Examples of Colstrip Transmission System in a sentence
Avista does not own, lease, sublease, occupy, use or otherwise have any interest in, or (other than as provided in Section 24 of the Ownership and Operation Agreement) have any contractual or preferential rights with respect to the acquisition, occupancy or use of, any real property for or in connection with the Project other than (a) the Real Property or (b) the Colstrip Transmission System real property.
The Parties agree that, prior to Closing, they will cooperate with one another in good faith to identify and ensure the proper inclusion and transfer, at Closing, of all property, contracts, agreements, leases or other interests associated with Avista’s Colstrip Units 3&4 Interests and related common facilities, excluding property, contracts, agreements, leases or interests associated with the Colstrip Transmission System.
In the event Colstrip Transmission System – Transmission Service and Interconnection Processes and Procedures 6 sufficient transfer capability does not exist to accommodate the transmission service request and all available ATC of the Owner(s) has been requested, the Eligible Customer will be informed of the need to perform a System Impact Study.
TRANSMISSION-TO-TRANSMISSION INTERCONNECTION REQUESTS 6.1. Initiating an Interconnection Request A customer desiring to interconnect transmission to the Colstrip Transmission System shall submit a request for transmission-to-transmission interconnection (a “Transmission Interconnection Request”) to each Owner, utilizing the common application form, included as an attachment hereto.
Colstrip Transmission System – Transmission Service and Interconnection Processes and Procedures 7 4.5. Dispute Resolution If there is a dispute between an Eligible Customer and any Owner(s) relating to the System Impact Study or Facilities Study, the dispute resolution procedures set forth in NorthWestern Energy’s OATT shall apply, and all other Owners shall have the right to participate in the dispute resolution process.
Request Portal –Transmission Service Requests Segment [Insert] Start Date [Insert] End Date [Insert] AVA PGE PSE PAC NWE Total ATC (MW) Request (MW) from ATC [Insert] [Insert] [Insert] [Insert] [Insert] Additional Request (MW) [Insert] Total Allocation by Owner (MW) Segment Field: In the “SEGMENT” field, an Eligible Customer must select the desired POR and POD on the Colstrip Transmission System for its transmission service request from among the options available in the dropdown menu.
YES NO Offer service; Owner will update TSR status Owner receives a short-term TSR Short-Term Transmission Service Request Processing Flowchart Colstrip Transmission System – Transmission Service and Interconnection Processes and Procedures 4 4.4. Submission of a Transmission Service Request Using the Request Portal 4.4.1. Request Portal Access The Request Portal may be accessed through any Owner’s OASIS.
GENERATOR INTERCONNECTION REQUESTS 5.1. Large Generator Interconnections 5.1.1. Initiating an Interconnection Request An Interconnection Customer desiring to interconnect to the Colstrip Transmission System a generator with a Generating Facility Capacity of more than 20 MW shall submit a request to interconnect a large generator (“Interconnection Request”) to each Owner utilizing the common application form, included as an attachment hereto.
A form of the Small Generator Interconnection Agreement for the Colstrip Transmission System will be provided by the Owners in response to a small generator interconnection request.
Transmission Interconnection Requests shall be studied in order based on the date, by which the last Owner has received a Transmission Interconnection Request that Colstrip Transmission System – Transmission Service and Interconnection Processes and Procedures 12 is considered to be a valid request, and the customer has consented to the sharing of information related to the request with the other Owners, to the extent such consent is necessary.