APPROVAL OF PLANS AND DRAWINGS AND INSPECTION DURING CONSTRUCTION Sample Clauses

APPROVAL OF PLANS AND DRAWINGS AND INSPECTION DURING CONSTRUCTION. 1. Approval of Plans and Drawings:
AutoNDA by SimpleDocs
APPROVAL OF PLANS AND DRAWINGS AND INSPECTION DURING CONSTRUCTION. 1. Approval of Plans and Drawings 19 2. Appointment of BUYER’s Supervisor 19 3. Inspection by the Supervisor 20 4. Facilities 21 5. Liability of BUILDER 21 6. Responsibility of BUYER 22 ARTICLE V - MODIFICATIONS, CHANGES AND EXTRAS
APPROVAL OF PLANS AND DRAWINGS AND INSPECTION DURING CONSTRUCTION. 1. Approval of Plans and Drawings: Approved plans and drawings of the BUILDER’s HN. 1674 (including all amendments, additions, deletions and variations incorporated into the Specification up to the date of this Contract signing) shall be deemed to be approved by the BUYER and shall be applied to the Drillship. The BUILDER shall be exempted from the approval of the BUYER for the plans and drawings in accordance with the Specifications. All plans and drawings, which are modified by the BUILDER shall, however, be subject to approval by the BUYER in accordance with Article V.
APPROVAL OF PLANS AND DRAWINGS AND INSPECTION DURING CONSTRUCTION. 1. APPROVAL OF PLANS AND DRAWINGS The Builder shall, within sixty (60) days after the Effective Date, present to the Buyer for its approval a list of typical drawings, schematic diagrams and other documents, with their preliminary time schedules to be presented to the Buyer for the Buyer's information. The Builder shall at the same time present to the Buyer the Builder's system of identifying drawings and diagrams.
APPROVAL OF PLANS AND DRAWINGS AND INSPECTION DURING CONSTRUCTION. 1. Approval of Plans and Drawings: BUILDER shall submit to BUYER three (3) copies of each of the plans and drawings, the list of which shall be mutually agreed upon between the parties hereto, for its approval. BUYER shall, within seventeen (17) days after receipt thereof, return to BUILDER one (1) copy of such plans and drawings with BUYER’s approval or comments (if any) written thereon, provided always that: if the REPRESENTATIVE (as hereinafter defined) shall have been sent by BUYER to the SHIPYARD as set out in Article IV.2, BUILDER may submit any remaining plans and drawings to the REPRESENTATIVE for his approval. The REPRESENTATIVE shall, within seven (7) days after receipt thereof, return to BUILDER one (1) copy of such plans and drawings with his approval or comments (if any) written thereon. Approval by the REPRESENTATIVE of the plans and drawings duly submitted to him shall be deemed to be approval by BUYER for all purposes of this CONTRACT. If the above comments made by BUYER are not clearly specified or detailed, BUILDER shall seek clarification from BUYER, and BUYER shall give its explanation thereto without undue delay and with reasonably sufficient detail. If BUYER fails to comply, BUILDER may place its own interpretation on such comments in implementing the same. If BUYER or the REPRESENTATIVE shall fail to return the plans and drawings to BUILDER within the time limits as above provided, such plans and drawings shall be deemed to have been approved or confirmed without any comment. Any approval or absence of approval by BUYER shall not relieve BUILDER of its obligations to build the DRILLSHIP in accordance with the SPECIFICATIONS.
APPROVAL OF PLANS AND DRAWINGS AND INSPECTION DURING CONSTRUCTION. 1. Approval of Plans and Drawings As soon as practical after the Date of Contract the Builder shall put forward a proposed detailed building schedule, including a schedule for testing. The Buyer shall make its comment on the schedule as soon as practical and at the latest within seven (7) days. The schedules shall be issued by the Builder in writing not later than thirty (30) days after the Date of Contract.
APPROVAL OF PLANS AND DRAWINGS AND INSPECTION DURING CONSTRUCTION. 21 6.1 Schedule and Project Management & Scheduling Information 21
AutoNDA by SimpleDocs
APPROVAL OF PLANS AND DRAWINGS AND INSPECTION DURING CONSTRUCTION. 6.1 Schedule and Project Management & Scheduling Information Within thirty calendar days after signing of the contract, the Builder shall submit a complete Master Construction Schedule to the buyerLevel 1 (Milestones) and within 60 days Level
APPROVAL OF PLANS AND DRAWINGS AND INSPECTION DURING CONSTRUCTION. 1. Approval of Plans and Drawings: BUILDER shall submit to BUYER three (3) copies of each of the plans and drawings, the list of which shall be mutually agreed upon between the parties hereto, for its approval. BUYER shall, within seventeen (17) days after receipt thereof, return to BUILDER one (1) copy of such plans and drawings with BUYER’s approval or comments (if any) written thereon, provided always that:
APPROVAL OF PLANS AND DRAWINGS AND INSPECTION DURING CONSTRUCTION. 1. Approval of Plans and Drawings: All plans and drawings of HN.1837 shall be deemed to be approved and applicable to the Drillship without any distinct approval procedure.