Extension of Time not Cumulative Sample Clauses

Extension of Time not Cumulative. In case the Design-Build Firm shall be delayed for any period of time by two or more of the causes mentioned in Article 68, Excusable Delays the Design-Build Firm shall not be entitled to a separate extension for each one of the causes; only one period of extension shall be granted for the delay.
AutoNDA by SimpleDocs
Extension of Time not Cumulative. 7.11.1 In case the Contractor shall be delayed at any time or for any period by two or more causes for an extension of time, the Contractor shall not be entitled to a separate extension of time for each one of the causes but only one period of extension will be granted for the delay.
Extension of Time not Cumulative. In the event the Contractor shall be delayed concurrently by two or more of the causes identified in Article 38 "Extension of Time" above, the Contractor shall be entitled to a separate extension of time for each one of the causes but only one period of extension shall be granted for the delay. In addition, the Contractor shall not be entitled, by reason of a delay, to an extension of time for the completion of the overall Work unless the overall Work is necessarily affected by the delay. Accordingly, in the event of a delay, the Contractor shall proceed continuously and diligently with the performance of the unaffected portions of the Work.

Related to Extension of Time not Cumulative

  • Extension of Time If the Executive shall be in violation of any provision of this Article 6, then each time limitation set forth in this Article 6 shall be extended for a period of time equal to the period of time during which such violation or violations occur. If the Company seeks injunctive relief from such violation in any court, then the covenants set forth in this Article 6 shall be extended for a period of time equal to the pendency of such proceeding including all appeals by the Executive.

  • Extension of Time Limits The time limits referred to in this Article may be extended by mutual agreement of the parties in writing.

  • Extension of time for completion (i) Without prejudice to any other provision of this Agreement for and in respect of extension of time, the Contractor shall be entitled to extension of time in the Project Completion Schedule (the “Time Extension”) to the extent that completion of any Project Milestone is or will be delayed by any of the following, namely:

  • Delays and Extension of Time If the Contractor is delayed at any time in the progress of providing goods and/or services by an act or neglect of the District, or by changes ordered in the work, or by labor disputes, strikes, insurrections, fire, acts of God; unusual but well documented and excusable delays in performance, or other causes beyond the Contractor’s control, or by delay authorized by the District, then the contract Term of service may be extended by a contract amendment for such reasonable time as the District and the Contractor may agree.

  • No Extension of Time If the Owner’s determination proves valid that good cause existed to believe a violation had occurred, the Contractor is not entitled to an extension of time for any delay arising directly or indirectly from the arbitration procedures set forth herein.

  • Calculation of Time Periods Unless otherwise specified, in computing any period of time described in this Agreement, the day of the act or event after which the designated period of time begins to run is not to be included and the last day of the period so computed is to be included, unless such last day is a Saturday, Sunday or legal holiday under the laws of the State in which the Property is located, in which event the period shall run until the end of the next day which is neither a Saturday, Sunday or legal holiday. The final day of any such period shall be deemed to end at 5 p.m., local time.

  • Calculation of Time For the purposes of this Agreement, “days” refers to calendar days unless otherwise specified.

  • Computation of Time Periods In this Agreement in the computation of periods of time from a specified date to a later specified date, the word “from” means “from and including” and the words “to” and “until” each mean “to but excluding”.

  • Extension Term Provided Lessee is not in default in the performance of any term or condition of this Lease, Lessee shall have the option to extend this Lease for two (2) additional terms of five (5) years per term, commencing with the expiration of the first or additional term, upon the following conditions:

  • Extension Terms County may, at its sole option, extend the term of this Agreement beyond the Initial Term for up to ___ additional one-year terms at the same rates and under the same terms provided for herein (each such period being an “Extension Term”). County shall notify Contractor of its election for an Extension Term(s) as provided for in §6.

Time is Money Join Law Insider Premium to draft better contracts faster.