Progress Payment at Initial Acceptance. A payment will be made to Contractor at the conclusion of the Initial Acceptance Test (IAT), if EWEB determines that the system substantially meets the criteria described in the IAT plan. This payment will cover costs for construction the accepted AMI communications network. Payment will also cover software licensing and installation costs related to the AMI Master Station and associated systems, along with CIS- AMI integration costs. Acceptance criteria and a fixed payment amount will be determined during negotiations with the winning bidder. Bidders should expect a hold back of percentage of this progress payment in the event that the IAT identifies areas where test results were not satisfactory but both parties choose to proceed with Full Scale Deployment on the condition that the issues are resolving before Final Acceptance.
AutoNDA by SimpleDocs

Related to Progress Payment at Initial Acceptance

  • PROGRESS PAYMENT 5.4.1 After receipt by the Contract Administrator of a Proper Invoice submitted by the Contractor in accordance with 5.3 – PROPER INVOICES:

  • Progress Payments; Retainage A. Owner shall make progress payments on account of the Contract Price on the basis of Contractor’s Applications for Payment on or about the first day of each month during performance of the Work as provided in Paragraph 6.02.A.1 below, provided that such Applications for Payment have been submitted in a timely manner and otherwise meet the requirements of the Contract. All such payments will be measured by the Schedule of Values established as provided in the General Conditions (and in the case of Unit Price Work based on the number of units completed) or, in the event there is no Schedule of Values, as provided elsewhere in the Contract.

  • Progress Payments 5.1.1 Based upon Applications for Payment submitted to the Architect by the Contractor and Certificates for Payment issued by the Architect, the Owner shall make progress payments on account of the Contract Sum to the Contractor as provided below and elsewhere in the Contract Documents.

  • Final Acceptance When the Project/Service or any portion thereof, as designated by the COUNTY, is ready for its intended use, the COUNTY and any other invited parties shall make an inspection of the Project/Service, to verify its completeness and develop a punch list of items needing completion or correction before final payment will be made. CONTRACTOR shall have ten (10) calendar days to correct all deficiencies. An eighty-dollar ($80.00) re-inspection fee shall be applied for the third inspection and any required re-inspection thereafter. The COUNTY shall have the right to exclude CONTRACTOR from those portions of the work designated as complete after the inspection; provided, however, that CONTRACTOR will have reasonable access for the time allotted by the COUNTY to complete or correct items on the punch list. When the work provided for under this Agreement has been completely performed by CONTRACTOR, and the final inspection has been made by the COUNTY, a final invoice will be prepared by the CONTRACTOR. The amount of this invoice, less any sums that may have been deducted or retained under the provisions of this Agreement, will be paid to CONTRACTOR in accordance with this Agreement, and after CONTRACTOR has agreed in writing to accept the balance due, as determined by the COUNTY, as full settlement of the account under the contract and of all claims in connection therewith. Occupancy by the COUNTY alone does not constitute final acceptance.

  • Order Acceptance All orders are subject to acceptance only at Seller’s facility in Farmington, Connecticut. These Terms of Sale shall be deemed accepted by Buyer upon Seller’s receipt of Purchase Order from Buyer. No condition stated by Buyer shall be binding upon Seller if in conflict with, inconsistent with or in addition to the Terms of Sale, unless expressly accepted in a writing signed by Seller. In the event of conflict or differences in the terms or conditions of Buyer’s Purchase Order and the Terms of Sale herein, the Terms of Sale shall govern.

  • INSPECTION, ACCEPTANCE AND REJECTION a. All Goods will be subject to Mercy Corps' inspection and testing (which may be done by a third party authorized by Mercy Corps), at any time and place, including the period of manufacture/production/creation and before final acceptance. If Mercy Corps inspects or tests at Supplier's premises, Supplier, without additional charge, will provide all reasonable facilities and assistance for the safety and convenience of Mercy Corps' inspectors. No inspection or testing done or not done before final inspection and acceptance will relieve Supplier from responsibility for defects or for other failure to meet the requirements of this Agreement. Notwithstanding any prior inspections or payments made, all Goods will be subject to final inspection and acceptance at the Delivery Location within a reasonable time after delivery (but in no event, less than three days after the date of delivery).

  • Final Completion Date Final Completion for the Work as defined in Article 6.1.3 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by September 30, 2022.

  • Acceptance/Payment Unless otherwise agreed to in writing by County, 1) acceptance shall not be deemed complete unless in writing and until all the goods/services have actually been received, inspected, and tested to the satisfaction of County, and 2) payment shall be made in arrears after satisfactory acceptance.

  • Final Completion The full and final completion of all Work in accordance with the Contract Documents.

  • Periodic Progress Payments The Owner shall make progress payments, less retainage, as set forth in Section 4 of the General Conditions.