Examples of Committed Work Programme in a sentence
The following LD shall be levied in case of unfinished Committed Work Programme during the Exploration Period as per Article 5.4 of MRSC.
The bidders are required to fulfil requisite Net Worth criteria commensurate to the value of their bid for the Committed Work Programme as specified, at the time of bidding.
One-time Bank Guarantee (“BG”) shall be applicable for the Committed Work Programme.
Predetermined Liquidated Damages (“LD”) have been specified for unfinished Committed Work Programme.
At this stage, Net Worth of the bidder should be equal to or more than the higher of:• Estimated expenditure for the Committed Work Programme; or• LD equivalent value of the Committed Work Programme.The Net Worth of the Bidder can be topped-up by a supporting Bank Guarantee in lieu of Net Worth, which can be utilized against any shortfall in Net Worth as required above.
The Contractor will be required to bid the Work Programme for the block and commit to carry out the Committed Work Programme within the timelines as mentioned above in Article 3 of the MRSC.
In the event that the Contractor fails to fulfill the said Committed Work Programme by the end of the Exploration Period, if any, or Contract is terminated in accordance with the Article 28, the Contractor shall pay to the Government an amount equivalent to Liquidated Damages as specified in Appendix I for the unfinished Committed Work Programme.
Bids not fulfilling these requirements will not be accepted.Computed value of Average NPV will be displayed to the bidders in e-Bidding portal at the time of bidding, the same value would be used for bid evaluation.Quote for Committed Work Programme and biddable share of Government Revenue shall not to be mentioned in hard copy submission.
In case the Contractor does not exercise this option within three months of receipt of the communication of reduction of area but proposes to exit from the Contract later, an LD will be levied to the extent of unfinished Committed Work Programme, proportional to the reduced area.
In case of swapping of 2D and 3D Acquisition, Processing and Interpretation data, the LD will be levied as per Committed Work Programme.