Examples of Relevant Milestone in a sentence
The Company and the Trustee shall diligently progress the Works to enable each Construction Milestone to be achieved by the Relevant Milestone Date.
If a Construction Milestone has not been achieved by the Relevant Milestone Date, the Company, the Trustee and the State shall within 5 Business Days of the passing of that Relevant Milestone Date enter into discussions and consultation to achieve the purposes set out in paragraph (d).
Neither the Company nor the Trustee shall be in breach of this Deed or liable in damages to the State solely as a result of either a Construction Milestone not being achieved by the Relevant Milestone Date or a failure to observe paragraph (a).
Neither the Company nor the Trustee shall be in breach of this Deed or liable in damages to the State solely as a result of either a Construction Milestone not being achieved by the Relevant Milestone Date or a failure to observe paragraph (a).8.6 Requirements for Completion of a SectionSch.
An audit of all accounts of the school district shall be made annually by an independent public accountant selected by the Town of Brookfield Board of Finance and approved by the secretary of the Office of Policy and Management.
Relevant Milestone No.3: Verification of Equipment- Corresponds to the trial and / or testing of the high voltage equipment of the New Works, such as switches, insulators, power transformers, measurement transformers, high voltage insulated wire, among others, all of which must comply with the characteristics techniques and applicable standards.
Not later than the date established for compliance with the first Relevant Milestone, and regardless of whether the performance bond has been called in for this first milestone by the respective TA, the awardee must submit another performance bond in the same amount indicated in the previous paragraph, and valid for at least 60 days after the deadline established in the Gantt chart for the next Relevant Milestone of each project yet to be executed according to the project schedule.
No more than 30 days before completion of the first Relevant Milestone on the Gantt chart in the Technical Bid, the awardee shall deliver one or more insurance policies covering catastrophic risks throughout the project implementation stage and until all the works are commissioned.
The Company, in respect of the Company Road, and the Trustee, in respect of the Trust Road, shall advise the State and the Independent Reviewer at each Relevant Milestone Date whether or not the Construction Milestone has been achieved.
The presentation of the Guarantee for the Compliance of the First Relevant Milestone of the Work, indicated in numeral 4.1 of the Bases of Execution of New Works.