Reduction in Scope of the Project Sample Clauses

Reduction in Scope of the Project. 16.6.1 If the Concessionaire shall have failed to complete any Construction Works on account of Force Majeure or for reasons solely attributable to the Authority, the Authority may, in its discretion, require the Concessionaire to pay 80% (eighty percent) of the sum saved therefrom, and upon such payment to the Authority, the obligations of the Concessionaire in respect of such works shall be deemed to have been fulfilled. For the avoidance of doubt, it is agreed that in the event such reduction in Scope of the Project causes or will cause a reduction in net after-tax return of the Concessionaire, the Parties shall meet, as soon as reasonably practical, and agree on a full or partial waiver of the aforesaid payment of 80% (eighty per cent) so as to place the Concessionaire in the same financial position as it would have enjoyed had there been no reduction in Scope of the Project. It is further agreed that the liability of the Authority under this Clause 16.6 shall not extend beyond waiver of the aforesaid 80% (eighty per cent). It is also agreed that in the event of a dispute, the Dispute Resolution Procedure shall apply.
AutoNDA by SimpleDocs
Reduction in Scope of the Project. $ The Authority shall transfer 75% (seventy five percent) of the amount so received to the first ranked bidder whose bid shall have been matched by the Concessionaire.
Reduction in Scope of the Project. 16.6.1 If the Concessionaire shall have failed to complete any Construction Works on account of Force Majeure or for reasons solely attributable to the Concessioning Authority, the Concessioning Authority may, in its discretion, require the Concessionaire to pay 80% (eighty percent) of the sum saved therefrom, and upon such payment to the Concessioning Authority, the obligations of the Concessionaire in respect of such works shall be deemed to have been fulfilled.
Reduction in Scope of the Project. 16.6.1. If the Concessionaire shall have failed to complete any Construction Works on account of Force Majeure or for reasons solely attributable to the Authority, the Authority may, in its discretion, require the Concessionaire to pay 80% (eighty percent) of the sum saved therefrom, and upon such payment to the Authority, the obligations of the Concessionaire in respect of such works shall be deemed to have been fulfilled. For the avoidance of doubt, it is agreed that in the event such reduction in Scope of the Project causes or will cause a reduction in net after-tax return of the Concessionaire, the Parties shall meet, as soon as reasonably practical, and agree on a full or partial waiver of the aforesaid payment of 80% (eighty per cent) so as to place the Concessionaire in the same financial position as $ The Authority shall transfer 75% (seventy five percent) of the amount so received to the first ranked bidder whose bid shall have been matched by the Concessionaire. it would have enjoyed had there been no reduction in Scope of the Project. It is further agreed that the liability of the Authority under this Clause 16.6 shall not extend beyond waiver of the aforesaid 80% (eighty per cent). It is also agreed that in the event of a dispute, the Dispute Resolution Procedure shall apply.
Reduction in Scope of the Project. 16.6.1 If the Concessionaire shall have failed to complete any Construction Works on account of Force Majeure or for reasons attributable to the Authority or under the provision of Clause 10.3.4 of this Agreement, the Authority shall follow the following process for calculation of total cost of reduced Scope
Reduction in Scope of the Project. 16.6.1 If the Concessionaire shall have failed to complete any Construction Works on account of Force Majeure or for reasons solely attributable to MPRDC, MPRDC may, in its discretion, require the Concessionaire to pay 80% (eighty per cent) of the sum saved therefrom, and upon such payment to MPRDC, the obligations of the Concessionaire in respect of such works shall be deemed to have been fulfilled. For the avoidance of doubt, it is agreed that in the event such reduction in Scope of the Project causes or will cause a reduction in net after-tax return of the Concessionaire, the Parties shall meet, as soon as reasonably practical, and agree on a full or partial waiver of the aforesaid payment of 80% (eighty per cent) so as to place the Concessionaire in the same financial position as it would have enjoyed had there been no reduction in Scope of the Project. It is further agreed that the liability of MPRDC under this Clause 16.6 shall not extend beyond waiver of the aforesaid 80% (eighty per cent). It is also agreed that in the event of a dispute, the Dispute Resolution Procedure shall apply.
Reduction in Scope of the Project. 23.5.1 If the Change of Scope Order results in a reduction in Scope of the Project, the Mine Developer and Operator shall pay back to TANGEDCO the sum saved therefrom, if any, within 30 (thirty) days from the date of Change of Scope Order, and upon such payment to TANGEDCO, the obligations of the Mine Developer and Operator in respect of such works shall be deemed to have been fulfilled.
AutoNDA by SimpleDocs
Reduction in Scope of the Project. 16.6.1 If the Concessionaire shall have failed to complete any Construction Works on account of Force Majeure or for reasons solely attributable to the MPRDC, the MPRDC may in its discretion require the Concessionaire to pay 80% (eighty percent) of the sum saved therefrom, and upon such payment to the MPRDC, the obligations of the Concessionaire in respect of such works shall be deemed to have been fulfilled.
Reduction in Scope of the Project. 16.5.1 If the DEVELOPER has received full consideration and shall have failed to complete any Construction Works with respect to the Residential Property on account of Force Majeure or for reasons solely attributable to the SH&DB, the SH&DB may, in its discretion, require the DEVELOPER to pay 50%( fifty percent) of the sum saved therefrom, and upon such payment to the SH&DB, the obligations of the DEVELOPER in respect of such works shall be deemed to have been fulfilled. It is further agreed that the liability of the SH&DB under this shall not extend beyond waiver of the aforesaid 50% (fifty per cent). It is also agreed that in the event of a dispute, the Dispute Resolution Procedure shall apply.
Reduction in Scope of the Project. If the Concessionaire or the entity appointed by the Concessionaire shall have failed to complete any construction works on account of Force Majeure or for reasons solely attributable to the Authority, the Authority may, in its discretion, require the Concessionaire to pay 80% (eighty percent) of the sum saved therefrom, and upon such payment to the Authority, the obligations of the Concessionaire in respect of such works shall be deemed to have been fulfilled. For the avoidance of doubt, it is agreed that in the event such reduction in Scope of the Project causes or will cause a reduction in the net after-tax return of the Concessionaire, the Parties shall meet, as soon as reasonably practical, and agree on a full or partial waiver of the aforesaid payment of 80% (eighty per cent) so as to place the Concessionaire in the same financial position as it would have enjoyed had there been no reduction in Scope of the Project. It is further agreed that the liability of the Authority under this Clause 21.6 shall not extend beyond waiver of the aforesaid 80% (eighty per cent). It is also agreed that in the event of a dispute, the Dispute Resolution Procedure shall apply. ARTICLE 21A
Time is Money Join Law Insider Premium to draft better contracts faster.