CONTRACTOR GUARANTEES AND LIQUIDATED DAMAGES Sample Clauses

CONTRACTOR GUARANTEES AND LIQUIDATED DAMAGES and (A) the Contract Price has been reduced in accordance with Section 10.5 for the percentage of the Final Acceptance Performance Level that has not been achieved and (B) Contractor has performed all Remediation Work requested by FPL related to any Work not associated with the percentage of the Final Acceptance Performance Level that has been achieved; *** CONFIDENTIAL MATERIAL REDACTED AND SEPARATELY FILED WITH THE SECURITIES AND EXCHANGE COMMISSION. Solar Photovoltaic EPC TURNKEY EPC AGREEMENT SOLAR PHOTOVOLTAIC GENERATING FACILITY (continued)
AutoNDA by SimpleDocs
CONTRACTOR GUARANTEES AND LIQUIDATED DAMAGES the Net Energy Output is equal to or greater than *** percent (***%) of the Net Energy Output Guarantee when corrected to Guarantee Design Conditions.
CONTRACTOR GUARANTEES AND LIQUIDATED DAMAGES. (e) The Project has achieved the Noise Guarantee simultaneously with the Minimum Performance Level;
CONTRACTOR GUARANTEES AND LIQUIDATED DAMAGES. Further, Contractor acknowledges that the implementation of any such recovery plan may result in material additional costs and expenditures for Contractor (including by way of overtime, additional crews and/or additional shifts). Contractor agrees that it shall not be entitled to a Change Order or any other compensation or increase in the Contract Price in connection with the implementation of any such recovery plan.
CONTRACTOR GUARANTEES AND LIQUIDATED DAMAGES. In addition, Contractor shall repeat the Tests in accordance with Section 11.6.1 during the applicable time periods set forth in Section 11.1, Completion Guarantee, of Article XI,
CONTRACTOR GUARANTEES AND LIQUIDATED DAMAGES. Contractor shall provide a written report of the results of each Test to FPL.

Related to CONTRACTOR GUARANTEES AND LIQUIDATED DAMAGES

  • Waiver of Liquidated Damages If the Partnership is unable to cause a Registration Statement to become effective on or before the Target Effective Date, then the Partnership may request a waiver of the Liquidated Damages, which may be granted by the consent of the Holders of at least the Registrable Securities Required Voting Percentage, in their sole discretion, and which such waiver shall apply to all the Holders of Registrable Securities included on such Registration Statement.

  • Obligation Absolute; Partial Liquidated Damages The Company’s obligations to issue and deliver the Conversion Shares upon conversion of this Debenture in accordance with the terms hereof are absolute and unconditional, irrespective of any action or inaction by the Holder to enforce the same, any waiver or consent with respect to any provision hereof, the recovery of any judgment against any Person or any action to enforce the same, or any setoff, counterclaim, recoupment, limitation or termination, or any breach or alleged breach by the Holder or any other Person of any obligation to the Company or any violation or alleged violation of law by the Holder or any other Person, and irrespective of any other circumstance which might otherwise limit such obligation of the Company to the Holder in connection with the issuance of such Conversion Shares; provided, however, that such delivery shall not operate as a waiver by the Company of any such action the Company may have against the Holder. In the event the Holder of this Debenture shall elect to convert any or all of the outstanding principal amount hereof, the Company may not refuse conversion based on any claim that the Holder or anyone associated or affiliated with the Holder has been engaged in any violation of law, agreement or for any other reason, unless an injunction from a court, on notice to Holder, restraining and or enjoining conversion of all or part of this Debenture shall have been sought and obtained, and the Company posts a surety bond for the benefit of the Holder in the amount of 150% of the outstanding principal amount of this Debenture, which is subject to the injunction, which bond shall remain in effect until the completion of arbitration/litigation of the underlying dispute and the proceeds of which shall be payable to the Holder to the extent it obtains judgment. In the absence of such injunction, the Company shall issue Conversion Shares or, if applicable, cash, upon a properly noticed conversion. If the Company fails for any reason to deliver to the Holder such Conversion Shares pursuant to Section 4(c)(ii) by the Share Delivery Date, the Company shall pay to the Holder, in cash, as liquidated damages and not as a penalty, for each $1,000 of principal amount being converted, $10 per Trading Day (increasing to $20 per Trading Day on the fifth (5th) Trading Day after such liquidated damages begin to accrue) for each Trading Day after such Share Delivery Date until such Conversion Shares are delivered or Holder rescinds such conversion. Nothing herein shall limit a Hxxxxx’s right to pursue actual damages or declare an Event of Default pursuant to Section 8 hereof for the Company’s failure to deliver Conversion Shares within the period specified herein and the Holder shall have the right to pursue all remedies available to it hereunder, at law or in equity including, without limitation, a decree of specific performance and/or injunctive relief. The exercise of any such rights shall not prohibit the Holder from seeking to enforce damages pursuant to any other Section hereof or under applicable law.

  • Payment of Liquidated Damages With respect to any Liquidated Damages that accrue, Owner shall invoice Contractor for such Liquidated Damages. Contractor shall pay such Liquidated Damages within ten (10) Days after Contractor’s receipt of such invoice. To the extent Contractor does not pay such Liquidated Damages within such ten (10) Day period, Owner may, at its option, do one or more of the following: (i) withhold from Contractor amounts that are otherwise due and payable to Contractor in the amount of such Liquidated Damages and/or (ii) collect on the Letter of Credit in the amount of such Liquidated Damages. For the avoidance of doubt, prior to exercising such right to withhold or collect on the Letter of Credit, Owner shall not be required to provide the notice as set forth in Section 7.8. As used in this Agreement, Liquidated Damages are “paid” if and to the extent Owner exercises option (i) or (ii) above for the collection of Liquidated Damages.

  • Payment of Damages The indemnification required hereunder shall be made by periodic payments of the amount thereof during the course of the investigation or defense, within 10 days as and when reasonably specific bills are received or loss, liability, claim, damage or expense is incurred and reasonable evidence thereof is delivered. In calculating any amount to be paid by an indemnifying party by reason of the provisions of this Agreement, the amount shall be reduced by all tax benefits and other reimbursements (including, without limitation, insurance proceeds) credited to or received by the other party related to the Damages.

  • Liquidated Damages The Company’s obligations to pay any partial liquidated damages or other amounts owing under the Transaction Documents is a continuing obligation of the Company and shall not terminate until all unpaid partial liquidated damages and other amounts have been paid notwithstanding the fact that the instrument or security pursuant to which such partial liquidated damages or other amounts are due and payable shall have been canceled.

  • Indemnification Obligations of Seller Seller shall defend, indemnify, save and keep harmless Purchaser and its successors and permitted assigns against and from all Damages sustained or incurred by any of them resulting from or arising out of or by virtue of:

  • Registration Obligations The Company expressly agrees to register, with the Securities and Exchange Commission, the shares of common stock underlying the options issued herein in a registration statement on Form S-8, if and when available (and all related qualifications under the state securities laws.

  • Duty Obligations and Liabilities (a) The Agent’s sole duty with respect to the custody, safekeeping and physical preservation of the Collateral in its possession shall be to deal with it in the same manner as the Agent deals with similar property for its own account. The powers conferred on the Agent hereunder are solely to protect the Agent’s interest in the Collateral and shall not impose any duty upon the Agent to exercise any such powers. The Agent shall be accountable only for amounts that it receives as a result of the exercise of such powers, and neither it nor any of its Related Persons shall be responsible to any Grantor for any act or failure to act hereunder, except for their own gross negligence, bad faith, or willful misconduct as determined by a court of competent jurisdiction in a final and non-appealable decision. In addition, the Agent shall not be liable or responsible for any loss or damage to any Collateral, or for any diminution in the value thereof, by reason of the act or omission of any warehousemen, carrier, forwarding agency, consignee or other bailee if such Person has been selected by the Agent in good faith.

  • Certain Rules Relating to the Payment of Additional Amounts (a) Upon the request, and at the expense of the Borrower, each Lender and Agent to which the Borrower is required to pay any additional amount pursuant to Subsection 4.10 or 4.11, and any Participant in respect of whose participation such payment is required, shall reasonably afford the Borrower the opportunity to contest, and reasonably cooperate with the Borrower in contesting, the imposition of any Non-Excluded Tax giving rise to such payment; provided that (i) such Lender or Agent shall not be required to afford the Borrower the opportunity to so contest unless the Borrower shall have confirmed in writing to such Lender or Agent its obligation to pay such amounts pursuant to this Agreement and (ii) the Borrower shall reimburse such Lender or Agent for its reasonable attorneys’ and accountants’ fees and disbursements incurred in so cooperating with the Borrower in contesting the imposition of such Non-Excluded Tax; provided, however, that notwithstanding the foregoing no Lender or Agent shall be required to afford the Borrower the opportunity to contest, or cooperate with the Borrower in contesting, the imposition of any Non-Excluded Taxes, if such Lender or Agent in its sole discretion in good faith determines that to do so would have an adverse effect on it.

  • Indemnification Obligations Subject to the limitations set forth in this Agreement, each Fund severally and not jointly agrees to indemnify and hold harmless the Custodian and its nominees from all loss, damage and expense (including reasonable attorneys' fees) suffered or incurred by the Custodian or its nominee caused by or arising from actions taken by the Custodian on behalf of such Fund in the performance of its duties and obligations under this Agreement; provided however, that such indemnity shall not apply to loss, damage and expense occasioned by or resulting from the negligence, misfeasance or misconduct of the Custodian or its nominee. In addition, each Fund agrees severally and not jointly to indemnify any Person against any liability incurred by reason of taxes assessed to such Person, or other loss, damage or expenses incurred by such Person, resulting from the fact that securities and other property of such Fund's Portfolios are registered in the name of such Person; provided however, that in no event shall such indemnification be applicable to income, franchise or similar taxes which may be imposed or assessed against any Person.