Permitted Delays definition
Examples of Permitted Delays in a sentence
Contractor shall not be entitled to any additional compensation for any Permitted Delays.
Contractor shall be excused for any delay in performance or completion of the Work caused by (1) acts of God, public utilities or public bodies, (2) the elements beyond average weather conditions for the region, (3) modifications requested by Owner, and (4) other matters Contractor could not reasonably anticipate, control or avoid ("Permitted Delays").
In the event that either party hereto shall be delayed or hindered in or prevented from the performance required hereunder by reason of strikes, lockouts, labor troubles, failure of power, riots, insurrection, war, acts of God, or other reasons of like nature not the fault of the party delayed in performing work or doing acts (hereinafter, "Permitted Delay" or "Permitted Delays"), such party shall be excused for the period of time equivalent to the delay caused by such Permitted Delay.
The Completion Date may be extended for a period of time, not to exceed sixty (60) days in the aggregate, equal to any period of Permitted Delays.
Sublessor and Sublessee hereby acknowledge and agree that the ninety (90) day periods referred to in the immediately preceding sentence shall not be extended by any Permitted Delay(s).
The Company shall commence construction of the Project not later than sixty (60) days following the successful procurement of all Required Permits and governmental approvals, which is preliminarily estimated to be August 31, 2022, but that date is a preliminary estimate and is subject to change due to Permitted Delays.
The preliminary estimated date for the New IDI Facility Completion Date is June 30, 2024, but that date is a preliminary estimate and is subject to Permitted Delays.
If Landlord fails to meet the Outside Commencement Date, other than because of the Permitted Delays, Tenant shall have the right to terminate this Lease upon giving Landlord written notice of termination at any time prior to its taking possession of the Premises.
Builder will make all reasonable efforts to substantially complete the Improvements within 365 calendar days from the date hereof (Projected Completion Date), subject to Permitted Delays (as defined below).
The Project shall be Substantially Completed by Developer in a good and workmanlike manner in accordance with the design approved by the City under this Contract no later than that date which is twelve (12) months after commencement of construction (the “Construction Completion Deadline”), subject to Permitted Delays.