Termination for Default (Construction Sample Clauses

Termination for Default (Construction. If contractor refuses or fails to prosecute the work or any separable part, with the diligence that will insure its completion within the time specified, or any extension, or fails to complete the work within this time, or if contractor fails to comply with any other provisions of this contract, the recipient may terminate this contract for default. the recipient shall terminate by delivering to contractor a notice of termination specifying the nature of default. In this event, the recipient may take over the work and compete it by contract or otherwise, and may take possession of and use any materials, appliances, and plant on the work site necessary for completing the work. Contractor and its sureties shall be liable for any damage to the recipient resulting from contractor's refusal or failure to complete the work within specified time, whether or not contractor's right to proceed with the work is terminated. This liability includes any increased costs incurred by the recipient in completing the work. Contractor's right to proceed shall not be terminated nor shall contractor be charged with damages under this clause if:
AutoNDA by SimpleDocs
Termination for Default (Construction. If the Contractor refuses or fails to prosecute the work or any separable part, with the diligence that will insure its completion within the time specified in this contract or any extension or fails to complete the work within this time, or if the Contractor fails to comply with any other provisions of this contract, the Purchaser may terminate this contract for default. The Purchaser shall terminate by delivering to the Contractor a Notice of Termination specifying the nature of the default. In this event, the Purchaser may take over the work and compete it by contract or otherwise, and may take possession of and use any materials, appliances, and plant on the work site necessary for completing the work. The Contractor and its sureties shall be liable for any damage to the Purchaser resulting from the Contractor's refusal or failure to complete the work within specified time, whether or not the Contractor's right to proceed with the work is terminated. This liability includes any increased costs incurred by the Purchaser in completing the work. The Contractor's right to proceed shall not be terminated nor the Contractor charged with damages under this clause if:
Termination for Default (Construction. Section 80-09 of FAA Advisory Circular 150/5370-10 establishes conditions, rights, and remedies associated with Owner termination of this contract due to default of the Contractor.
Termination for Default (Construction. If the Contractor refuses or fails to prosecute the work or any separable part, with the diligence that will ensure its completion within the time specified in this contract or any extension or fails to complete the work within this time, or if the Contractor fails to comply with any other provision of this contract, City may terminate this contract for default. The City shall terminate by delivering to the Contractor a Notice of Termination specifying the nature of the default. In this event, the City may take over the work and compete it by contract or otherwise, and may take possession of and use any materials, appliances, and plant on the work site necessary for completing the work. The Contractor and its sureties shall be liable for any damage to the City resulting from the Contractor's refusal or failure to complete the work within specified time, whether or not the Contractor's right to proceed with the work is terminated. This liability includes any increased costs incurred by the City in completing the work. The Contractor's right to proceed shall not be terminated nor shall the Contractor be charged with damages under this clause if: 1. The delay in completing the work arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor. Examples of such causes include: acts of God, acts of City, acts of another contractor in the performance of a contract with City, epidemics, quarantine restrictions, strikes, freight embargoes; and 2. The Contractor, within [10] days from the beginning of any delay, notifies City in writing of the causes of delay. If, in the judgment of City, the delay is excusable, the time for completing the work shall be extended. The judgment of City shall be final and conclusive for the parties, but subject to appeal under the Disputes clause(s) of this contract. If, after termination of the Contractor's right to proceed, it is determined that the Contractor was not in default, or that the delay was excusable, the rights and obligations of the parties will be the same as if the termination had been issued for the convenience of City.
Termination for Default (Construction. If the Contractor refuses or fails to prosecute the work or any separable part, with the diligence that will insure its completion within the time specified in this contract or any extension or fails to complete the work within this time, or if the Contractor fails to comply with any other provisions of this contract, the county may terminate this contract for default. The County shall terminate by delivering to the Contractor a Notice of Termination specifying the nature of the default. In this event, the County may take over the work and complete it by contract or otherwise, and may take possession of and use any materials, appliances, and plant on the work site necessary for completing the work. The Contractor and its sureties shall be liable for any damage to the County resulting from the Contractor’s refusal or failure to complete the work within the specified time, whether or not the Contractor’s right to proceed with the work is terminated. This liability includes any increased costs incurred by the County in completing the work. The Contractor’s right to proceed shall not be terminated nor the Contractor charged with damages under this clause if:

Related to Termination for Default (Construction

  • Termination for Default; Remedies 8.2.1 Each of the following shall constitute an immediate event of default (“Event of Default”) under this Agreement:

  • Termination for Default The County may, by written notice to the Contractor terminate this contract for default in whole or in part (delivery orders, if applicable) if the Contractor fails to:

  • SUSPENSION & TERMINATION FOR DEFAULT Enterprise Services may suspend Contractor’s operations under this Master Contract immediately by written cure notice of any default. Suspension shall continue until the default is remedied to Enterprise Services’ reasonable satisfaction; Provided, however, that, if after thirty (30) days from such a suspension notice, Contractor remains in default, Enterprise Services may terminate Contractor’s rights under this Master Contract. All of Contractor’s obligations to Enterprise Services and Purchasers survive termination of Contractor’s rights under this Master Contract, until such obligations have been fulfilled.

  • Default Remedies Termination A. [Sec. 400]

  • Erroneous Termination for Default If, after notice of termination of Vendor’s right to proceed under the provisions of this clause, it is determined for any reason that the contract was not in default, or that the delay was excusable under the provisions of the prior paragraph (Excuse for Nonperformance or Delayed Performance), the rights and obligations of the parties shall be the same as if the notice of termination had been one of termination for convenience.

  • Performance Default and Remedies Subsection B. DEFAULT AND REMEDIES, second paragraph of the Contract is modified as follows (underlined language is added and stricken language is deleted): “Written notice of default and a reasonable 30-day opportunity to cure must be issued by the party claiming default.”

  • Termination Remedies In the event of any such material default under or material breach of the terms of this Lease by the Relevant Asset Owner, the Related Refinery Owner may, at the Related Refinery Owner’s option, at any time thereafter that such default or breach remains uncured, without further notice or demand:

  • Contractor Default Failure of the Contractor, which has neither been remedied nor waived, to perform or otherwise to comply with the terms of the Construction Contract.

  • CANCELLATION FOR DEFAULT a. Buyer may, by written notice to Seller, cancel all or part of this Contract: (i) if Seller fails to deliver the Goods within the time specified by this Contract or any written extension; (ii) if Seller fails to perform any other provision of this Contract or fails to make progress, so as to endanger performance of this Contract, and, in either of these two circumstances, within ten (10) days after receipt of notice from Buyer specifying the failure, does not cure the failure or provide Buyer with a written detailed plan adequate to cure the failure if such failure reasonably cannot be cured within such ten (10) days and such plan is acceptable to Buyer’s Authorized Procurement Representative; or (iii) in the event of Seller's bankruptcy, suspension of business, insolvency, appointment of a receiver for Seller's property or business, or any assignment, reorganization or arrangement by Seller for the benefit of its creditors.

  • Event of Default Remedies 8.1 Any one or more of the following acts or omissions of the Contractor shall constitute an event of default hereunder (“Event of Default”):