progress Assessment Reports to report actual payments made to Disadvantaged Business Enterprises or Historically Underutilized Businesses. One copy shall be submitted with each billing statement and one copy shall be submitted to the address included in Attachment H, Disadvantaged Business Enterprise or Historically Underutilized Business Program Requirements.

  • Construction Reports Each Constructing Entity shall issue reports to each other Construction Party on a monthly basis, and at such other times as reasonably requested, regarding the status of the construction and installation of the Interconnection Facilities. Each Construction Party shall promptly identify, and shall notify each other Construction Party of, any event that the Construction Party reasonably expects may delay completion, or may significantly increase the cost, of the Interconnection Facilities. Should a Construction Party report such an event, Transmission Provider shall, within fifteen days of such notification, convene a technical meeting of the Construction Parties to evaluate schedule alternatives.

  • Environmental Compliance and Reports Borrower shall comply in all respects with any and all Environmental Laws; not cause or permit to exist, as a result of an intentional or unintentional action or omission on Borrower's part or on the part of any third party, on property owned and/or occupied by Borrower, any environmental activity where damage may result to the environment, unless such environmental activity is pursuant to and in compliance with the conditions of a permit issued by the appropriate federal, state or local governmental authorities; shall furnish to Lender promptly and in any event within thirty (30) days after receipt thereof a copy of any notice, summons, lien, citation, directive, letter or other communication from any governmental agency or instrumentality concerning any intentional or unintentional action or omission on Borrower's part in connection with any environmental activity whether or not there is damage to the environment and/or other natural resources. Additional Assurances. Make, execute and deliver to Lender such promissory notes, mortgages, deeds of trust, security agreements, assignments, financing statements, instruments, documents and other agreements as Lender or its attorneys may reasonably request to evidence and secure the Loans and to perfect all Security Interests.

  • Construction, Etc Each covenant contained herein shall be construed (absent express provision to the contrary) as being independent of each other covenant contained herein, so that compliance with any one covenant shall not (absent such an express contrary provision) be deemed to excuse compliance with any other covenant. Where any provision herein refers to action to be taken by any Person, or which such Person is prohibited from taking, such provision shall be applicable whether such action is taken directly or indirectly by such Person. For the avoidance of doubt, all Schedules and Exhibits attached to this Agreement shall be deemed to be a part hereof.

Time is Money Join Law Insider Premium to draft better contracts faster.