Examples of Progress Milestone in a sentence
If, at any time, TSP’s actual progress in performing the Work as measured against the Project Schedule or any of the Progress Milestone Dates is inadequate to meet the requirements of this Contract, the Joint Board may so notify TSP.
If TSP has reason to believe that the Work will not be performed consistent with the Progress Milestone Dates, TSP shall promptly so notify the Joint Board, specifying in its notice any corrective action planned by TSP.
The Project Schedule shall indicate a Progress Milestone for completion of the Baseline Test that is not more than 180 days after NTP.
The Pre-Toll Operations Readiness Deadline, the Mobilization Readiness Deadline, the East-End Bridge Tolling Readiness Deadline, the Downtown Bridges Temporary Traffic Configuration Tolling Readiness Deadline and the Downtown Bridges Final Traffic Configuration Tolling Readiness Deadline, and the other Progress Milestone Dates shall not be modified except by Change Order.
The primary purpose of the progress meetings shall be to review the Project Schedule, the Progress Milestone Dates, and the Project Management Reports submitted by TSP and to examine and assess the actual progress of the Work, including the status of pending Change Orders and any other design or installation related issues which the parties may wish to discuss.
TSP may be entitled to an extension of Progress Milestone Dates or Completion Deadlines, but no additional compensation due to delays in the TSP’s ability to progress the work caused solely by the deficiencies in the ETC Contractor’s work, provided all other conditions to a Change Order specified in Section 13 are satisfied.
If a Party fails to meet a Progress Milestone Date, either Party can require the other Party to meet and confer regarding the impact to the Milestone Schedule of such failure with the goal of the Parties reaching mutual agreement on adjustments to the Progress Milestone Dates in the Milestone Schedule.
Mon 3/1/21 Fri 4/2/21 20 Award Construction Contract 2 wks Tue 4/6/21 Mon 4/19/21 Project: COLLIN COUNTY OUTER LO Date: Mon 5/13/19 Task Split Progress Milestone Summary Project Summary External Tasks External Milestone Deadline 2019-269 EXHIBIT “C” PAYMENT SCHEDULE Invoices will be transmitted to the County on a monthly basis based on a percentage of completion up to that time, and payments to the Engineer will be made as follows: A derivation of the total contract fee amount is attached.
All deadlines set forth in the Development Schedule that are not considered Major Milestone Dates are considered "Progress Milestone Dates." The Parties shall make commercially reasonable efforts to meet the Progress Milestone Dates but failure to meet a Progress Milestone Date shall not be considered an Event of Default pursuant to Section 14.2 unless, as a result of such failure, it would be impossible for a Major Milestone Date to be met.
If Developer is rendered wholly or partly unable to meet any Progress Milestone by the deadline set forth in Section 2.5 because of an event of Force Majeure, Developer’s time to meet such Progress Milestone date shall be extended to the extent such delay impacted its ability to maintain it schedule by the actual number of calendar days Developer was delayed to meet any such Progress Milestone Date as a direct and proximate result of such event of Force Majeure.