Construction Period Reports. (a) The Borrower shall promptly, and in any event within five Business Days, after receipt from the P1 CASA Advisor, deliver to the TCF Administrative Agent and the Independent Engineer a copy of any material written statement, budget, plan or reports delivered to the Borrower under the P1 CASA (including any such statements, budget, plan or report with respect to the Rio Grande Facility) and all lien and claim waivers with respect to the Rio Grande Facility required to be delivered pursuant to Section 3.10(c) (Other Services) of the P1 CASA. (b) Not later than thirty days after the end of each month following the month during which the Closing Date occurs up to and including the month during which the Project Completion Date occurs, the Borrower shall deliver to the TCF Administrative Agent a monthly construction report from the Independent Engineer regarding the construction activities in relation to the Project carried out during such month based on the report delivered by the P1 CASA Advisor under Section 3.3(j) (Requirements of Independent Engineers) of the P1 CASA and such other information reasonably requested by the Independent Engineer. |US-DOCS\164448857.1|| (c) The Borrower shall promptly, and in any event within five Business Days, after receipt from the P1 EPC Contractor, deliver to the TCF Administrative Agent and the Independent Engineer a copy of the Substantial Completion Certificate (as defined in each of the P1 EPC Contracts) with respect to each of Train 1, Train 2, and Train 3.
Appears in 1 contract
Sources: Credit Agreement (NextDecade Corp)
Construction Period Reports. (a) The Borrower shall promptly, and in any event within five Business Days, after receipt from the P1 CASA Advisor, deliver to the TCF Administrative Agent and the Independent Engineer a copy of any material written statement, budget, plan or reports delivered to the Borrower under the P1 CASA (including any such statements, budget, plan or report with respect to the Rio Grande Facility) and all lien and claim waivers with respect to the Rio Grande Facility required to be delivered pursuant to Section 3.10(c) (Other Services) of the P1 CASA.
(b) Not later than thirty days after the end of each month following the month during which the Closing Date occurs up to and including the month during which the Project Completion Date occurs, the Borrower shall deliver to the TCF Administrative Agent a monthly construction report from the Independent Engineer regarding the construction activities in relation to the Project carried out during such month based on the report delivered by the P1 CASA Advisor under Section 3.3(j) (Requirements of Independent Engineers) of the P1 CASA and such other information reasonably requested by the Independent Engineer. |US-DOCS\164448857.1||.
(c) The Borrower shall promptly, and in any event within five Business Days, after receipt from the P1 EPC Contractor, deliver to the TCF Administrative Agent and the Independent Engineer a copy of the Substantial Completion Certificate (as defined in each of the P1 EPC Contracts) with respect to each of Train 1, Train 2, and Train 3.
Appears in 1 contract
Construction Period Reports. (a) The Borrower shall promptly, and in any event within five Business Days, after receipt from the P1 CASA Advisor, deliver to the TCF P1 Administrative Agent and the Independent Engineer a copy of any material written statement, budget, plan or reports delivered to the Borrower under the P1 CASA (including any such statements, budget, plan or report with respect to the Rio Grande Facility) and all lien and claim waivers with respect to the Rio Grande Facility required to be delivered pursuant to Section 3.10(c) (Other Services) of the P1 CASA.
(b) Not later than thirty days after the end of each month following the month during which the Closing Date occurs up to and including the month during which the Project Completion Date occurs, the Borrower shall deliver to the TCF P1 Administrative Agent a monthly construction report from the Independent Engineer regarding the construction activities in relation to the Project carried out during such month based on the report delivered by the P1 CASA Advisor under Section 3.3(j) (Requirements of Independent Engineers) of the P1 CASA and such other information reasonably requested by the Independent Engineer. |US-DOCS\164448857.1||.
(c) The Borrower shall promptly, and in any event within five Business Days, after receipt from the P1 EPC Contractor, deliver to the TCF P1 Administrative Agent and the Independent Engineer a copy of the Substantial Completion Certificate (as defined in each of the P1 EPC Contracts) with respect to each of Train 1, Train 2, and Train 3.
Appears in 1 contract
Construction Period Reports. (a) The Borrower shall promptly, and in any event within five Business Days, after receipt from the P1 CASA Advisor, deliver to the TCF P1 Administrative Agent and the Independent Engineer a copy of any material written statement, budget, plan or reports delivered to the Borrower under the P1 CASA (including any such statements, budget, plan or report with respect to the Rio Grande Facility) and all lien and claim waivers with respect to the Rio Grande Facility required to be delivered pursuant to Section 3.10(c) (Other Services) of the P1 CASA.
(b) Not later than thirty days after the end of each month following the month during which the Closing Date occurs up to and including the month during which the Project Completion Date occurs, the Borrower shall deliver to the TCF P1 Administrative Agent a monthly construction report from the Independent Engineer regarding the construction activities in relation to the Project carried out during such month based on the report delivered by the P1 CASA Advisor under |US-DOCS\137622719.74|| Section 3.3(j) (Requirements of Independent Engineers) of the P1 CASA and such other information reasonably requested by the Independent Engineer. |US-DOCS\164448857.1||.
(c) The Borrower shall promptly, and in any event within five Business Days, after receipt from the P1 EPC Contractor, deliver to the TCF P1 Administrative Agent and the Independent Engineer a copy of the Substantial Completion Certificate (as defined in each of the P1 EPC Contracts) with respect to each of Train 1, Train 2, and Train 3.
Appears in 1 contract
Sources: Credit Agreement (NextDecade Corp)
Construction Period Reports. (a) The Borrower shall promptly, and in any event within five Business Days, after receipt from the P1 CASA Advisor, deliver to the TCF P1 Administrative Agent and the Independent Engineer a copy of any material written statement, budget, plan or reports delivered to the Borrower under the P1 CASA (including any such statements, budget, plan or report with respect to the Rio Grande Facility) and all lien and claim waivers with respect to the Rio Grande Facility required to be delivered pursuant to Section 3.10(c) (Other Services) of the P1 CASA.
(b) Not later than thirty days after the end of each month following the month during which the Closing Date occurs up to and including the month during which the Project Completion Date occurs, the Borrower shall deliver to the TCF P1 Administrative Agent a monthly construction report from the Independent Engineer regarding the construction activities in relation to the Project carried out during such month based on the report delivered by the P1 CASA Advisor under Section 3.3(j) (Requirements of Independent Engineers) of the P1 CASA and such other information reasonably requested by the Independent Engineer. |US-DOCS\164448857.1||DOCS\137622719.74||
(c) The Borrower shall promptly, and in any event within five Business Days, after receipt from the P1 EPC Contractor, deliver to the TCF P1 Administrative Agent and the Independent Engineer a copy of the Substantial Completion Certificate (as defined in each of the P1 EPC Contracts) with respect to each of Train 1, Train 2, and Train 3.
Appears in 1 contract
Sources: Credit Agreement (NextDecade Corp)