Contractor Required to Continue Performance Sample Clauses

Contractor Required to Continue Performance. Pending the final determination of the Claim, including any judicial review or appeal process, and unless otherwise agreed upon in writing by County, Contractor shall proceed diligently with performance of the Contract and County shall continue to make payments in accordance with the Construction Documents.
AutoNDA by SimpleDocs
Contractor Required to Continue Performance. Pending the final determination of the Claim, including any judicial review or appeal process, and unless otherwise agreed upon in writing by the Director, the Contractor shall proceed diligently with performance of the Contractor’s Agreement and DFCM shall continue to make payments in accordance with the Contract Documents.
Contractor Required to Continue Performance. 7.7.8 Decision.
Contractor Required to Continue Performance. Pending the final resolution of the issue, unless otherwise agreed upon in writing by the Owner Representative, the Contractor shall proceed diligently with performance of the Contract and the Owner shall continue to make payments in accordance with the Contract Documents.
Contractor Required to Continue Performance. Pending the final resolution of the issue, unless otherwise agreed upon in writing by the DFCM Representative, the Contractor shall proceed diligently with performance of the Agreement and DFCM shall continue to make payments in accordance with the Contract Documents.

Related to Contractor Required to Continue Performance

  • OUTCOME IF GRANTEE CANNOT COMPLETE REQUIRED PERFORMANCE Unless otherwise specified in this Statement of Work, if Grantee cannot complete or otherwise comply with a requirement included in this Statement of Work, HHSC, at its sole discretion, may impose remedies or sanctions outlined under Contract Attachment C, Local Mental Health Authority Special Conditions, Section 7.09 (Remedies and Sanctions).

  • CONTRACTOR PERFORMANCE Agencies shall report any vendor failure to perform according to the requirements of this contract on Complaint to Vendor, form PUR 7017. Should the vendor fail to correct the problem within a prescribed period of time, then form PUR 7029, Request for Assistance, is to be filed with this office.

  • Excuse from Performance The Parties shall be excused from performing their respective obligations hereunder if they are prevented from so performing by reason of floods, earthquakes, other acts of nature, war, civil insurrection, riots, acts of any government (including judicial action), and other similar catastrophic events which are beyond the control of and not the fault of the Party claiming excuse from performance hereunder. Labor unrest, including but not limited to strike, work stoppage or slowdown, sick-out, picketing, or other concerted job action conducted by Contractor's employees or directed at Contractor is not an excuse from performance and Contractor shall be obligated to continue to provide service notwithstanding the occurrence of any or all of such events. The Party claiming excuse from performance shall, within two (2) Business Days after such Party has notice of such cause, give the other Party notice of the facts constituting such cause and asserting its claim to excuse under this Section. If either Party validly exercises its rights under this Section, the Parties hereby waive any claim against each other for any damages sustained thereby. The partial or complete interruption or discontinuance of Contractor's services caused by one or more of the events described in this Section shall not constitute a default by Contractor under this Agreement. Notwithstanding the foregoing, however, if Contractor is excused from performing its obligations hereunder for any of the causes listed in this Section for a period of thirty (30) calendar days or more, the SCWMA shall nevertheless have the right, in its sole discretion, to terminate this Agreement by giving ten (10) calendar days notice to Contractor unless Contractor has demonstrated, by the thirtieth (30th) calendar day, to the satisfaction of the SCWMA that the Contractor will resume services no later than the sixtieth (60th) day following the date service was interrupted or discontinued by Contractor.

  • Excuse for Nonperformance or Delayed Performance Except with respect to defaults of subcontractors, Contractor/Vendor shall not be in default by reason of any failure in performance of this contract in accordance with its terms (including any failure by Contractor/Vendor to make progress in the prosecution of the work hereunder which endangers such performance) if Contractor/Vendor has notified the Commission or designee within 15 days after the cause of the delay and the failure arises out of causes such as: acts of God; acts of the public enemy; acts of the State and any other governmental entity in its sovereign or contractual capacity; fires; floods; epidemics; quarantine restrictions; strikes or other labor disputes; freight embargoes; or unusually severe weather. If the failure to perform is caused by the failure of a subcontractor to perform or to make progress, and if such failure arises out of causes similar to those set forth above, Contractor/Vendor shall not be deemed to be in default, unless the services to be furnished by the subcontractor were reasonably obtainable from other sources in sufficient time to permit Contractor to meet the contract requirements. Upon request of Contractor, the Commission or designee shall ascertain the facts and extent of such failure, and, if such officer determines that any failure to perform was occasioned by any one or more of the excusable causes, and that, but for the excusable cause, Contractor’s progress and performance would have met the terms of the contract, the delivery schedule shall be revised accordingly, subject to the rights of the State under the clause entitled (in fixed-price contracts, “Termination for Convenience,” in cost-reimbursement contracts, “Termination”). (As used in this Paragraph of this clause, the term “subcontractor” means subcontractor at any tier).

  • Acceptance/Performance Test 4.7.1 Prior to synchronization of the Power Project, the SPD shall be required to get the Project certified for the requisite acceptance/performance test as may be laid down by Central Electricity Authority or an agency identified by the central government to carry out testing and certification for the solar power projects.

  • Service Performance All Services provided by the Agency shall be performed in a diligent, safe, courteous, and timely manner in accordance with this Contract and the Associated federal requirements.

  • Time for Performance 1.1. The term of this SOW Agreement shall begin on and end on (the “Initial Term”). The Initial Term may be extended as the parties may agree. The State may terminate this SOW for convenience upon thirty days prior written notice to the Contractor. If the Master Agreement should expire or otherwise terminate prior to the end of the term of this SOW Agreement, this SOW Agreement shall continue to the end of its existing term, unless or until terminated in accordance with the terms of this SOW Agreement, and the Parties acknowledge and agree that the terms of the Master Agreement shall survive and apply to this SOW Agreement.

  • CONTRACTOR PERFORMANCE AUDIT The Contractor shall allow the Authorized User to assess Contractor’s performance by providing any materials requested in the Authorized User Agreement (e.g., page load times, response times, uptime, and fail over time). The Authorized User may perform this Contractor performance audit with a third party at its discretion, at the Authorized User’s expense. The Contractor shall perform an independent audit of its Data Centers, at least annually, at Contractor expense. The Contractor will provide a data owner facing audit report upon request by the Authorized User. The Contractor shall identify any confidential, trade secret, or proprietary information in accordance with Appendix B, Section 9(a), Confidential/Trade Secret Materials.

  • Responsibility for Performance Participation in state Centralized Contracts by Authorized Users is permitted upon the following conditions: (i) the responsibility with regard to performance of any contractual obligation, covenant, condition or term thereunder by any Authorized User other than State Agencies shall be borne and is expressly assumed by such Authorized User and not by the State; (ii) a breach of the Contract by any particular Authorized User shall neither constitute nor be deemed a breach of the Contract as a whole which shall remain in full force and effect, and shall not affect the validity of the Contract nor the obligations of the Contractor thereunder respecting non-breaching Authorized Users, whether State or otherwise; (iii) for a breach by an Authorized User other than a State Agency, the State specifically and expressly disclaims any and all liability for such breach; and (iv) each non-state agency Authorized User and Contractor guarantees to save the State, its officers, agents and employees harmless from any liability that may be or is imposed by their failure to perform in accordance with its obligations under the Contract.

  • Monitoring of Contract Performance The Contractor shall comply with the monitoring arrangements set out in the Monitoring Schedule including, but not limited to, providing such data and information as the Contractor may be required to produce under the Contract.